Add Cinder deadlines for Mitaka
Including the sates that are advertized here: http://lists.openstack.org/pipermail/openstack-dev/2015-November/078215.html Change-Id: Ia01cff9731f2e7fe808e16c5b7e747909771ff66
This commit is contained in:
parent
8a14fb2497
commit
c967f78ccf
@ -32,6 +32,10 @@
|
||||
| Jan 11-15 | R-12 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Jan 16-22 | R-11 | :ref:`m-2` | :ref:`m-nova-npff` |
|
||||
| | +---------------------------+-----------------------------+
|
||||
| | | | :ref:`m-cinder-nddeadline` |
|
||||
| | +---------------------------+-----------------------------+
|
||||
| | | | :ref:`m-cinder-spec-freeze` |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Jan 25-29 | R-10 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
@ -43,7 +47,7 @@
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Feb 22-26 | R-6 | :ref:`m-final-lib` | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Feb 29-4 | R-5 | :ref:`m-3` | |
|
||||
| Feb 29-4 | R-5 | :ref:`m-3` | :ref:`m-cinder-ff` |
|
||||
| | +---------------------------+-----------------------------+
|
||||
| | | :ref:`m-ff` | |
|
||||
| | +---------------------------+-----------------------------+
|
||||
@ -234,3 +238,32 @@ The deadline for non-priority feature code to be merged into master is
|
||||
21st January 2015.
|
||||
|
||||
Please note, the Feature Freeze for priority features is aligned with :ref:`m-ff`.
|
||||
|
||||
Cinder
|
||||
------
|
||||
|
||||
.. _m-cinder-nddeadline:
|
||||
|
||||
Cinder New Backend Driver Deadline
|
||||
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
The deadline for getting a new backend driver added to Cinder is 19th January
|
||||
2015. All review issues must be addressed and third party CI must be reporting
|
||||
and stable with enough time for reviewers prior to the deadline. Meeting these
|
||||
requirements on the 19th does not guarantee core reviewers will have enough
|
||||
time to merge the driver.
|
||||
|
||||
.. _m-cinder-spec-freeze:
|
||||
|
||||
Cinder Spec/Blueprint Freeze
|
||||
^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
All Cinder specs and blueprints must be approved by 19th January 2015.
|
||||
|
||||
.. _m-cinder-ff:
|
||||
|
||||
Cinder Feature Freeze
|
||||
^^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
The deadline for new features and driver functionality is 1st March 2016. Any
|
||||
changes past that date will be at the discretion of the core team.
|
||||
|