Newton release schedule
|
|
=========================
|
|
|
|
+-------------------+---------------------------+-----------------------------+
|
|
| Week | Cross-project events | Project-specific events |
|
|
+============+======+===========================+=============================+
|
|
| Apr 04-08 | | :ref:`m-release` | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Apr 11-15 | R-25 | | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Apr 18-22 | R-24 | | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Apr 25-29 | R-23 | :ref:`n-design-summit` | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| May 02-06 | R-22 | | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| May 09-13 | R-21 | | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| May 16-20 | R-20 | | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| May 23-27 | R-19 | | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| May 30-03 | R-18 | :ref:`n-1` | :ref:`n-nova-non-prio-s-fr` |
|
|
| | +---------------------------+-----------------------------+
|
|
| | | | :ref:`n-key-spec-pfreeze` |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Jun 06-10 | R-17 | | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Jun 13-17 | R-16 | | :ref:`n-trove-spec-prop` |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Jun 20-24 | R-15 | | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Jun 27-01 | R-14 | | :ref:`n-nova-non-prio-ff` |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Jul 04-08 | R-13 | | :ref:`n-key-spec-freeze` |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Jul 11-15 | R-12 | :ref:`n-2` | :ref:`n-cinder-nddeadline` |
|
|
| | +---------------------------+-----------------------------+
|
|
| | | :ref:`n-mf` | :ref:`n-cinder-spec-freeze` |
|
|
| | +---------------------------+-----------------------------+
|
|
| | | | :ref:`n-trove-spec-freeze` |
|
|
| | +---------------------------+-----------------------------+
|
|
| | | | :ref:`n-key-fpf` |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Jul 18-22 | R-11 | | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Jul 25-29 | R-10 | | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Aug 01-05 | R-9 | | :ref:`n-nova-prio-spec-frz` |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Aug 08-12 | R-8 | :ref:`n-extra-atcs` | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Aug 15-19 | R-7 | | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Aug 22-26 | R-6 | :ref:`n-final-lib` | :ref:`n-trove-cl-soft` |
|
|
| | +---------------------------+-----------------------------+
|
|
| | | | :ref:`n-trove-guest-req` |
|
|
| | +---------------------------+-----------------------------+
|
|
| | | | :ref:`n-horizon-ff` |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Aug 29-02 | R-5 | :ref:`n-3` | :ref:`n-cinder-ff` |
|
|
| | +---------------------------+-----------------------------+
|
|
| | | :ref:`n-ff` | :ref:`n-trove-ff` |
|
|
| | +---------------------------+-----------------------------+
|
|
| | | :ref:`n-final-clientlib` | :ref:`n-key-ff` |
|
|
| | +---------------------------+-----------------------------+
|
|
| | | :ref:`n-soft-sf` | |
|
|
| | +---------------------------+-----------------------------+
|
|
| | | :ref:`n-rf` | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Sep 05-09 | R-4 | | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Sep 12-16 | R-3 | :ref:`n-rc1` | :ref:`o-ptl-nomination` |
|
|
| | +---------------------------+-----------------------------+
|
|
| | | :ref:`n-hard-sf` | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Sep 19-23 | R-2 | | :ref:`o-ptl-election` |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Sep 26-30 | R-1 | :ref:`n-finalrc` | :ref:`o-tc-nomination` |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Oct 03-07 | R+0 | :ref:`n-release` | :ref:`o-tc-election` |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Oct 10-14 | R+1 | | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Oct 17-21 | R+2 | :ref:`n-trailing` | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
| Oct 24-28 | R+3 | :ref:`o-design-summit` | |
|
|
+------------+------+---------------------------+-----------------------------+
|
|
|
|
.. note::
|
|
|
|
All deadlines are generally the Thursday of the week on which they
|
|
are noted above. For example, The Feature Freeze in week R-5 is on
|
|
1 September. Exceptions to this policy will be explicitly mentioned
|
|
in the event description.
|
|
|
|
Cross-project events
|
|
====================
|
|
|
|
.. _n-design-summit:
|
|
|
|
Newton Design Summit
|
|
--------------------
|
|
|
|
`Planning in Austin <https://www.openstack.org/summit/austin-2016/>`__
|
|
|
|
|
|
.. _n-1:
|
|
|
|
newton-1 milestone
|
|
------------------
|
|
|
|
May 31 - June 2 is the newton-1 milestone window for projects following the
|
|
`release:cycle-with-milestones`_ model.
|
|
|
|
.. _release:cycle-with-milestones: https://releases.openstack.org/reference/release_models.html#cycle-with-milestones
|
|
|
|
.. _n-2:
|
|
|
|
newton-2 milestone
|
|
------------------
|
|
|
|
July 12-14 is the newton-2 milestone window for projects following the
|
|
`release:cycle-with-milestones`_ model.
|
|
|
|
.. _n-final-lib:
|
|
|
|
Final release for non-client libraries
|
|
--------------------------------------
|
|
|
|
Libraries that are not client libraries (Oslo and others) should issue their
|
|
final release during this week. That allows to give time for last-minute
|
|
changes before feature freeze.
|
|
|
|
.. _n-3:
|
|
|
|
newton-3 milestone
|
|
------------------
|
|
|
|
August 30 - Sept 1 is the newton-3 milestone window for projects following the
|
|
`release:cycle-with-milestones`_ model.
|
|
|
|
.. _n-extra-atcs:
|
|
|
|
extra-atcs deadline
|
|
-------------------
|
|
|
|
Project teams should identify contributors who have had a significant
|
|
impact this cycle but who would not qualify for ATC status using the
|
|
regular process because they have not submitted a patch. Those names
|
|
should be added to the governance repo for consideration as ATC for
|
|
the future.
|
|
|
|
Although extra ATCs can be nominated at any point, there is a deadline
|
|
to be included in electorate for the next release cycle. The ATC list
|
|
needs to be approved by the TC by 25 Aug, and in order to appear on
|
|
the TC agenda to be discussed, the proposals need to be submitted to
|
|
the ``openstack/governance`` repository by 16 Aug.
|
|
|
|
.. _n-ff:
|
|
|
|
Feature freeze
|
|
--------------
|
|
|
|
The newton-3 milestone marks feature freeze for projects following the
|
|
`release:cycle-with-milestones`_ model. No featureful patch should be landed
|
|
after this point. Exceptions may be granted by the project PTL.
|
|
|
|
.. _n-rf:
|
|
|
|
Requirements freeze
|
|
-------------------
|
|
|
|
After the newton-3 milestone, only critical requirements and
|
|
constraints changes will be allowed. Freezing our requirements list
|
|
gives packagers downstream an opportunity to catch up and prepare
|
|
packages for everything necessary for distributions of the upcoming
|
|
release. The requirements remain frozen until the stable branches are
|
|
created, with the release candidates.
|
|
|
|
.. _n-final-clientlib:
|
|
|
|
Final release for client libraries
|
|
----------------------------------
|
|
|
|
Client libraries should issue their final release during this week, to match
|
|
feature freeze.
|
|
|
|
.. _n-soft-sf:
|
|
|
|
Soft StringFreeze
|
|
-----------------
|
|
|
|
You are no longer allowed to accept proposed changes containing modifications
|
|
in user-facing strings. Such changes should be rejected by the review team
|
|
and postponed until the next series development opens (which should happen
|
|
when RC1 is published).
|
|
|
|
.. _n-mf:
|
|
|
|
Membership Freeze
|
|
-----------------
|
|
|
|
Projects must participate in at least two milestones in order to be
|
|
considered part of the release. Projects made official after the
|
|
second milestone, or which fail to produce milestone releases for at
|
|
least one of the first and second milestones as well as the third
|
|
milestone, are therefore not considered part of the release for the
|
|
cycle.
|
|
|
|
.. _n-rc1:
|
|
|
|
RC1 target week
|
|
---------------
|
|
|
|
The week of September 12 is the target date for projects following the
|
|
`release:cycle-with-milestones`_ model to issue their first release candidate.
|
|
|
|
.. _n-hard-sf:
|
|
|
|
Hard StringFreeze
|
|
-----------------
|
|
|
|
This happens when the RC1 for the project is tagged. At this point, ideally
|
|
no strings are changed (or added, or removed), to give translator time to
|
|
finish up their efforts.
|
|
|
|
.. _n-finalrc:
|
|
|
|
Final RCs and intermediary releases
|
|
-----------------------------------
|
|
|
|
The week of September 26 is the last week to issue release candidates
|
|
or intermediary releases before release week. On release week only
|
|
final-release-critical releases will be accepted (at the discretion of the
|
|
release team).
|
|
|
|
.. _n-release:
|
|
|
|
Newton release
|
|
--------------
|
|
|
|
The Newton coordinated release will happen on October 6th, 2016.
|
|
|
|
.. _n-trailing:
|
|
|
|
Newton cycle-trailing Deadline
|
|
------------------------------
|
|
|
|
The deadline for projects using the release:cycle-trailing model that
|
|
follow the main release cycle.
|
|
|
|
Project-specific events
|
|
=======================
|
|
|
|
Elections
|
|
---------
|
|
|
|
.. _o-ptl-nomination:
|
|
|
|
Ocata cycle PTLs self-nomination
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
Project team lead candidates for the Ocata cycle should announce their
|
|
candidacy during this week.
|
|
|
|
.. _o-ptl-election:
|
|
|
|
Ocata cycle PTLs election
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
Election week for Project team leads (where an election must be held to
|
|
determine the winner).
|
|
|
|
.. _o-tc-nomination:
|
|
|
|
TC member self-nomination
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
Candidates for the partial Technical Committee member renewal should announce
|
|
their candidacy during this week.
|
|
|
|
.. _o-tc-election:
|
|
|
|
TC member election
|
|
^^^^^^^^^^^^^^^^^^
|
|
|
|
Election for partially renewing Technical Committee members will happen
|
|
during this week.
|
|
|
|
Cinder
|
|
------
|
|
|
|
.. _n-cinder-nddeadline:
|
|
|
|
Cinder New Backend Driver Deadline
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
The deadline for getting a new backend driver added to Cinder is 12th July,
|
|
2016. All review issues must be addressed and third party CI must be reporting
|
|
and stable with enough time for reviewers prior to the deadline. Meeting these
|
|
requirements on the 12th does not guarantee core reviewers will have enough
|
|
time to merge the driver.
|
|
|
|
.. _n-cinder-spec-freeze:
|
|
|
|
Cinder Spec Freeze
|
|
^^^^^^^^^^^^^^^^^^
|
|
|
|
All Cinder specs must be approved by 12th July, 2016.
|
|
|
|
.. _n-cinder-ff:
|
|
|
|
Cinder Feature Freeze
|
|
^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
The deadline for new features and driver functionality is 31 August, 2016. Any
|
|
changes past that date will be at the discretion of the core team.
|
|
|
|
Nova
|
|
----
|
|
|
|
For reference, these are the `Nova review priorities for Newton`_.
|
|
|
|
.. _Nova review priorities for Newton: https://specs.openstack.org/openstack/nova-specs/priorities/newton-priorities.html
|
|
|
|
.. _n-nova-non-prio-s-fr:
|
|
|
|
Nova non-priority spec approval freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
All non-priority Nova specs must be approved by June 2nd, 2016.
|
|
|
|
.. _n-nova-non-prio-ff:
|
|
|
|
Nova non-priority feature freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
The deadline for non-priority features is June 30th, 2016. There may be a round
|
|
of feature freeze exceptions but that will be at the discretion of the Nova
|
|
core team.
|
|
|
|
.. _n-nova-prio-spec-frz:
|
|
|
|
Nova priority spec approval freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
All priority Nova specs must be approved by August 4th, 2016. This is
|
|
intentionally after the Nova midcycle meetup for Newton so there is some time
|
|
for last minute adjustments to priority features.
|
|
|
|
Trove
|
|
-----
|
|
|
|
The deadlines below are specific to the Trove project.
|
|
|
|
.. _n-trove-spec-prop:
|
|
|
|
Trove Spec Proposal Deadline
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
Submit all Trove specs for the Newton release by the end of this week
|
|
(for review) in trove-specs repository.
|
|
|
|
.. _n-trove-spec-freeze:
|
|
|
|
Trove Spec Freeze
|
|
^^^^^^^^^^^^^^^^^
|
|
|
|
All Trove specs for the Newton release must be approved by the end of
|
|
this week.
|
|
|
|
.. _n-trove-guest-req:
|
|
|
|
Trove Guest Requirements Freeze:
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
Freeze the requirements for all guest agents by this date and make the
|
|
newton requirements file for guests.
|
|
|
|
.. _n-trove-cl-soft:
|
|
|
|
Trove Client Soft Freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
All major features for the python-troveclient must be reviewed and
|
|
approved by the end of this week, this gives us one additional week to
|
|
address any issues with dependencies.
|
|
|
|
.. _n-trove-ff:
|
|
|
|
Trove Feature Freeze
|
|
^^^^^^^^^^^^^^^^^^^^
|
|
|
|
All major Trove features and projects for Newton must be approved by
|
|
the end of this week.
|
|
|
|
This is the deadline for the Trove server, the python-troveclient and
|
|
all trove-dashboard changes.
|
|
|
|
Horizon
|
|
-------
|
|
|
|
The deadlines below are specific to the Horizon project.
|
|
|
|
.. _n-horizon-ff:
|
|
|
|
Horizon Feature Freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
The deadline for Horizon features for Newton. This is a week earlier than
|
|
the standard milestone to allow plugins time to sync before the standard
|
|
release.
|
|
|
|
Keystone
|
|
--------
|
|
|
|
.. _n-key-spec-pfreeze:
|
|
|
|
Keystone Spec Proposal Freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
The deadline for proposing a Keystone specification that will land in the
|
|
Newton development cycle.
|
|
|
|
.. _n-key-spec-freeze:
|
|
|
|
Keystone Spec Freeze
|
|
^^^^^^^^^^^^^^^^^^^^
|
|
|
|
The deadline for merging a Keystone Spec and approving a blueprint.
|
|
|
|
.. _n-key-fpf:
|
|
|
|
Keystone Feature Proposal Freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
The deadline for proposing code for an approved feature. The code must: show
|
|
functionality and be ready for review. Approved features that miss the deadline
|
|
will be moved to the backlog or the first milestone of the next release.
|
|
|
|
.. _n-key-ff:
|
|
|
|
Keystone Feature Freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
All approved features must be merged by this week. Please note, the Keystone
|
|
Feature Freeze date is aligned with :ref:`n-ff`.
|