As part of the "neutral governance website" effort, TC-related governance content is moved under governance.openstack.org/tc. While those links are preserved through redirects, it doesn't hurt to give the right examples (and avoid redirection) wherever we can. Change-Id: I85160e0c9bdf3d1f3fbf372162415e80dfc41187
220 lines
5.5 KiB
ReStructuredText
220 lines
5.5 KiB
ReStructuredText
========================
|
|
Pike Release Schedule
|
|
========================
|
|
|
|
.. note::
|
|
|
|
All deadlines are generally the Thursday of the week on which they
|
|
are noted above. For example, the Feature Freeze in week XXX is on
|
|
XXX. Exceptions to this policy will be explicitly mentioned
|
|
in the event description.
|
|
|
|
Cross-project events
|
|
====================
|
|
|
|
.. _p-goals-research:
|
|
|
|
Pike Goals Research
|
|
--------------------
|
|
|
|
Pre-cycle planning and investigation into `the community-wide goals
|
|
for Pike <https://governance.openstack.org/tc/goals/pike/index.html>`__.
|
|
|
|
.. _p-design-summit:
|
|
|
|
Pike Design Summit
|
|
------------------
|
|
|
|
TBD
|
|
|
|
.. _p-ptg:
|
|
|
|
Pike Project Team Gathering (PTG)
|
|
---------------------------------
|
|
|
|
TBD
|
|
|
|
.. _p-1:
|
|
|
|
Pike-1 milestone
|
|
----------------
|
|
|
|
XXX is the Pike-1 milestone window for projects following the
|
|
`release:cycle-with-milestones`_ model.
|
|
|
|
.. _release:cycle-with-milestones: https://governance.openstack.org/tc/reference/tags/release_cycle-with-milestones.html
|
|
|
|
.. _p-2:
|
|
|
|
Pike-2 milestone
|
|
----------------
|
|
|
|
XXX is the Pike-2 milestone window for projects following the
|
|
`release:cycle-with-milestones`_ model.
|
|
|
|
.. _p-final-lib:
|
|
|
|
Final release for non-client libraries
|
|
--------------------------------------
|
|
|
|
Libraries that are not client libraries (Oslo and others) should issue their
|
|
final release during this week. That allows to give time for last-minute
|
|
changes before feature freeze.
|
|
|
|
.. _p-3:
|
|
|
|
Pike-3 milestone
|
|
----------------
|
|
|
|
XXX is the Pike-3 milestone window for projects following the
|
|
`release:cycle-with-milestones`_ model.
|
|
|
|
.. _p-extra-atcs:
|
|
|
|
Extra-ATCs deadline
|
|
-------------------
|
|
|
|
Project teams should identify contributors who have had a significant
|
|
impact this cycle but who would not qualify for ATC status using the
|
|
regular process because they have not submitted a patch. Those names
|
|
should be added to the governance repo for consideration as ATC for
|
|
the future.
|
|
|
|
Although extra ATCs can be nominated at any point, there is a deadline
|
|
to be included in electorate for the next release cycle. The ATC list
|
|
needs to be approved by the TC by (TBD), and in order to appear on the
|
|
TC agenda to be discussed, the proposals need to be submitted to the
|
|
``openstack/governance`` repository by (TBD).
|
|
|
|
.. _p-ff:
|
|
|
|
Feature freeze
|
|
--------------
|
|
|
|
The Pike-3 milestone marks feature freeze for projects following the
|
|
`release:cycle-with-milestones`_ model. No featureful patch should be landed
|
|
after this point. Exceptions may be granted by the project PTL.
|
|
|
|
.. _p-rf:
|
|
|
|
Requirements freeze
|
|
-------------------
|
|
|
|
After the Pike-3 milestone, only critical requirements and
|
|
constraints changes will be allowed. Freezing our requirements list
|
|
gives packagers downstream an opportunity to catch up and prepare
|
|
packages for everything necessary for distributions of the upcoming
|
|
release. The requirements remain frozen until the stable branches are
|
|
created, with the release candidates.
|
|
|
|
.. _p-final-clientlib:
|
|
|
|
Final release for client libraries
|
|
----------------------------------
|
|
|
|
Client libraries should issue their final release during this week, to
|
|
match feature freeze.
|
|
|
|
.. _p-soft-sf:
|
|
|
|
Soft StringFreeze
|
|
-----------------
|
|
|
|
You are no longer allowed to accept proposed changes containing
|
|
modifications in user-facing strings. Such changes should be rejected
|
|
by the review team and postponed until the next series development
|
|
opens (which should happen when RC1 is published).
|
|
|
|
.. _p-mf:
|
|
|
|
Membership Freeze
|
|
-----------------
|
|
|
|
Projects must participate in at least two milestones in order to be
|
|
considered part of the release. Projects made official after the
|
|
second milestone, or which fail to produce milestone releases for at
|
|
least one of the first and second milestones as well as the third
|
|
milestone, are therefore not considered part of the release for the
|
|
cycle.
|
|
|
|
.. _p-rc1:
|
|
|
|
RC1 target week
|
|
---------------
|
|
|
|
The week of XXX - XXX is the target date for projects
|
|
following the `release:cycle-with-milestones`_ model to issue their
|
|
first release candidate, with a deadline of XXX.
|
|
|
|
.. _p-hard-sf:
|
|
|
|
Hard StringFreeze
|
|
-----------------
|
|
|
|
This happens when the RC1 for the project is tagged. At this point, ideally
|
|
no strings are changed (or added, or removed), to give translator time to
|
|
finish up their efforts.
|
|
|
|
.. _p-finalrc:
|
|
|
|
Final RCs and intermediary releases
|
|
-----------------------------------
|
|
|
|
The week of XXX is the last week to issue release candidates or
|
|
intermediary releases before release week. During release week, only
|
|
final-release-critical releases will be accepted (at the discretion of
|
|
the release team).
|
|
|
|
.. _p-release:
|
|
|
|
Pike release
|
|
------------
|
|
|
|
The Pike coordinated release will happen on XXX.
|
|
|
|
.. _p-trailing:
|
|
|
|
Pike cycle-trailing Deadline
|
|
----------------------------
|
|
|
|
The deadline for projects using the release:cycle-trailing model that
|
|
follow the main release cycle.
|
|
|
|
Project-specific events
|
|
=======================
|
|
|
|
Elections
|
|
---------
|
|
|
|
.. _q-ptl-nomination:
|
|
|
|
Queens PTLs self-nomination
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
Project team lead candidates for the Pike cycle should announce their
|
|
candidacy during this week.
|
|
|
|
.. _q-ptl-election:
|
|
|
|
Queens cycle PTLs election
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
Election week for Project team leads (where an election must be held to
|
|
determine the winner).
|
|
|
|
.. _q-tc-nomination:
|
|
|
|
TC member self-nomination
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
Candidates for the partial Technical Committee member renewal should announce
|
|
their candidacy during this week.
|
|
|
|
.. _q-tc-election:
|
|
|
|
TC member election
|
|
^^^^^^^^^^^^^^^^^^
|
|
|
|
Election for partially renewing Technical Committee members will happen
|
|
during this week.
|