Victoria Release Schedule
|
|
=========================
|
|
|
|
.. note::
|
|
|
|
Deadlines are generally the Thursday of the week on which they are noted
|
|
below. Exceptions to this policy will be explicitly mentioned in the event
|
|
description.
|
|
|
|
18 May 2020 - 16 October 2020 (22 weeks)
|
|
|
|
.. datatemplate::
|
|
:source: schedule.yaml
|
|
:template: schedule_table.tmpl
|
|
|
|
.. ics::
|
|
:source: schedule.yaml
|
|
:name: Victoria
|
|
|
|
`Subscribe to iCalendar file <schedule.ics>`_
|
|
|
|
Cross-project events
|
|
====================
|
|
|
|
.. _v-goals-research:
|
|
|
|
Victoria Goals Research
|
|
-----------------------
|
|
|
|
Pre-cycle planning and investigation into `the community-wide goals
|
|
for Victoria
|
|
<https://governance.openstack.org/tc/goals/selected/victoria/index.html>`__.
|
|
|
|
.. _v-ptg:
|
|
|
|
Virtual PTG
|
|
-----------
|
|
|
|
A virtual PTG will be held during this week. The Project Teams Gathering
|
|
provides and opportunity for teams to collaborate
|
|
and plan, and discuss requirements for future releases.
|
|
|
|
.. _v-1:
|
|
|
|
Victoria-1 milestone
|
|
--------------------
|
|
|
|
18 June, 2020 is the Victoria-1 milestone. See project-specific notes for
|
|
relevant deadlines.
|
|
|
|
.. _v-cycle-trail:
|
|
|
|
Ussuri Cycle-Trailing Release Deadline
|
|
--------------------------------------
|
|
|
|
All projects following the cycle-trailing release model must release
|
|
their Ussuri deliverables by 13 August, 2020.
|
|
|
|
.. _v-2:
|
|
|
|
Victoria-2 milestone
|
|
--------------------
|
|
|
|
30 July, 2020 is the Victoria-2 milestone. See project-specific notes for
|
|
relevant deadlines.
|
|
|
|
.. _v-final-lib:
|
|
|
|
Final release for non-client libraries
|
|
--------------------------------------
|
|
|
|
Libraries that are not client libraries (Oslo and others) should issue their
|
|
final release during this week. That allows to give time for last-minute
|
|
changes before feature freeze.
|
|
|
|
.. _v-3:
|
|
|
|
Victoria-3 milestone
|
|
--------------------
|
|
|
|
10 September, 2020 is the Victoria-3 milestone. See project-specific notes for
|
|
relevant deadlines.
|
|
|
|
.. _v-goals-complete:
|
|
|
|
Victoria Community Goals Completed
|
|
----------------------------------
|
|
|
|
Teams should prepare their documentation for completing `the
|
|
community-wide goals for Victoria
|
|
<https://governance.openstack.org/tc/goals/selected/victoria/index.html>`__.
|
|
|
|
.. _v-ff:
|
|
|
|
Feature freeze
|
|
--------------
|
|
|
|
The Victoria-3 milestone marks feature freeze for projects following the
|
|
`release:cycle-with-rc`_ model. No featureful patch should be landed
|
|
after this point. Exceptions may be granted by the project PTL.
|
|
|
|
.. _release:cycle-with-rc: https://releases.openstack.org/reference/release_models.html#cycle-with-rc
|
|
|
|
.. _v-rf:
|
|
|
|
Requirements freeze
|
|
-------------------
|
|
|
|
After the Victoria-3 milestone, only critical requirements and constraints
|
|
changes will be allowed. Freezing our requirements list gives packagers
|
|
downstream an opportunity to catch up and prepare packages for everything
|
|
necessary for distributions of the upcoming release. The requirements remain
|
|
frozen until the stable branches are created, with the release candidates.
|
|
|
|
.. _v-final-clientlib:
|
|
|
|
Final release for client libraries
|
|
----------------------------------
|
|
|
|
Client libraries should issue their final release during this week, to match
|
|
feature freeze.
|
|
|
|
.. _v-soft-sf:
|
|
|
|
Soft StringFreeze
|
|
-----------------
|
|
|
|
You are no longer allowed to accept proposed changes containing modifications
|
|
in user-facing strings. Such changes should be rejected by the review team and
|
|
postponed until the next series development opens (which should happen when RC1
|
|
is published).
|
|
|
|
.. _v-mf:
|
|
|
|
Membership Freeze
|
|
-----------------
|
|
|
|
Projects must participate in at least two milestones in order to be considered
|
|
part of the release. Projects made official after the second milestone, or
|
|
which fail to produce milestone releases for at least one of the first and
|
|
second milestones as well as the third milestone, are therefore not considered
|
|
part of the release for the cycle. This does not apply to cycle-trailing
|
|
packaging / lifecycle management projects.
|
|
|
|
.. _v-rc1:
|
|
|
|
RC1 target week
|
|
---------------
|
|
|
|
The week of 21 September is the target date for projects following the
|
|
`release:cycle-with-rc`_ model to issue their first release candidate.
|
|
|
|
.. _v-hard-sf:
|
|
|
|
Hard StringFreeze
|
|
-----------------
|
|
|
|
This happens when the RC1 for the project is tagged. At this point, ideally
|
|
no strings are changed (or added, or removed), to give translators time to
|
|
finish up their efforts.
|
|
|
|
.. _v-finalrc:
|
|
|
|
Final RCs and intermediary releases
|
|
-----------------------------------
|
|
|
|
The week of 5 October is the last week to issue release candidates or
|
|
intermediary releases before release week. During release week, only
|
|
final-release-critical releases will be accepted (at the discretion of the
|
|
release team).
|
|
|
|
.. _v-final:
|
|
|
|
Victoria release
|
|
----------------
|
|
|
|
The Victoria coordinated release will happen on Wednesday, 14 October, 2020.
|
|
|
|
.. _v-summit:
|
|
|
|
Open Infrastructure Summit
|
|
--------------------------
|
|
|
|
The virtual Open Infrastructure Summit will take place October 19-23.
|
|
|
|
.. _v-cycle-highlights:
|
|
|
|
Cycle Highlights
|
|
---------------------
|
|
|
|
Cycle highlights need to be added to the release deliverables by feature
|
|
freeze to be included in any marketing release messaging.
|
|
Highlights may be added after this point, but they will likely only be
|
|
useful for historical purposes.
|
|
|
|
See the `Project Team Guide`_ for more details and instructions on adding
|
|
these highlights.
|
|
|
|
.. _Project Team Guide: https://docs.openstack.org/project-team-guide/release-management.html#cycle-highlights
|
|
|
|
|
|
Project-specific events
|
|
=======================
|
|
|
|
Cinder
|
|
------
|
|
|
|
.. _v-cinder-spec-freeze:
|
|
|
|
Cinder Spec Freeze
|
|
^^^^^^^^^^^^^^^^^^
|
|
|
|
All Cinder Specs for features to be implemented in Victoria must be approved by
|
|
Wednesday 1 July 2020 (23:59 UTC).
|
|
|
|
.. _v-cinder-driver-deadline:
|
|
|
|
Cinder New Driver Merge Deadline
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
The deadline for merging a new backend driver to Cinder for the Victoria
|
|
release is Thursday 30 July 2020 (23:59 UTC). New drivers must be (a) code
|
|
complete including unit tests, (b) merged into the code repository, and (c)
|
|
must have a 3rd Party CI running reliably. (The idea is that new drivers will
|
|
be included in a release at the second milestone and thus be easily available
|
|
for downstream testing, documentation feedback, etc.)
|
|
|
|
.. _v-cinder-target-driver-deadline:
|
|
|
|
Cinder New Target Driver Merge Deadline
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
The deadline for merging a new target driver to Cinder for the Victoria release
|
|
is Thursday 30 July 2020 (23:59 UTC). New target drivers must be (a) code
|
|
complete including unit tests, (b) merged into the code repository, and (c)
|
|
must have a 3rd Party CI running reliably. (The idea is that new drivers will
|
|
be included in a release at the second milestone and thus be easily available
|
|
for downstream testing, documentation feedback, etc.)
|
|
|
|
.. _v-cinder-feature-checkpoint:
|
|
|
|
Cinder New Feature Status Checkpoint
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
If your new Cinder feature requires client support, keep in mind that the final
|
|
release for client libraries is in three weeks. Thus your Cinder feature
|
|
should be substantially complete with unit tests by this time so that any
|
|
client changes can be reviewed, tested, and merged before 10 September. Keep
|
|
in mind that 7 September is a holiday for many Cinder core reviewers, so we
|
|
will have reduced bandwith around the time of the Feature Freeze. So please
|
|
plan ahead.
|
|
|
|
.. _v-cinder-driver-features-declaration:
|
|
|
|
Cinder Driver Features Declaration
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
New features added to Cinder drivers must be merged at the time of the
|
|
OpenStack-wide Feature Freeze, which is coming up in three weeks. During this
|
|
week, you should post a blueprint in Launchpad listing the Gerrit reviews of
|
|
features you'd like to land in Victoria. (You can look among the Ussuri
|
|
blueprints for examples; contact the PTL if you have any questions.) This will
|
|
help the team prioritize reviews and give you candid early feedback on whether
|
|
the features look ready. Due to the 7 September holiday in the USA, there will
|
|
be reduced reviewing bandwidth right around the Feature Freeze, so it will pay
|
|
to plan ahead.
|
|
|
|
.. _v-cinder-ci-checkpoint:
|
|
|
|
Cinder 3rd Party CI Compliance Checkpoint
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
This is a reminder that in order for a Cinder driver to be considered
|
|
'supported' in the Victoria release, its third party CI must be running
|
|
properly when the Cinder team does a final compliance check around the
|
|
time of the third milestone. See the `Driver Compliance
|
|
<https://docs.openstack.org/cinder/latest/drivers-all-about.html#driver-compliance>`_
|
|
section of the Cinder Documentation for details.
|
|
|
|
Manila
|
|
------
|
|
|
|
.. _v-manila-spec-freeze:
|
|
|
|
Manila Spec Freeze
|
|
^^^^^^^^^^^^^^^^^^
|
|
|
|
All Manila specs targeted to Victoria must be approved by the end of the week.
|
|
|
|
.. _v-manila-new-driver-deadline:
|
|
|
|
Manila New Driver Deadline
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
By the end of the week all new backend drivers for Manila must be substantially
|
|
complete, with unit tests, and passing 3rd party CI. Drivers do not have to
|
|
actually merge until feature freeze.
|
|
|
|
.. _v-manila-fpfreeze:
|
|
|
|
Manila Feature Proposal Freeze
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
All new Manila features must be proposed and substantially completed, with
|
|
unit, functional and integration tests by the end of the week.
|
|
|
|
|
|
Oslo
|
|
----
|
|
|
|
.. _v-oslo-feature-freeze:
|
|
|
|
Oslo Feature Freeze
|
|
^^^^^^^^^^^^^^^^^^^
|
|
|
|
All new Oslo features must be proposed and substantially complete, with unit
|
|
tests by the end of the week.
|