Change-Id: Ic0700f2b2dd030e41b717ac6023ffa30d76f12a6
11 KiB
Stein Release Schedule
3 September 2018 - 8 April 2019 (32 weeks)
Note
With the exception of the final release date and cycle-trailing release date, deadlines are generally the Thursday of the week on which they are noted above. Exceptions to this policy will be explicitly mentioned in the event description.
Cross-project events
Stein TC Election
Stein TC Election Email Deadline
Contributors that will be in the electorate for the upcoming election should confirm their gerrit email addresses by this date (September 9th, 2018 at 00:00 UTC). Electorate rolls are generated after this date and ballots will be sent to the listed gerrit email address.
Stein TC Election Nomination Begins
Technical committee candidates interested in serving for the next calendar year should announce their candidacies and platforms during this week. Please see the Election site for specific timing information.
Stein TC Election Campaigning Begins
The electorate has time to ask candidates questions about their platforms and debate topics before polling begins. Please see the Election site for specific timing information.
Stein TC Election Polling Begins
Election polling week for open seats on the TC. Please see the Election site for specific timing information.
Train TC Election
Train Election Email Deadline
Contributors that will be in the electorate for the upcoming PTL and TC elections should confirm their gerrit email addresses by this date (February 19th, 2019 at 00:00 UTC). Electorate rolls are generated after this date and ballots will be sent to the listed gerrit email address.
Train TC Election Nomination Begins
Technical committee candidates interested in serving for the next calendar year should announce their candidacies and platforms during this week. Please see the Election site for specific timing information.
Train TC Election Campaigning Begins
The electorate has time to ask candidates questions about their platforms and debate topics before polling begins. Please see the Election site for specific timing information.
Train TC Election Polling Begins
Election polling week for open seats on the TC. Please see the Election site for specific timing information.
Keystone
Keystone Spec Proposal Freeze
All Keystone specs targeted to Stein must be submitted to the keystone-specs repository by the end of the week.
Keystone Spec Freeze
All Keystone specs targeted to Stein must be approved by the end of the week.
Keystone Feature Proposal Freeze
All new Keystone features must be proposed and substantially completed, with unit tests and documentation by the end of the week.
Keystone Feature Freeze
All new Keystone features must be merged by the end of the week.
Stein Goals Research
Pre-cycle planning and investigation into the community-wide goals for Stein.
Stein Project Team Gathering (PTG)
Project team gathering for the Stein cycle 10 - 14 September in Denver, Colorado, USA.
Stein-1 milestone
25 October 2018 is the Stein-1 milestone.
Stein Community Goals Acknowledgement
Teams should prepare their acknowledgement of the community-wide goals for Stein.
OpenStack Summit
The OpenStack Summit happens during this week in Berlin, Germany. It will include a "Forum" in which people from all parts of our community will gather to give feedback on the last release (Rocky) and discuss requirements for the next development cycle (Stein).
Stein-2 milestone
10 January 2019 is the Stein-2 milestone.
Final release for non-client libraries
Libraries that are not client libraries (Oslo and others) should issue their final release during this week. That allows to give time for last-minute changes before feature freeze.
Stein-3 milestone
7 March 2019 is the Stein-3 milestone.
Stein Community Goals Completed
Teams should prepare their documentation for completing the community-wide goals for Stein.
Feature freeze
The Stein-3 milestone marks feature freeze for projects following the release:cycle-with-rc model. No featureful patch should be landed after this point. Exceptions may be granted by the project PTL.
Requirements freeze
After the Stein-3 milestone, only critical requirements and constraints changes will be allowed. Freezing our requirements list gives packagers downstream an opportunity to catch up and prepare packages for everything necessary for distributions of the upcoming release. The requirements remain frozen until the stable branches are created, with the release candidates.
Final release for client libraries
Client libraries should issue their final release during this week, to match feature freeze.
Soft StringFreeze
You are no longer allowed to accept proposed changes containing modifications in user-facing strings. Such changes should be rejected by the review team and postponed until the next series development opens (which should happen when RC1 is published).
Membership Freeze
Projects made official after the second milestone, are not considered part of the release for the cycle. This does not apply to cycle-trailing packaging / lifecycle management projects.
RC1 target week
This week is the target for projects following the release:cycle-with-rc model to issue their first release candidate, with a deadline of 21 March 2019.
Hard StringFreeze
This happens when the RC1 for the project is tagged. At this point, ideally no strings are changed (or added, or removed), to give translator time to finish up their efforts.
Final RCs and intermediary releases
The week of 1 April 2019 is the last week to issue release candidates or intermediary releases before release week. During release week, only final-release-critical releases will be accepted (at the discretion of the release team).
Cycle highlights marketing deadline
Cycle highlights need to be added to the release deliverables by this point to be included in any marketing release messaging. Highlights may be added after this point, but they will likely only be useful for historical purposes.
See the project team guide for more details and instructions on adding these highlights.
Stein release
The Stein coordinated release will happen on 10 April 2019.
Stein cycle-trailing release deadline
The release deadline for projects using the release:cycle-trailing model that follow the main release cycle is set to 11 July, 2019.
Project-specific events
PTL Elections
Train PTL self-nomination
Project team lead candidates for the Stein cycle should announce their candidacy during this week. Refer to the Election Site for exact details.
Train PTL Election Polling Begins
Election week for Project team leads (where an election must be held to determine the winner). Refer to the Election Site for exact details.
Manila
Manila Spec Freeze
All Manila specs must be approved by 8 Nov 2018 (23:59 UTC).
Manila New Driver Submission Deadline
The deadline for submitting new backend drivers to to Manila is 10 Jan 2019 (23:59 UTC). New drivers must be substantially complete, with unit tests, and passing 3rd party CI by this date. Drivers do not need to be merged until the feature freeze date, but drivers that don't meet this deadline will not be considered at all for Rocky.
Manila Feature Proposal Freeze
All new Manila features must be proposed and substantially complete, with unit tests by 21 February 2019 (23:59 UTC).
Cinder
Cinder Spec Freeze
All Cinder Specs must be approved by 10 Jan 2019 (23:59 UTC).
Cinder New Driver Submission Deadline
The deadline for submitting new backend drivers to Cinder is 10 Jan 2019 (23:59 UTC). New drivers must be complete with unit tests at this point in time. The backend driver must also have a 3rd Party CI running reliably and the driver must be merged at this point to be included in the Stein release.
Cinder New Target Driver Submission Deadline
The deadline for submitting new target drivers to Cinder is 10 Jan 2019 (23:59 UTC). New target drivers must be complete with unit tests at this point in time. The target driver must also have a 3rd Party CI running reliably and the target driver must be merged at this point to be included in the Stein release.
Cinder Feature Proposal Freeze
All new Cinder features must be proposed and substantially complete with unit tests by 07 Mar 2019 (23:59 UTC).
Oslo
Oslo Feature Freeze
All new Oslo features must be proposed and substantially complete, with unit tests by the end of the week.