Change-Id: I3328e0e360570ccc78bb33f8f5acee5a73488b3a Signed-off-by: Doug Hellmann <doug@doughellmann.com>
12 KiB
Mitaka release schedule
Week | Cross-project events | Project-specific events |
+============+======+===========================+=============================+
| Oct 19-23 | R-24 | | |
+------------+------+---------------------------+-----------------------------+
| Oct 26-30 | R-23 | m-design-summit
| |
+------------+------+---------------------------+-----------------------------+
| Nov 2-6 | R-22 | | |
+------------+------+---------------------------+-----------------------------+
| Nov 9-13 | R-21 | | |
+------------+------+---------------------------+-----------------------------+
| Nov 16-20 | R-20 | | |
+------------+------+---------------------------+-----------------------------+
| Nov 23-27 | R-19 | | |
+------------+------+---------------------------+-----------------------------+
| Nov 30-4 | R-18 | m-1
| m-nova-bp-freeze
| |
| +---------------------------+-----------------------------+ | | | |
m-key-bp-freeze
|
+------------+------+---------------------------+-----------------------------+
| Dec 7-11 | R-17 | | |
+------------+------+---------------------------+-----------------------------+
| Dec 14-18 | R-16 | | |
+------------+------+---------------------------+-----------------------------+
| Dec 21-25 | R-15 | | |
+------------+------+---------------------------+-----------------------------+
| Dec 28-1 | R-14 | | m-glance-bp-freeze
|
+------------+------+---------------------------+-----------------------------+
| Jan 4-8 | R-13 | | |
+------------+------+---------------------------+-----------------------------+
| Jan 11-15 | R-12 | | |
+------------+------+---------------------------+-----------------------------+
| Jan 18-22 | R-11 | m-2
| m-nova-npff
| | |
+---------------------------+-----------------------------+ | | | |
m-cinder-nddeadline
| |
| +---------------------------+-----------------------------+ | | | |
m-key-fpdeadline
| | |
+---------------------------+-----------------------------+ | | | |
m-cinder-spec-freeze
|
| | +---------------------------+-----------------------------+ | | | |
m-glance_store-maint
|
+------------+------+---------------------------+-----------------------------+
| Jan 25-29 | R-10 | | |
+------------+------+---------------------------+-----------------------------+
| Feb 1-5 | R-9 | | |
+------------+------+---------------------------+-----------------------------+
| Feb 8-12 | R-8 | | |
+------------+------+---------------------------+-----------------------------+
| Feb 15-19 | R-7 | | |
+------------+------+---------------------------+-----------------------------+
| Feb 22-26 | R-6 | m-final-lib
| |
+------------+------+---------------------------+-----------------------------+
| Feb 29-4 | R-5 | m-3
| m-cinder-ff
| | |
+---------------------------+-----------------------------+ | | | m-ff
| | | |
+---------------------------+-----------------------------+ | | | m-rf
| | | |
+---------------------------+-----------------------------+ | | | m-final-clientlib
| | | |
+---------------------------+-----------------------------+ | | | m-soft-sf
| |
+------------+------+---------------------------+-----------------------------+
| Mar 7-11 | R-4 | | |
+------------+------+---------------------------+-----------------------------+
| Mar 14-18 | R-3 | m-rc1
| n-ptl-nomination
| | |
+---------------------------+-----------------------------+ | | | m-hard-sf
| |
+------------+------+---------------------------+-----------------------------+
| Mar 21-25 | R-2 | | n-ptl-election
|
+------------+------+---------------------------+-----------------------------+
| Mar 28-1 | R-1 | m-finalrc
| n-tc-nomination
|
+------------+------+---------------------------+-----------------------------+
| Apr 4-8 | R-0 | m-release
| n-tc-election
|
+------------+------+---------------------------+-----------------------------+
Cross-project events
Mitaka Design Summit
Planning in Tokyo ! And Okonomiyaki.
mitaka-1 milestone
Dec 1-3 is the mitaka-1 milestone window for projects following the release:cycle-with-milestones model.
mitaka-2 milestone
Jan 19-21 is the mitaka-2 milestone window for projects following the release:cycle-with-milestones model.
Final release for non-client libraries
Libraries that are not client libraries (Oslo and others) should issue their final release during this week. That allows to give time for last-minute changes before feature freeze.
Library releases resume around R-2.
mitaka-3 milestone
March 1-3 is the mitaka-3 milestone window for projects following the release:cycle-with-milestones model.
Feature freeze
The mitaka-3 milestone marks feature freeze for projects following the release:cycle-with-milestones model. No featureful patch should be landed after this point. Exceptions may be granted by the project PTL.
Requirements freeze
After the mitaka-3 milestone, only critical requirements and constraints changes will be allowed. Freezing our requirements list gives packagers downstream an opportunity to catch up and prepare packages for everything necessary for distributions of the upcoming release. The requirements remain frozen until the stable branches are created, with the release candidates.
Final release for client libraries
Client libraries should issue their final release during this week, to match feature freeze.
Library releases resume around R-2.
Soft StringFreeze
You are no longer allowed to accept proposed changes containing modifications in user-facing strings. Such changes should be rejected by the review team and postponed until the next series development opens (which should happen when RC1 is published).
RC1 target week
The week of March 14-18 is the target date for projects following the release:cycle-with-milestones model to issue their first release candidate.
Hard StringFreeze
This happens when the RC1 for the project is tagged. At this point, ideally no strings are changed (or added, or removed), to give translator time to finish up their efforts.
Final RCs and intermediary releases
The week of March 28 to April 1st is the last week to issue release candidates or intermediary releases before release week. On release week only final-release-critical releases will be accepted (at the discretion of the release team).
Mitaka release
The Mitaka coordinated release will happen on April 7th.
Project-specific events
Elections
N cycle PTLs self-nomination
Project team lead candidates for the N cycle should announce their candidacy during this week.
N cycle PTLs election
Election week for Project team leads (where an election must be held to determine the winner).
TC member self-nomination
Candidates for the partial Technical Committee member renewal should announce their candidacy during this week.
TC member election
Election for partially renewing Technical Committee members will happen during this week.
Nova
Nova Blueprint Freeze
The deadline for getting a Nova blueprint approved for Mitaka is 3rd December 2015. Please note this is also the deadline to get any Mitaka nova-specs merged.
Nova Non-Priority Feature Freeze
A non-priority feature is any feature that is not associated with one of the Mitaka priorities: http://specs.openstack.org/openstack/nova-specs/priorities/mitaka-priorities.html
The deadline for non-priority feature code to be merged into master is 21st January 2015.
Please note, the Feature Freeze for priority features is aligned with
m-ff
.
Cinder
Cinder New Backend Driver Deadline
The deadline for getting a new backend driver added to Cinder is 19th January 2015. All review issues must be addressed and third party CI must be reporting and stable with enough time for reviewers prior to the deadline. Meeting these requirements on the 19th does not guarantee core reviewers will have enough time to merge the driver.
Cinder Spec/Blueprint Freeze
All Cinder specs and blueprints must be approved by 19th January 2015.
Cinder Feature Freeze
The deadline for new features and driver functionality is 1st March 2016. Any changes past that date will be at the discretion of the core team.
Glance
Glance Blueprints Freeze
All Glance new feature requests must be approved by Jan 1st.
Glance Store maintainers deadline
Glance store drivers without maintainers will be marked as deprecated and then removed in N. Please, refer to this email thread for some more information:
http://lists.openstack.org/pipermail/openstack-dev/2015-December/081966.html
Keystone
Keystone Spec/Blueprint Freeze
The deadline for getting a Keystone blueprint approved for Mitaka is 3rd December 2015. Please note this is also the deadline to get any Mitaka keystone-specs merged. Specs that wish to land past this deadline must send an email to the dev mailing list asking for an exemption.
Keystone Feature Proposal Deadline
All approved features must have a patch that shows most functionality ready for review by 18th January 2016. Approved features that do not have a patch ready for review by the deadline must send an email to the dev mailing list asking for an exemption. Approved features that miss the deadline or do not receive an exemption will be moved to the backlog or the first milestone of the next release.
Please note, the Keystone Feature Freeze date is aligned with m-ff
.