Release Processes
===================
This document describes the process and week-per-week steps related to
preparing the release. It should be adapted to take team holidays and
other commitments into account, and turned into a clear action plan for
the release cycle.
Week after previous release
===========================
#. Process any late or blocked release requests for deliverables
for any branch (treating the new series branch as stable).
#. Prepare for the next release cycle by adding deliverable files under the
next cycle's directory. Remove any deliverable files from the current cycle
that ended up not having any releases. Then run the following command to use
the current cycle deliverables to generate placeholders for the next cycle::
tox -e venv -- init-series $SERIES $NEXT_SERIES
#. Coordinate with the Infrastructure team to swap out the previous cycle
signing key and establish the new one for the startniog cycle.
#. Create the $series-relmgt-tracking etherpad using the
``make-tracking-etherpad`` command.
For example::
tox -e venv -- make-tracking-pad ussuri
The output from this command can be pasted into a
``$SERIES-relmgt-tracking`` etherpad. Set title formatting for the top
sections. Then highlight all listed weeks and set to **Heading 3** style.
Fill in the contents of one of the weeks with the typical items, then copy
and past that into each subsequent week to prepare for the rest of the
cycle.
#. Email PTLs directly one time to explain the use of the "[release][ptl]"
email tag on the openstack-discuss list and tell them to pay attention
to [release] countdown emails.
#. At the end of the week, send the following weekly email content::
Welcome back to the release countdown emails! These will be sent at
major points in the $SERIES development cycle, which should conclude
with a final release on $release-date.
Development Focus
-----------------
At this stage in the release cycle, focus should be on planning the
$SERIES development cycle, assessing $SERIES community goals and approving
$SERIES specs.
General Information
-------------------
$remark-on-series-length. In case you haven't seen it yet, please take
a look over the schedule for this release:
https://releases.openstack.org/$SERIES/schedule.html
By default, the team PTL is responsible for handling the release cycle
and approving release requests. This task can (and probably should) be
delegated to release liaisons. Now is a good time to review release
liaison information for your team and make sure it is up to date:
https://opendev.org/openstack/releases/src/branch/master/data/release_liaisons.yaml
By default, all your team deliverables from the Train release are
continued in $SERIES with a similar release model. If you intend to drop
a deliverable, or modify its release model, please do so before the
$SERIES-1 milestone by proposing a change to the deliverable file at:
https://opendev.org/openstack/releases/src/branch/master/deliverables/$SERIES
Upcoming Deadlines & Dates
--------------------------
$other-upcoming-event_
$SERIES-1 milestone: $milestone1
Week before milestone-1
=======================
#. Review cycle-trailing projects to check which haven't released yet.
Ask them to prepare their releases, if they haven't already. The list
of pending cycle-trailing deliverables can be determined by running
the command::
tox -e venv -- list-deliverables --series $LASTSERIES \
--model cycle-trailing --missing-final
#. At the end of the week, send the following weekly email content::
Development Focus
-----------------
The $SERIES-1 milestone is next week, on $milestone1! Project team plans
for the $SERIES cycle should now be solidified.
General Information
-------------------
If you planned to change the release model for any of your deliverables
this cycle, please remember to do so ASAP, before milestone-1.
Libraries need to be released at least once per milestone period. Next
week, the release team will propose releases for any library which had
changes but has not been otherwise released since the $LASTSERIES release.
PTL's or release liaisons, please watch for these and give a +1 to
acknowledge them. If there is some reason to hold off on a release, let
us know that as well, by posting a -1. If we do not hear anything at all
by the end of the week, we will assume things are OK to proceed.
NB: If one of your libraries is still releasing 0.x versions, start
thinking about when it will be appropriate to do a 1.0 version. The
version number does signal the state, real or perceived, of the library,
so we strongly encourage going to a full major version once things are
in a good and usable state.
Upcoming Deadlines & Dates
--------------------------
$SERIES-1 milestone: $milestone1
Milestone-1
===========
#. Propose autoreleases for cycle-with-intermediary libraries which
did not release since the previous release.
- List them using::
tox -e venv -- list-deliverables --unreleased \
--model cycle-with-intermediary --type client-library --type library
- Generate release requests for all cycle-with-intermediary libraries
which had changes, but did not release since the previous release.
That patch will be used as a base to communicate with the team: if
a team wants to wait for a specific patch to make it to the library,
someone from the team can -1 the patch to have it held, or update
that patch with a different commit SHA.
- Between Tuesday and Thursday, merge as soon as possible the patches that
get +1 from the PTL or the release liaison.
- On the Friday, merge patches that did not get any feedback from PTL or
release liaison. Discuss standing -1s to see if they should be granted
an exception and wait until next week.
#. To catch if there are acl issues in newly created repositories,
run tools/aclissues.py to detect potential leftovers in Gerrit ACLs
allowing official deliverables to be directly tagged or branched without
going through openstack/releases. You need to specify the location
of up-to-date checkouts for the governance and the project-config
repositories. For example::
tools/aclissues.py ../project-config ../governance
If the tool reports any violation, you can re-run it with ``--patch`` to
generate needed changes in ../project-config to align ACLs with governance,
and propose the changes for review.
#. At the end of the week, send the following weekly email content::
Development Focus
-----------------
We are now past the $SERIES-1 milestone. Teams should now be focused on
feature development and completion of release cycle goals [0].
[0] https://governance.openstack.org/tc/goals/selected/$SERIES/index.html
General Information
-------------------
Our next milestone in this development cycle will be $SERIES-2, on
$milestone2. This milestone is when we freeze the list of deliverables
that will be included in the $SERIES final release, so if you plan to
introduce new deliverables in this release, please propose a change to
add an empty deliverable file in the deliverables/$SERIES directory of
the openstack/releases repository.
Now is also generally a good time to look at bugfixes that were
introduced in the master branch that might make sense to be backported
and released in a stable release.
If you have any question around the OpenStack release process, feel free
to ask on this mailing-list or on the #openstack-release channel on IRC.
Upcoming Deadlines & Dates
--------------------------
$SERIES-2 Milestone: $milestone2
Week after milestone-1
======================
#. Review any remaining milestone-1 exceptions
Between Milestone-1 and Milestone-2
===================================
#. Send the following weekly email content::
Development Focus
-----------------
The $SERIES-2 milestone will happen in next month, on $milestone2.
$SERIES-related specs should now be finalized so that teams can move
to implementation ASAP. Some teams observe specific deadlines on
the second milestone (mostly spec freezes): please refer to
https://releases.openstack.org/$SERIES/schedule.html for details.
General Information
-------------------
Please remember that libraries need to be released at least once per
milestone period. At milestone 2, the release team will propose releases
for any library that has not been otherwise released since milestone 1.
Other non-library deliverables that follow the cycle-with-intermediary
release model should have an intermediary release before milestone-2.
Those who haven't will be proposed to switch to the cycle-with-rc model,
which is more suited to deliverables that are released only once per cycle.
At milestone-2 we also freeze the contents of the final release. If you
have a new deliverable that should be included in the final release, you
should make sure it has a deliverable file in:
https://opendev.org/openstack/releases/src/branch/master/deliverables/$series
You should request a beta release (or intermediary release) for those new
deliverables by milestone-2. We understand some may not be quite ready
for a full release yet, but if you have something minimally viable to
get released it would be good to do a 0.x release to exercise the release
tooling for your deliverables. See the MembershipFreeze description for
more details: https://releases.openstack.org/$SERIES/schedule.html#$S-mf
Finally, now may be a good time for teams to check on any stable
releases that need to be done for your deliverables. If you have
bugfixes that have been backported, but no stable release getting
those. If you are unsure what is out there committed but not released,
in the openstack/releases repo, running the command
"tools/list_stable_unreleased_changes.sh <cycle_name>" gives a nice report.
Upcoming Deadlines & Dates
--------------------------
$SERIES-2 Milestone: $milestone2
Week before Milestone-2
=======================
#. Ahead of MembershipFreeze, run ``membership_freeze_test`` to check for
any new deliverable in governance that has not been released yet::
tox -e membership_freeze_test -- $series ~/branches/governance/reference/projects.yaml
Those should either be tagged as a release management exception if they do
not need to be released (see ``release-management`` key in the governance
projects.yaml file) or an empty deliverable file should be added to the
series so that we can properly track it. Leftovers are considered too young
to be released in the next release and will be reconsidered at the next
cycle.
Milestone-2
===========
#. Generate a list of all cycle-with-intermediary libraries which did not
release since the YYYY-MM-DD date of milestone-1. For this, run::
tox -e venv -- list-deliverables --unreleased-since YYYY-MM-DD
--model cycle-with-intermediary --type client-library --type library
Generate release requests for all cycle-with-intermediary libraries
which had changes, but did not release since milestone-1.
That patch will be used as a base to communicate with the team:
if a team wants to wait for a specific patch to make it to the library,
someone from the team can -1 the patch to have it held, or update
that patch with a different commit SHA.
#. To catch if there are acl issues in newly created repositories,
run ``tools/aclissues.py`` to detect potential leftovers in Gerrit ACLs
allowing official deliverables to be directly tagged or branched without
going through openstack/releases. You need to specify the location
of up-to-date checkouts for the governance and the project-config
repositories. For example::
tools/aclissues.py ../project-config ../governance
If the tool reports any violation, you can re-run it with ``--patch`` to
generate needed changes in ../project-config to align ACLs with governance,
and propose the changes for review.
Between Milestone-2 and Milestone-3
===================================
#. Plan the next release cycle schedule based on the number of desired weeks or
by making sure the cycle ends within a few weeks of the next developer
event. Using the first Monday following the close of the last cycle, and the
Monday of the planned last week of the new cycle, use the tool
``tools/weeks.py`` to generate the release schedule YAML file. For example::
./tools/list_weeks.py t 2019-04-15 2019-10-16
The generated output can be used to set up the schedule similar to what was
done for the `Ussuri release <https://review.opendev.org/#/c/679822/>`_.
#. In the countdown email immediately after Milestone-2, include a
reminder about the various freezes that happen around Milestone-3.
Remind PTLs a heads up to start thinking about what they might want to
include in their deliverables file as cycle-highlights
and that feature freeze is the deadline for them.
#. Check with the election team about whether the countdown email
needs to include any updates about the election schedule.
#. Generate a list of intermediary-released service deliverables that have
not done a release in this cycle yet. For this, use::
tox -e venv -- list-deliverables --unreleased \
--model cycle-with-intermediary \
--type horizon-plugin --type other --type service
Intermediary-released deliverables that did release only once during
the last cycle, and have not done a release yet are good candidates to
switch to the cycle-with-rc model, which is much more suitable for
deliverables that are only released once per cycle.
Propose a release model change for all deliverables meeting that criteria.
PTLs and release liaisons may decide to:
- immediately release an intermediary release (and -1 the proposed change)
- confirm the release model change (+1 the proposed change)
- stay uncertain for this cycle of how many releases will be made, but
acknowledge that they need to do a release before RC1 (-1 the proposed
change)
#. Two weeks before Milestone-3, include a reminder about the final
library release freeze coming the week before Milestone-3.
#. Run the following command to get a list of libraries::
tools/list_library_unreleased_changes.sh
#. Include list of unreleased libraries in the email to increase visibility.
#. One week before Milestone-3, include a reminder about the final
client library release freeze coming the week of Milestone-3.
#. Run the following command to get a list of client libraries::
tools/list_client_library_unreleased_changes.sh
#. Include list of unreleased client libraries in the email to increase
visibility.
#. Two weeks before Milestone-3, prepare other teams to the final release
rush.
#. Ask the release liaisons for the affected teams to audit the
contents of their ``$project-stable-maint`` groups, as that group
will control the ``stable/$series`` branch prior to release. They
should reach out to the ``stable-maint-core`` group for additions.
#. Include a reminder about the stable branch ACLs in the countdown email.
#. Notify the Infrastructure team to `generate an artifact signing key`_
(but not replace the current one yet), and
begin the attestation process.
.. _generate an artifact signing key: https://docs.openstack.org/infra/system-config/signing.html#generation
#. Include a reminder in the weekly countdown email reminding PTLs of the
feature freeze deadline for cycle-highlights.
R-6 week (Final Library Release deadline)
=========================================
#. Propose autoreleases for cycle-with-intermediary libraries (excluding
client libraries) which had commits that have not been included in a
release.
- List them using::
./tools/list_library_unrelease_changes.sh
- That patch will be used as a base to communicate with the
team: if a team wants to wait for a specific patch to make it to the
library, someone from the team can -1 the patch to have it held, or update
that patch with a different commit SHA.
.. note::
At this point, we want *all* changes in the deliverables, to ensure
that we have CI configuration up to date when the stable branch
is created later.
- Allow the ``stable/$series`` branch to be requested with each library
final release if they know they are ready. Do not require branching at
this point in case of critical issues requiring another approved release
past the freeze date.
- Between Tuesday and Thursday, merge as soon as possible the patches that
get +1 from the PTL or the release liaison.
- On the Friday, merge patches that did not get any feedback from PTL or
release liaison. Discuss standing -1s to see if they should be granted
an exception and wait until next week.
#. Update the feature list and allowed stable branch names in
devstack-gate for the new stable branch. For
example, https://review.opendev.org/362435 and
https://review.opendev.org/363084
#. At the end of the week, send weekly email content preparing for R-5 week::
Development Focus
-----------------
We are getting close to the end of the $series cycle! Next week on
$milestone3 is the $series-3 milestone, also known as feature freeze.
It's time to wrap up feature work in the services and their client
libraries, and defer features that won't make it to the $next-series cycle.
General Information
-------------------
This coming week is the deadline for client libraries: their last feature
release needs to happen before "Client library freeze" on $milestone3.
Only bugfix releases will be allowed beyond this point.
When requesting those library releases, you can also include the
stable/$series branching request with the review. As an example, see the
"branches" section here:
https://opendev.org/openstack/releases/src/branch/master/deliverables/pike/os-brick.yaml#n2
$milestone3 is also the deadline for feature work in all OpenStack
deliverables following the cycle-with-rc model. To help those projects
produce a first release candidate in time, only bugfixes should be allowed
in the master branch beyond this point. Any feature work past that deadline
has to be raised as a Featur Freeze Exception (FFE) and approved by the
team PTL.
Finally, feature freeze is also the deadline for submitting a first version
of your cycle-highlights. Cycle highlights are the raw data hat helps shape
what is communicated in press releases and other release activity at the
end of the cycle, avoiding direct contacts from marketing folks. See
https://docs.openstack.org/project-team-guide/release-management.html#cycle-highlights
for more details.
Upcoming Deadlines & Dates
--------------------------
$series-3 milestone (feature freeze): $milestone3 (R-5 week)
RC1 deadline: $rc1-deadline (R-3 week)
Final RC deadline: $final-rc-deadline (R-1 week)
Final Train release: $release-date
$other-upcoming-event
R-5 week (Milestone-3)
======================
#. Process any remaining library freeze exception.
#. Early in the week, email openstack-discuss list to remind PTLs that
cycle-highlights are due this week so that they can be included in
release marketing preparations.
#. Propose autoreleases for cycle-with-intermediary client libraries which
had commits that have not been included in a release.
- List them using::
./tools/list_client_library_unreleased_changes.sh
- That patch will be used as a base
to communicate with the team: if a team wants to wait for a specific patch
to make it to the library, someone from the team can -1 the patch to have
it held, or update that patch with a different commit SHA.
- Allow the ``stable/$series`` branch to be requested with each client
library final release if they know they are ready. Do not require
branching at this point in case of critical issues requiring another
approved release past the freeze date.
- Between Tuesday and Thursday, merge as soon as possible the patches that
get +1 from the PTL or the release liaison.
- On the Friday, merge patches that did not get any feedback from PTL or
release liaison. Discuss standing -1s to see if they should be granted
an exception and wait until next week.
#. Evaluate any libraries that did not have any change merged over the
cycle to see if it is time to `transition them to the independent release
model <https://releases.openstack.org/reference/release_models.html#openstack-related-libraries>`__.
If it is OK to transition them, propose to move the deliverable file to
the ``_independent`` directory.
If it is not OK to transition them, create a new stable branch from the
latest release from the previous series.
#. List cycle-with-intermediary deliverables that have not been released yet::
tox -e venv -- list-deliverables --unreleased \
--model cycle-with-intermediary \
--type horizon-plugin --type other --type service
Send a separate email targeted to teams with such unreleased deliverables
saying::
Quick reminder that we'll need a release very soon for a number of
deliverables following a cycle-with-intermediary release model but which
have not done *any* release yet in the $series cycle:
{{list-of-deliverables}}
Those should be released ASAP, and in all cases before $rc1-deadline, so
that we have a release to include in the final $series release.
#. On Friday, remind the requirements team to freeze changes to
``openstack/requirements`` by applying -2 to all
open patches. Ensure that reviewers do not approve changes created
by the proposal bot, but do approve changes for new OpenStack deliverable
releases.
#. At the end of the week, send weekly email content for R-3 week::
Development Focus
-----------------
We just passed feature freeze! Until release branches are cut, you
should stop accepting featureful changes to deliverables following the
cycle-with-rc release model, or to libraries. Exceptions should be
discussed on separate threads on the mailing-list, and feature freeze
exceptions approved by the team's PTL.
Focus should be on finding and fixing release-critical bugs, so that
release candidates and final versions of the $series deliverables can be
proposed, well ahead of the final $series release date.
General Information
-------------------
We are still finishing up processing a few release requests, but the
$series release requirements are now frozen. If new library releases are
needed to fix release-critical bugs in $series, you must request a
Requirements Freeze Exception (RFE) from the requirements team before we
can do a new release to avoid having something released in $series that
is not actually usable. This is done by posting to the openstack-discuss
mailing list with a subject line similar to:
[$PROJECT][requirements] RFE requested for $PROJECT_LIB
Include justification/reasoning for why a RFE is needed for this lib.
If/when the requirements team OKs the post-freeze update, we can then
process a new release.
A soft String freeze is now in effect, in order to let the I18N team do the
translation work in good conditions. In Horizon and the various dashboard
plugins, you should stop accepting changes that modify user-visible
strings. Exceptions should be discussed on the mailing-list. By
$rc-final-date this will become a hard string freeze, with no changes
in user-visible strings allowed.
Actions
-------
stable/$series branches should be created soon for all not-already-branched
libraries. You should expect 2-3 changes to be proposed for each: a
.gitreview update, a reno update (skipped for projects not using reno),
and a tox.ini constraints URL update. Please review those in priority
so that the branch can be functional ASAP.
The Prelude section of reno release notes is rendered as the top level
overview for the release. Any important overall messaging for $series
changes should be added there to make sure the consumers of your release
notes see them.
Finally, if you haven't proposed $series cycle-highlights yet, you are
already late to the party. Please see $email for details.
Upcoming Deadlines & Dates
--------------------------
RC1 deadline: $rc1-deadline (R-3 week)
Final RC deadline: $final-rc-deadline (R-1 week)
Final Train release: $release-date
$other-upcoming-event
R-4 week
========
#. Process any remaining client library freeze exception.
#. Freeze all cycle-based library releases except for release-critical
bugs. Independently-released libraries may still be released, but
constraint or requirement changes will be held until after the freeze
period.
.. note::
Do not release libraries without a link to a message to openstack-discuss
requesting a requirements RFE and an approval response from that team.
#. Propose ``stable/$series`` branch creation for all client and non-client
libraries that had not requested it at freeze time.
- The following command may be used::
tox -e venv -- propose-library-branches --include-clients
- That patch will be used as a base
to communicate with the team: if a team wants to wait for a specific patch
to make it to the library, someone from the team can -1 the patch to have
it held, or update that patch with a different commit SHA.
- On the Friday, merge patches that did not get any feedback from PTL or
release liaison. Discuss standing -1s to see if they should be granted
an exception and wait until next week.
#. List cycle-with-intermediary deliverables that have not been refreshed in
the last 2 months. For this, use the following command, with YYYY-MM-DD
being the day two months ago::
tox -e venv -- list-deliverables --unreleased-since YYYY-MM-DD
--model cycle-with-intermediary \
--type horizon-plugin --type other --type service
Send a separate email targeted to teams with such old deliverables
saying::
Quick reminder that for deliverables following the cycle-with-intermediary
model, the release team will use the latest $series release available on
release week.
The following deliverables have done a $series release, but it was not
refreshed in the last two months:
{{list_of_deliverables}}
You should consider making a new one very soon, so that we don't use an
outdated version for the final release.
#. At the end of the week, send weekly email content preparing for R-3 week::
Development Focus
-----------------
The Release Candidate (RC) deadline is next Thursday, $rc1-deadline. Work
should be focused on fixing any release-critical bugs.
General Information
-------------------
All deliverables released under a cycle-with-rc model should have a first
release candidate by the end of the week, from which a stable/$series
branch will be cut. This branch will track the $series release.
Once stable/$series has been created, master will will be ready to switch
to $next-series development. While master will no longer be feature-frozen,
please prioritize any work necessary for completing $series plans.
Release-critical bugfixes will need to be merged in the master branch
first, then backported to the stable/$series branch before a new release
candidate can be proposed.
Actions
-------
Early in the week, the release team will be proposing RC1 patches for all
cycle-with-rc projects, using the latest commit from master. If your team
is ready to go for cutting RC1, please let us know by leaving a +1 on these
patches.
If there are still a few more patches needed before RC1, you can -1 the
patch and update it later in the week with the new commit hash you would
like to use. Remember, stable/$series branches will be created with this,
so you will want to make sure you have what you need included to avoid
needing to backport changes from master (which will technically then be
$next-series) to this stable branch for any additional RCs before the final
release.
The release team will also be proposing releases for any deliverable
following a cycle-with-intermediary model that has not produced any $series
release so far.
Finally, now is a good time to finalize release highlights. Release
highlights help shape the messaging around the release and make sure that
your work is properly represented.
Upcoming Deadlines & Dates
--------------------------
RC1 deadline: $rc1-deadline (R-3 week)
Final RC deadline: $final-rc-deadline (R-1 week)
Final Train release: $release-date
$other-upcoming-event
R-3 week (RC1 deadline)
=======================
#. Process any remaining library branching exception.
#. On the Monday, generate release requests for all deliverables
that have do not have a suitable Train candidate yet. That includes:
- Using `release-test` as a canary test. `release-test`
needs to have a RC1 anyway for preparing the final release.
- cycle-with-intermediary deliverables that have not released yet, for
which a release should be proposed from HEAD, and include stable branch
creation. You can list those using::
tox -e venv -- list-deliverables --unreleased \
--model cycle-with-intermediary \
--type horizon-plugin --type other --type service
- cycle-with-rc deliverables that have not done a RC1 yet, for which
a release should be proposed from HEAD, and include stable branch
creation. You can list those using::
tox -e venv -- list-deliverables --missing-rc --model cycle-with-rc
- cycle-automatic deliverables, for which a final release should be
proposed from HEAD (unless there is an existing release in the cycle
and no change was merged since). Those should **not** include stable
branch creation. You can list those using::
tox -e venv -- list-deliverables --model cycle-automatic
- Those patches will be used as a base to communicate with the team:
if a team wants to wait for a specific patch to make it to the release,
someone from the team can -1 the patch to have it held, or update
that patch with a different commit SHA.
- Between Tuesday and Thursday, merge as soon as possible the patches that
get +1 from the PTL or the release liaison.
- By EOD Thursday, ideally we would want a +1 from the PTL and/or
release liaison to indicate approval. However we will consider the
absence of -1 or otherwise negative feedback as an indicator that the
automatically proposed patches can be approved.
- On the Friday, merge patches that did not get any feedback from PTL or
release liaison. Discuss standing -1s to see if they should be granted
an exception and wait until next week.
#. At the end of the week, send weekly email content preparing for R-2 week::
Development Focus
-----------------
At this point we should have release candidates (RC1 or recent intermediary
release) for all the $series deliverables. Teams should be working on any
release-critical bugs that would require another RC or intermediary release
before the final release.
Actions
-------
Early in the week, the release team will be proposing stable/$series branch
creation for all deliverables that have not branched yet, using the latest
available $series release as the branch point. If your team is ready to go
for creating that branch, please let us know by leaving a +1 on these
patches.
If you would like to wait for another release before branching, you can -1
the patch and update it later in the week with the new release you would
like to use. By the end of the week the release team will merge those
patches though, unless an exception is granted.
Once stable/$series branches are created, if a release-critical bug is
detected, you will need to fix the issue in the master branch first, then
backport the fix to the stable/$series branch before releasing out of the
stable/$series branch.
After all of the cycle-with-rc projects have branched we will branch
devstack, grenade, and the requirements repos. This will effectively open
them up for $next-series development, though the focus should still be on
finishing up $series until the final release.
For projects with translations, watch for any translation patches coming
through and merge them quickly. A new release should be produced so that
translations are included in the final $series release.
Finally, now is a good time to finalize release notes. In particular,
consider adding any relevant "prelude" content. Release notes are
targetted for the downstream consumers of your project, so it would be
great to include any useful information for those that are going to pick
up and use or deploy the $series version of your project.
Upcoming Deadlines & Dates
--------------------------
Final RC deadline: $final-rc-deadline (R-1 week)
Final Train release: $release-date
$other-upcoming-event
R-2 week
========
#. Process any standing RC1 deadline exceptions.
#. On the Monday, generate stable branches for all cycle deliverables that
are still missing one.
- You can list those using::
tox -e venv -- list-deliverables --no-stable-branch
- Those patches will be used as a base to communicate with the team:
if a team wants to wait and make another release before the branch is
cut, someone from the team can -1 the patch to have it held, or update
that patch to include another release and stable branch point.
- Between Tuesday and Thursday, merge as soon as possible the patches that
get +1 from the PTL or the release liaison.
- On the Friday, merge patches that did not get any feedback from PTL or
release liaison. Discuss standing -1s to see if they should be granted
an exception and wait until next week.
#. After all the projects enabled in devstack by default have been branched,
we can engage with the QA, I18n and Requirements PTLs to finalize the
stable branch setup:
- Remind the QA PTL to create a branch in the devstack repository.
Devstack doesn't push a tag at RC1 it is just branched off of HEAD.
- After devstack is branched, remind the QA PTL to create a branch in the
grenade repository. As with devstack, it will branch from HEAD instead
of a tag.
- Remind the QA PTL to update the default branch for devstack in the new
stable branch. For example, https://review.opendev.org/#/c/493208/
- Remind the QA PTL to update the grenade settings in devstack-gate for the
new branch. For example, https://review.opendev.org/362438.
.. note::
As soon as grenade is updated for the new branch (see the RC1
instructions that follow), projects without stable branches may
start seeing issues with their grenade jobs because without the
stable branch the branch selection will cause the jobs to run
master->master instead of previous->master. At the end of Ocata
this caused trouble for the Ironic team, for example.
- Remind the I18n PTL to update the translation tools for the new stable
series.
- After all cycle-with-rc projects have their branches created, remind the
requirements PTL to propose an update to the deliverable file to create
the ``stable/$series`` branch for ``openstack/requirements``. Then
announce that the requirements freeze is lifted from master.
.. note::
We wait until after the other projects have branched to
create the branch for requirements because tests for the stable
branches of those projects will fall back to using the master
branch of requirements until the same stable branch is created,
but if the branch for the requirements repo exists early the
changes happening in master on the other projects will not use it
and we can have divergence between the requirements being tested
and being declared as correct.
- Remind the QA PTL to create new branch specific jobs for our two
branchless projects, devstack-gate and tempest, in the tempest repo.
Configure tempest to run them on all changes, voting. Configure tempest
to run them as periodic bitrot jobs as well. All this can be done in one
tempest patch, for example, see https://review.opendev.org/521888.
Configure devstack-gate to run the new jobs in check pipeline only,
non-voting, for example see https://review.opendev.org/545144.
- Remind the QA PTL to add the new branch to the list of branches in the
periodic-stable job templates in openstack-zuul-jobs. For example, see
https://review.opendev.org/545268/.
#. Ensure that all projects that are publishing release notes have the
notes link included in their deliverable file. See
tools/add_release_note_links.sh.
#. Let cycle-with-rc projects iterate on RCs as needed. The final release
candidate for each project needs to be prepared at least one week before
the final release date.
.. note::
Try to avoid creating more than 3 release candidates so we are not
creating candidates that consumers are then trained to ignore. Each
release candidate should be kept for at least 1 day, so if there is a
proposal to create RCx but clearly a reason to create another one,
delay RCX to include the additional patches. Teams that know they will
need additional release candidates can submit the requests and mark
them WIP until actually ready, so the release team knows that more
candidates are coming.
#. At the end of the week, send weekly email content preparing for R-1 week::
Development Focus
-----------------
We are on the final mile of the $series development cycle!
Remember that the $series final release will include the latest release
candidate (for cycle-with-rc deliverables) or the latest intermediary
release (for cycle-with-intermediary deliverables) available.
$final-rc-deadline is the deadline for final $series release candidates
as well as any last cycle-with-intermediary deliverables. We will then
enter a quiet period until we tag the final release on $release-date.
Teams should be prioritizing fixing release-critical bugs, before that
deadline.
Otherwise it's time to start planning the $next-series development cycle,
including discussing Forum and PTG sessions content, in preparation of
$other-upcoming-event.
Actions
-------
Watch for any translation patches coming through on the stable/$series
branch and merge them quickly. If you discover a release-critical issue,
please make sure to fix it on the master branch first, then backport the
bugfix to the stable/$series branch before triggering a new release.
Please drop by #openstack-release with any questions or concerns about
the upcoming release !
Upcoming Deadlines & Dates
--------------------------
Final Train release: $release-date
$other-upcoming-event
R-1 week (Final RC deadline)
============================
#. Process any remaining stable branching exception.
#. Notify the documentation team that it should be safe to apply
their process to create the new release series landing pages for
docs.openstack.org. Their process works better if they wait until
most of the projects have their stable branches created, but they
can do the work before the final release date to avoid having to
synchronize with the release team on that day.
#. Test the release process using the ``openstack/release-test``
repository to ensure our machinery is functional.
#. On the day before the deadline for final release candidates,
propose last-minute RCs where needed:
- Check the list of unreleased changes for cycle-with-rc projects, by
running the following command in the releases repo working directory::
$ ./tools/list_rc_updates.sh
- Propose patches creating a new RC for those that have unreleased
bugfixes or updated translations
- Patches that get a +1 from PTL or release liaison should be approved.
A -1 will mean that the PTL prefers to wait for a post-release stable
update. Patches that get no feedback by the deadline should be abandoned.
#. At the end of the week, send weekly email content preparing for R-0 week::
Development Focus
-----------------
We will be releasing the coordinated OpenStack $series release next week,
on $release-date. Thanks to everyone involved in the $series cycle!
We are now in pre-release freeze, so no new deliverable will be created
until final release, unless a release-critical regression is spotted.
Otherwise, teams attending the PTG in $ptg-location should start to plan
what they will be discussing there, by creating and filling team etherpads.
You can access the list of PTG etherpads at:
http://ptg.openstack.org/etherpads.html
General Information
-------------------
On release day, the release team will produce final versions of
deliverables following the cycle-with-rc release model, by re-tagging
the commit used for the last RC.
A patch doing just that will be proposed. PTLs and release liaisons should
watch for that final release patch from the release team. While not
required, we would appreciate having an ack from each team before we
approve it on the 16th, so that their approval is included in the metadata
that goes onto the signed tag.
Upcoming Deadlines & Dates
--------------------------
Final Train release: $release-date
$other-upcoming-event
#. After the email is sent, use ``propose-final-releases`` to tag the
existing most recent release candidates as the final release for
projects using the cycle-with-rc model.
R+0 week (Final Release)
========================
#. We are in pre-release freeze. Only release-critical regressions, or
legal compliance issues, or bugs making it otherwise impossible to install
and use the software on release day, should be considered by the release
management team for a pre-release freeze exception. If approved,
release freeze exceptions should trigger the production of a new RC (or
cycle-with-intermediary release) and (if needed) a regeneration of the
final release patch.
#. On release day, approve the final release patch created earlier.
.. note::
This needs to happen several hours before the press release
from the foundation (to give us time to handle failures) but not
too far in advance (to avoid releasing the day before the press
release).
#. Once the final patch is proceesed, run the ``missing-releases`` script
to check for missing tarballs on the release page before the announcement::
tox -e venv -- missing-releases --series $SERIES
If there are any missing deliverables, fix them.
#. Mark series as released on releases.o.o, by updating doc/source/index.rst
and doc/source/$series/index.rst.
See https://review.opendev.org/#/c/381006 for an example.
.. note::
This item can be staged as a patch on top of the final release patch.
#. Update the default series name in
``openstack/releases/openstack_releases/defaults.py`` to use the
new series name.
.. note::
This item can be staged as a patch on top of the previous patch.
Only workflow when previous step *fully* ready
#. Send release announcement email to
``openstack-announce@lists.openstack.org``, based on
``templates/final.txt``. Coordinate the timing of the email with
the press release from the Foundation staff.
#. Send an email to the openstack-discuss list to point to the official
release announcement from the previous step, and declare
``openstack/releases`` unfrozen for releases on the new series.