Remove steps in the release process around creating temporary ACLs for new stable branches and switching Gerrit group contents around release time. This implements the plan presented and discussed at: http://lists.openstack.org/pipermail/openstack-dev/2018-March/128731.html Change-Id: I2d211af54dc4f170172757a82dc1e6c55d2ab504
354 lines
14 KiB
ReStructuredText
354 lines
14 KiB
ReStructuredText
===================
|
|
Release Processes
|
|
===================
|
|
|
|
This document describes the relative ordering and rough timeline for
|
|
all of the steps related to preparing the release.
|
|
|
|
Before PTG (after closing previous release)
|
|
===========================================
|
|
|
|
1. Set up the release schedule for the newly opened cycle by creating
|
|
the required pages in openstack/releases.
|
|
|
|
2. Update the link to the documentation on the newly opened cycle page
|
|
to point to the right place on docs.openstack.org.
|
|
|
|
3. Create the $series-relmgt-plan and $series-relmgt-tracking
|
|
etherpads.
|
|
|
|
4. Use ``init-series`` to create stub deliverable files based on the
|
|
contents of the previous release.
|
|
|
|
Between Summit and Milestone-1
|
|
==============================
|
|
|
|
1. Establish liaisons by having them update
|
|
https://wiki.openstack.org/wiki/CrossProjectLiaisons with their
|
|
contact information.
|
|
|
|
2. Email PTLs directly one time to explain the use of the "[release]"
|
|
email tag on the openstack-dev list.
|
|
|
|
3. Encourage liaisons to ensure that their release model is set
|
|
properly before the first milestone.
|
|
|
|
4. Start weekly countdown emails, sent on Thursday afternoon (US)
|
|
or Friday morning (EU/APAC) with information needed about the
|
|
following week (deadlines, instructions, etc.).
|
|
|
|
5. The week before Milestone-1, include a reminder about completing
|
|
the responses to community-wide goals in the countdown email.
|
|
|
|
Milestone-1
|
|
===========
|
|
|
|
1. Include the deadline for the milestone in the countdown emails but
|
|
do not send extra reminders to liaisons. Missing the first
|
|
milestone isn't important in terms of the release, so we want to
|
|
encourage everyone to pay attention on their own.
|
|
|
|
Between Milestone-1 and Milestone-2
|
|
===================================
|
|
|
|
1. Follow up with PTLs and liaisons for projects that missed the first
|
|
milestone.
|
|
|
|
2. Use the countdown emails to list which projects have not done any
|
|
stable release yet, to encourage them to do so.
|
|
|
|
3. Use the countdown emails to list which intermediary-released (or
|
|
independent) projects haven't done a release yet. Remind teams that
|
|
we need at least one library release before milestone-2.
|
|
|
|
4. The week before Milestone-2 include a reminder of the deadline in
|
|
the countdown emails. Mention the MembershipFreeze deadline as well.
|
|
List teams that still haven't done a library release yet and remind
|
|
them of the milestone-2 deadline.
|
|
|
|
Milestone-2
|
|
===========
|
|
|
|
1. Run the following to get a report of which libraries have unreleased
|
|
changes::
|
|
|
|
tools/list_library_unreleased_changes.sh
|
|
|
|
Filter out libraries that have insignificant changes (Updates to .gitreview,
|
|
etc.) and include list in the weekly countdown email.
|
|
|
|
Between Milestone-2 and Milestone-3
|
|
===================================
|
|
|
|
1. Follow up with PTLs and liaisons for projects that missed the second
|
|
milestone, or still haven't done their library releases yet.
|
|
|
|
2. In the countdown email immediately after Milestone-2, include a
|
|
reminder about the various freezes that happen around Milestone-3.
|
|
|
|
3. Two weeks before Milestone-3, include a reminder about the final
|
|
library release freeze coming the week before Milestone-3.
|
|
|
|
1. Run the command from milestone-2 again to get a list of libraries::
|
|
|
|
tools/list_library_unreleased_changes.sh
|
|
|
|
2. Include list of unreleased libraries in the email to increase visibility.
|
|
|
|
4. Two weeks before Milestone-3, prepare other teams to the final release
|
|
rush.
|
|
|
|
1. Ask the release liaisons for the affected teams to update the
|
|
contents of their $project-stable-maint groups, as that group
|
|
will control the stable/$series branch prior to release. They
|
|
should reach out to the stable-maint-core group for additions.
|
|
|
|
2. Notify the Infrastructure team to `generate
|
|
<https://docs.openstack.org/infra/system-config/signing.html#generation>`_
|
|
an artifact signing key (but not replace the current one yet), and
|
|
begin the attestation process.
|
|
|
|
5. Two weeks before milestone 3, warn cycle-with-intermediary projects
|
|
without any releases that the release team will tag HEAD of master
|
|
for their project if they have not prepared a release by the
|
|
following week so that there is a fallback release to use for the
|
|
cycle and as a place to create their stable branch.
|
|
|
|
Final Library Release (week before Milestone-3)
|
|
===============================================
|
|
|
|
1. Release libraries as quickly as possible this week to ensure they
|
|
are all done before the freeze. Consider relaxing the "not on
|
|
Friday" release rule if absolutely necessary.
|
|
|
|
2. Remind liaisons to prepare releases for client libraries at
|
|
Milestone-3.
|
|
|
|
3. Update the feature list and allowed stable branch names in
|
|
devstack-gate for the new stable branch. For
|
|
example, https://review.openstack.org/362435 and
|
|
https://review.openstack.org/363084
|
|
|
|
4. Ensure that final releases for libraries also include the
|
|
specification to create the stable/$series branch.
|
|
|
|
5. Tag HEAD of master for any cycle-with-intermediary project without
|
|
any releases. Do not create branches for non-library projects.
|
|
|
|
Milestone-3
|
|
===========
|
|
|
|
1. Verify that all projects following release:cycle-with-intermediary
|
|
have prepared at least one release for the cycle.
|
|
|
|
2. Freeze changes to ``openstack/requirements`` by applying -2 to all
|
|
open patches. Ensure that reviewers do not approve changes created
|
|
by the proposal bot.
|
|
|
|
3. Ensure the stable/$series branch is requested with each client
|
|
library final release.
|
|
|
|
4. Remind PTLs/liaisons that master should be frozen except for bug
|
|
fixes and feature work with FFEs.
|
|
|
|
5. Remind PTL/liaisons to start preparing "prelude" release notes as
|
|
summaries of the content of the release so that those are merged
|
|
before their first release candidate.
|
|
|
|
6. Freeze all cycle-based library releases except for release-critical
|
|
bugs. Independently-released libraries may still be released, but
|
|
constraint or requirement changes will be held until after the freeze
|
|
period.
|
|
|
|
7. Include a reminder about completing the responses to community-wide
|
|
goals in the countdown email.
|
|
|
|
Between Milestone-3 and RC1
|
|
===========================
|
|
|
|
1. Encourage liaisons to wait as long as possible to create RC1 to
|
|
avoid immediately having to create an RC2 with a new bug fix.
|
|
|
|
2. Encourage release:independent projects to add the history for any
|
|
releases not yet listed in their deliverable file.
|
|
|
|
3. Remind projects using all release models to prepare their new
|
|
stable branch request around the RC1 target date.
|
|
|
|
As soon as grenade is updated for the new branch (see the RC1
|
|
instructions that follow), projects without stable branches may
|
|
start seeing issues with their grenade jobs because without the
|
|
stable branch the branch selection will cause the jobs to run
|
|
master->master instead of previous->master. At the end of Ocata
|
|
this caused trouble for the Ironic team, for example.
|
|
|
|
4. Warn cycle-with-intermediary projects that have releases more than
|
|
2 months old that we will use their existing release as a point for
|
|
branching if they have not prepared a newer release by the RC1
|
|
deadline.
|
|
|
|
RC1
|
|
===
|
|
|
|
1. Ensure all RC1 tag requests include the info to have the
|
|
stable/$series branch created, too.
|
|
|
|
Branches for cycle-trailing and cycle-with-intermediary projects
|
|
should be created when the PTL/liaison are ready, and not
|
|
necessarily for RC1 week.
|
|
|
|
2. After the minimum set of projects used by devstack have been branched, the
|
|
devstack branch can be created. Devstack doesn't push a tag at RC1 it is
|
|
just branched off of HEAD
|
|
|
|
3. After devstack is branched a grenade branch can be created. As with
|
|
devstack it will branch from HEAD instead of a tag.
|
|
|
|
4. Update the default branch for devstack in the new stable
|
|
branch. For example, https://review.openstack.org/#/c/493208/
|
|
|
|
5. Update the grenade settings in devstack-gate for the new branch. For
|
|
example, https://review.openstack.org/362438.
|
|
|
|
6. For translations, create stable-$series versions in the Zanata
|
|
translation server on https://translate.openstack.org for all
|
|
projects that the translation team wants to handle. Create new
|
|
translation-jobs-$series periodic jobs to import translations from
|
|
the Zanata translation server and propose them to projects, add
|
|
these jobs to all projects that have a stable-$series version.
|
|
|
|
Note this work is done by translation team.
|
|
|
|
7. After all cycle-with-milestone projects have their branches
|
|
created, someone from the requirements core team (preferably the
|
|
requirements PTL) needs to propose an update the deliverable file to
|
|
create the stable/$series branch for ``openstack/requirements``.
|
|
Then announce that the requirements freeze is lifted from master.
|
|
|
|
Note that we wait until after the other projects have branched to
|
|
create the branch for requirements because tests for the stable
|
|
branches of those projects will fall back to using the master
|
|
branch of requirements until the same stable branch is created,
|
|
but if the branch for the requirements repo exists early the
|
|
changes happening in master on the other projects will not use it
|
|
and we can have divergence between the requirements being tested
|
|
and being declared as correct.
|
|
|
|
8. In the tempest repo, create new branch specific jobs for our two branchless
|
|
projects, devstack-gate and tempest. Configure tempest to run them on all
|
|
changes, voting. Configure tempest to run them as periodic bitrot jobs as
|
|
well. All this can be done in one tempest patch, like for example, see
|
|
https://review.openstack.org/521888.
|
|
Configure devstack-gate to run the new jobs in check pipeline only,
|
|
non-voting, for example see https://review.openstack.org/545144.
|
|
|
|
9. Add the new branch to the list of branches in the periodic-stable job
|
|
templates in openstack-zuul-jobs. For example, see
|
|
https://review.openstack.org/545268/.
|
|
|
|
|
|
Between RC1 and Final
|
|
=====================
|
|
|
|
Try to avoid creating more than 3 release candidates so we are not
|
|
creating candidates that consumers are then trained to ignore. Each
|
|
release candidate should be kept for at least 1 day, so if there is a
|
|
proposal to create RCX but clearly a reason to create another one,
|
|
delay RCX to include the additional patches. Teams that know they will
|
|
need additional release candidates can submit the requests and mark
|
|
them WIP until actually ready, so the release team knows that more
|
|
candidates are coming.
|
|
|
|
1. Ensure that all projects that are publishing release notes have the
|
|
notes link included in their deliverable file. See
|
|
``tools/add_release_note_links.sh``.
|
|
|
|
2. Encourage liaisons to merge all translation patches.
|
|
|
|
3. When all translations and bug fixes are merged for a project,
|
|
prepare a new release candidate.
|
|
|
|
4. Ensure that the final release candidate for each project is
|
|
prepared at least one week before the final release date.
|
|
|
|
5. After final releases for release:cycle-with-intermediary projects
|
|
are tagged, create their stable branches.
|
|
|
|
6. On the morning of the deadline for final release candidates, check
|
|
the list of unreleased changes for milestone projects and verify
|
|
with the PTLs and liaisons that they are planning a release or that
|
|
they do not need one.
|
|
|
|
In the release-tools repository working directory, run::
|
|
|
|
$ ./list_unreleased_changes.sh stable/newton $(list-repos --tag release:cycle-with-milestones) 2>&1 | tee unreleased.log
|
|
|
|
7. As soon as the last release candidate is tagged and the freeze
|
|
period is entered, use ``propose-final-releases`` to tag the
|
|
existing most recent release candidates as the final release for
|
|
projects using the cycle-with-milestone model.
|
|
|
|
8. Ask liaisons and PTLs of milestone-based projects to review and +1
|
|
the final release proposal from the previous step so their approval
|
|
is included in the metadata that goes onto the signed tag.
|
|
|
|
9. The week before final release test the release process using the
|
|
openstack/release-test repository.
|
|
|
|
10. Notify the documentation team that it should be safe to apply
|
|
their process to create the new release series landing pages for
|
|
docs.openstack.org. Their process works better if they wait until
|
|
most of the projects have their stable branches created, but they
|
|
can do the work before the final release date to avoid having to
|
|
synchronize with the release team on that day.
|
|
|
|
Final Release
|
|
=============
|
|
|
|
1. Approve the final release patch created earlier.
|
|
|
|
2. Run the missing-releases script to check for missing tarballs on the
|
|
release page before the announcement::
|
|
|
|
tox -e venv -- missing-releases --series $SERIES
|
|
|
|
3. Mark series as released on releases.o.o, by updating doc/source/index.rst
|
|
and doc/source/$series/index.rst.
|
|
See https://review.openstack.org/#/c/381006 for an example.
|
|
|
|
4. Update the default series name in
|
|
``openstack/releases/openstack_releases/defaults.py`` to use the
|
|
new series name.
|
|
|
|
5. Send release announcement email to
|
|
``openstack-announce@lists.openstack.org``, based on
|
|
``templates/final.txt``. Coordinate the timing of the email with
|
|
the press release from the Foundation staff.
|
|
|
|
6. Send an email to the openstack-dev list to point to the official
|
|
release announcement, and declare ``openstack/releases`` unfrozen for
|
|
releases on the new series.
|
|
|
|
Post-Final Release
|
|
==================
|
|
|
|
1. The week after the final release, process any late or blocked
|
|
release requests for deliverables for any branch (treating the new
|
|
series branch as stable).
|
|
|
|
2. The week after the final releases for milestone-based projects are
|
|
tagged, use ``propose-final-releases --all`` to tag the existing
|
|
most recent release candidates as the final release for projects
|
|
using the cycle-trailing model.
|
|
|
|
3. Ask liaisons and PTLs of cycle-trailing projects to review and +1
|
|
the final release proposal from the previous step so their approval
|
|
is included in the metadata that goes onto the signed tag.
|
|
|
|
cycle-trailing Final Release
|
|
============================
|
|
|
|
1. Two weeks after the final release for milestone-based projects,
|
|
approve the final release patch created earlier.
|
|
|