Merge "Move Cycle Highlights task to R-4"

This commit is contained in:
Zuul 2022-09-08 13:56:49 +00:00 committed by Gerrit Code Review
commit edc69a07fe
3 changed files with 8 additions and 7 deletions

View File

@ -178,8 +178,8 @@ The Antelope coordinated release will happen on Wednesday, 22 March, 2023.
Cycle Highlights Cycle Highlights
---------------- ----------------
Cycle highlights need to be added to the release deliverables by feature Cycle highlights need to be added to the release deliverables after the
freeze to be included in any marketing release messaging. feature freeze to be included in any marketing release messaging.
Highlights may be added after this point, but they will likely only be Highlights may be added after this point, but they will likely only be
useful for historical purposes. useful for historical purposes.

View File

@ -82,10 +82,11 @@ cycle:
- a-final-clientlib - a-final-clientlib
- a-soft-sf - a-soft-sf
- a-rf - a-rf
- a-cycle-highlights
- end: '2023-02-24' - end: '2023-02-24'
name: R-4 name: R-4
start: '2023-02-20' start: '2023-02-20'
x-project:
- a-cycle-highlights
- end: '2023-03-03' - end: '2023-03-03'
name: R-3 name: R-3
start: '2023-02-27' start: '2023-02-27'

View File

@ -869,10 +869,6 @@ R-5 week (Milestone-3)
#. Process any remaining library freeze exception. #. Process any remaining library freeze exception.
#. Early in the week, email openstack-discuss list to remind PTLs that
cycle-highlights are due this week so that they can be included in
release marketing preparations.
#. Propose autoreleases (``process_auto_releases``) for #. Propose autoreleases (``process_auto_releases``) for
``cycle-with-intermediary`` client libraries which had commits that have ``cycle-with-intermediary`` client libraries which had commits that have
not been included in a release. not been included in a release.
@ -1017,6 +1013,10 @@ R-4 week
#. Process any remaining client library freeze exception. #. Process any remaining client library freeze exception.
#. Early in the week, email openstack-discuss list to remind PTLs that
cycle-highlights are due this week so that they can be included in
release marketing preparations.
#. Freeze all cycle-based library releases except for release-critical #. Freeze all cycle-based library releases except for release-critical
bugs. Independently-released libraries may still be released, but bugs. Independently-released libraries may still be released, but
constraint or requirement changes will be held until after the freeze constraint or requirement changes will be held until after the freeze