Rocky Release Schedule
|
|
========================
|
|
|
|
1 March 2018 - 29 August 2018 (26 weeks)
|
|
|
|
.. datatemplate::
|
|
:source: schedule.yaml
|
|
:template: schedule_table.tmpl
|
|
|
|
.. ics::
|
|
:source: schedule.yaml
|
|
:name: Rocky
|
|
|
|
`Subscribe to iCalendar file <schedule.ics>`__
|
|
|
|
.. note::
|
|
|
|
With the exception of the final release date and cycle-trailing
|
|
release date, deadlines are generally the Thursday of the week on
|
|
which they are noted above. For example, the Feature Freeze in week
|
|
R-5 is on 26 July. Exceptions to this policy will be explicitly
|
|
mentioned in the event description.
|
|
|
|
Cross-project events
|
|
====================
|
|
|
|
.. _r-goals-research:
|
|
|
|
Rocky Goals Research
|
|
--------------------
|
|
|
|
Pre-cycle planning and investigation into `the community-wide goals
|
|
for Rocky <https://governance.openstack.org/tc/goals/rocky/index.html>`__.
|
|
|
|
.. _r-ptg:
|
|
|
|
Rocky Project Team Gathering (PTG)
|
|
----------------------------------
|
|
|
|
`Project team gathering <https://www.openstack.org/ptg>`__ for the Rocky
|
|
cycle 26 February - 2 March 2018 in Dublin, Ireland.
|
|
|
|
.. _r-1:
|
|
|
|
Rocky-1 milestone
|
|
-----------------
|
|
|
|
19 April 2018 is the Rocky-1 milestone window for projects following the
|
|
`release:cycle-with-milestones`_ model.
|
|
|
|
.. _release:cycle-with-milestones: https://releases.openstack.org/reference/release_models.html#cycle-with-milestones
|
|
|
|
.. _r-goals-ack:
|
|
|
|
Rocky Community Goals Acknowledgement
|
|
-------------------------------------
|
|
|
|
Teams should prepare their acknowledgement of `the community-wide
|
|
goals for
|
|
<https://governance.openstack.org/tc/goals/queens/index.html>`__.
|
|
|
|
.. _r-summit:
|
|
|
|
OpenStack Summit
|
|
----------------
|
|
|
|
The OpenStack Summit happens during this week in Vancouver, BC. It will
|
|
include a "Forum" in which people from all parts of our community will gather
|
|
to give feedback on the last release (Queens) and discuss requirements for the
|
|
next development cycle (S).
|
|
|
|
.. _r-2:
|
|
|
|
Rocky-2 milestone
|
|
-----------------
|
|
|
|
7 June 2018 is the Rocky-2 milestone window for projects following the
|
|
`release:cycle-with-milestones`_ model.
|
|
|
|
.. _r-final-lib:
|
|
|
|
Final release for non-client libraries
|
|
--------------------------------------
|
|
|
|
Libraries that are not client libraries (Oslo and others) should issue their
|
|
final release during this week. That allows to give time for last-minute
|
|
changes before feature freeze.
|
|
|
|
.. _r-3:
|
|
|
|
Rocky-3 milestone
|
|
-----------------
|
|
|
|
26 July 2018 is the Rocky-3 milestone window for projects following the
|
|
`release:cycle-with-milestones`_ model.
|
|
|
|
.. _r-goals-complete:
|
|
|
|
Rocky Community Goals Completed
|
|
-------------------------------
|
|
|
|
Teams should prepare their documentation for completing `the
|
|
community-wide goals for Rocky
|
|
<https://governance.openstack.org/tc/goals/rocky/index.html>`__.
|
|
|
|
.. _r-extra-atcs:
|
|
|
|
Extra-ATCs deadline
|
|
-------------------
|
|
|
|
Project teams should identify contributors who have had a significant
|
|
impact this cycle but who would not qualify for ATC status using the
|
|
regular process because they have not submitted a patch. Those names
|
|
should be added to the governance repo for consideration as ATC for
|
|
the future.
|
|
|
|
.. _r-ff:
|
|
|
|
Feature freeze
|
|
--------------
|
|
|
|
The Rocky-3 milestone marks feature freeze for projects following the
|
|
`release:cycle-with-milestones`_ model. No featureful patch should be landed
|
|
after this point. Exceptions may be granted by the project PTL.
|
|
|
|
.. _r-rf:
|
|
|
|
Requirements freeze
|
|
-------------------
|
|
|
|
After the Rocky-3 milestone, only critical requirements and
|
|
constraints changes will be allowed. Freezing our requirements list
|
|
gives packagers downstream an opportunity to catch up and prepare
|
|
packages for everything necessary for distributions of the upcoming
|
|
release. The requirements remain frozen until the stable branches are
|
|
created, with the release candidates.
|
|
|
|
.. _r-final-clientlib:
|
|
|
|
Final release for client libraries
|
|
----------------------------------
|
|
|
|
Client libraries should issue their final release during this week, to
|
|
match feature freeze.
|
|
|
|
.. _r-soft-sf:
|
|
|
|
Soft StringFreeze
|
|
-----------------
|
|
|
|
You are no longer allowed to accept proposed changes containing
|
|
modifications in user-facing strings. Such changes should be rejected
|
|
by the review team and postponed until the next series development
|
|
opens (which should happen when RC1 is published).
|
|
|
|
.. _r-mf:
|
|
|
|
Membership Freeze
|
|
-----------------
|
|
|
|
Projects must participate in at least two milestones in order to be
|
|
considered part of the release. Projects made official after the
|
|
second milestone, or which fail to produce milestone releases for at
|
|
least one of the first and second milestones as well as the third
|
|
milestone, are therefore not considered part of the release for the
|
|
cycle. This does not apply to cycle-trailing packaging / lifecycle
|
|
management projects.
|
|
|
|
.. _r-rc1:
|
|
|
|
RC1 target week
|
|
---------------
|
|
|
|
The week of 6 August 2018 is the target date for projects following the
|
|
`release:cycle-with-milestones`_ model to issue their first release candidate,
|
|
with a deadline of 9 August 2018.
|
|
|
|
.. _r-hard-sf:
|
|
|
|
Hard StringFreeze
|
|
-----------------
|
|
|
|
This happens when the RC1 for the project is tagged. At this point, ideally
|
|
no strings are changed (or added, or removed), to give translator time to
|
|
finish up their efforts.
|
|
|
|
.. _r-finalrc:
|
|
|
|
Final RCs and intermediary releases
|
|
-----------------------------------
|
|
|
|
The week of 20 August 2018 is the last week to issue release candidates or
|
|
intermediary releases before release week. During release week, only
|
|
final-release-critical releases will be accepted (at the discretion of
|
|
the release team).
|
|
|
|
.. _r-release:
|
|
|
|
Rocky release
|
|
-------------
|
|
|
|
The Rocky coordinated release will happen on 30 August 2018.
|
|
|
|
.. _r-trailing-release:
|
|
|
|
Rocky cycle-trailing release deadline
|
|
-------------------------------------
|
|
|
|
The release deadline for projects using the release:cycle-trailing model that
|
|
follow the main release cycle is set to November 28, 2018.
|
|
|
|
.. _r-tc-email-deadline:
|
|
|
|
TC Election Email Deadline
|
|
--------------------------
|
|
Contributors that will be in the electorate for the upcoming election
|
|
should confirm their gerrit email addresses by this date (April 18th, 2018 at
|
|
00:00 UTC). Electorate rolls are generated after this date and ballots will
|
|
be sent to the listed gerrit email address.
|
|
|
|
.. _r-tc-nominations:
|
|
|
|
TC Election Nomination Begins
|
|
-----------------------------
|
|
Technical committee candidates interested in serving for the next calendar year
|
|
should announce their candidacies and platforms during this week.
|
|
|
|
.. _r-tc-campaigning:
|
|
|
|
TC Election Campaigning Begins
|
|
------------------------------
|
|
The electorate has time to ask candidates questions about their platforms
|
|
and debate topics before polling begins.
|
|
|
|
.. _r-tc-polling:
|
|
|
|
TC Election Polling Begins
|
|
--------------------------
|
|
Election polling week for open seats on the TC.
|
|
|
|
Project-specific events
|
|
=======================
|
|
|
|
PTL Elections
|
|
-------------
|
|
|
|
Keystone
|
|
--------
|
|
|
|
.. _r-keystone-spec-proposal-freeze:
|
|
|
|
Keystone Spec Proposal Freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
All Keystone specs targeted to Rocky must be submitted to the keystone-specs
|
|
repository by the end of the week.
|
|
|
|
.. _r-keystone-spec-freeze:
|
|
|
|
Keystone Spec Freeze
|
|
^^^^^^^^^^^^^^^^^^^^
|
|
|
|
All Keystone specs targeted to Rocky must be approved by the end of the week.
|
|
|
|
.. _r-keystone-fpfreeze:
|
|
|
|
Keystone Feature Proposal Freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
All new Keystone features must be proposed and substantially completed, with
|
|
unit tests and documentation by the end of the week.
|
|
|
|
.. _r-keystone-ffreeze:
|
|
|
|
Keystone Feature Freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
All new Keystone features must be merged by the end of the week.
|
|
|
|
Manila
|
|
------
|
|
|
|
.. _r-manila-spec-freeze:
|
|
|
|
Manila Spec Freeze
|
|
^^^^^^^^^^^^^^^^^^
|
|
|
|
All Manila specs must be approved by 19 Apr 2018 (23:59 UTC).
|
|
|
|
.. _r-manila-driver-deadline:
|
|
|
|
Manila New Driver Submission Deadline
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
The deadline for submitting new backend drivers to to Manila is 4 Jun 2018
|
|
(23:59 UTC). New drivers must be substantially complete, with unit tests, and
|
|
passing 3rd party CI by this date. Drivers do not need to be merged until the
|
|
feature freeze date, but drivers that don't meet this deadline will not be
|
|
considered at all for Rocky.
|
|
|
|
|
|
.. _r-manila-fp-freeze:
|
|
|
|
Manila Feature Proposal Freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
All new Manila features must be proposed and substantially complete, with unit
|
|
tests by 9 Jul 2018 (23:59 UTC).
|
|
|
|
Cinder
|
|
------
|
|
|
|
.. _r-cinder-spec-freeze:
|
|
|
|
Cinder Spec Freeze
|
|
^^^^^^^^^^^^^^^^^^
|
|
|
|
All Cinder specs must be approved by 4 Jun 2018 (23:59 UTC).
|
|
|
|
.. _r-cinder-driver-deadline:
|
|
|
|
Cinder New Driver Submission Deadline
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
The deadline for submitting new backend drivers to Cinder is 4 Jun 2018
|
|
(23:59 UTC). New drivers must be complete, with unit tests, passing
|
|
3rd Party CI and be merged by this date.
|
|
|
|
.. _r-cinder-feature-freeze:
|
|
|
|
Cinder Feature Proposal Freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
All new Cinder features must be proposed and substantially complete,
|
|
with unit test by 16 Jul 2018 (23:59 UTC).
|
|
|