This is a proposed release schedule for OpenStack 2024.2 Dalmatian. 26 weeks long cycle, with 2 October, 2024 as planned release date. Change-Id: I8bf5d0ade01a81b1cfd340dce42e31d74a999a96
6.1 KiB
2024.2 Dalmatian Release Schedule
Note
Deadlines are generally the Thursday of the week on which they are noted below. Exceptions to this policy will be explicitly mentioned in the event description.
April 3, 2024 - October 2, 2024 (26 weeks)
Cross-project events
PTG (virtual)
From April 8 to April 12 we'll have a virtual PTG to plan the Dalmatian release schedule.
Dalmatian-1 milestone
30 May, 2024 is the Dalmatian-1 milestone. See project-specific notes for relevant deadlines.
2024.1 Caracal Cycle-Trailing Release Deadline
All projects following the cycle-trailing release model must release their 2024.1 Caracal deliverables by 13 June, 2024.
Dalmatian-2 milestone
18 July, 2024 is the Dalmatian-2 milestone. See project-specific notes for relevant deadlines.
Membership Freeze
Projects must participate in at least two milestones in order to be considered part of the release. Projects made official after the second milestone, or which fail to produce milestone releases for at least one of the first and second milestones as well as the third milestone, are therefore not considered part of the release for the cycle. This does not apply to cycle-trailing packaging / lifecycle management projects.
Extra-AC freeze
All contributions to OpenStack are valuable, but some are not expressed as Gerrit code changes. That allow teams to list active contributors to their projects and who do not have a code contribution this cycle, and therefore won't automatically be considered an Active Contributor and allowed to vote. This is done by adding extra-acs to https://opendev.org/openstack/governance/src/branch/master/reference/projects.yaml before the Extra-AC freeze date.
Final release for non-client libraries
Libraries that are not client libraries (Oslo and others) should issue their final release during this week. That allows to give time for last-minute changes before feature freeze.
Dalmatian-3 milestone
29 August, 2024 is the Dalmatian-3 milestone. See project-specific notes for relevant deadlines.
Feature freeze
The Dalmatian-3 milestone marks feature freeze for projects following the release:cycle-with-rc model. No featureful patch should be landed after this point. Exceptions may be granted by the project PTL.
Final release for client libraries
Client libraries should issue their final release during this week, to match feature freeze.
Soft StringFreeze
You are no longer allowed to accept proposed changes containing modifications in user-facing strings. Such changes should be rejected by the review team and postponed until the next series development opens (which should happen when RC1 is published).
Requirements freeze
After the Dalmatian-3 milestone, only critical requirements and constraints changes will be allowed. Freezing our requirements list gives packagers downstream an opportunity to catch up and prepare packages for everything necessary for distributions of the upcoming release. The requirements remain frozen until the stable branches are created, with the release candidates.
RC1 target week
The week of 9 September, 2024 is the target date for projects following the release:cycle-with-rc model to issue their first release candidate.
Hard StringFreeze
This happens when the RC1 for the project is tagged. At this point, ideally no strings are changed (or added, or removed), to give translators time to finish up their efforts.
Final RCs and intermediary releases
The week of 23 September, 2024 is the last week to issue release candidates or intermediary releases before release week. During release week, only final-release-critical releases will be accepted (at the discretion of the release team).
Dalmatian release
The Dalmatian coordinated release will happen on Wednesday, 2 October, 2024.
Cycle Highlights
Cycle highlights need to be added to the release deliverables after the feature freeze to be included in any marketing release messaging. Highlights may be added after this point, but they will likely only be useful for historical purposes.
See the Project Team Guide for more details and instructions on adding these highlights.
For examples of previous release highlights: Stein Highlights, Train Highlights, Ussuri Highlights, Victoria Highlights, Wallaby Highlights, Xena Highlights, Yoga Highlights, Zed Highlights. 2023.1 Antelope Highlights. 2023.2 Bobcat Highlights. 2024.1 Caracal Highlights.