Host Software Deployment (USM)
Story: 2010676 Task: 50141 Change-Id: I2ab679259b22c71d1e544a036d2cfa5cc8f81a2c Signed-off-by: Ngairangbam Mili <ngairangbam.mili@windriver.com>
This commit is contained in:
		@@ -535,45 +535,18 @@
 | 
			
		||||
.. |apply-update-to-the-openstack-application| replace:: :ref:`Apply Update to the OpenStack Application <apply-update-to-the-openstack-application>`
 | 
			
		||||
.. |software-updates-and-upgrades-overview| replace:: :ref:`Overview <software-updates-and-upgrades-overview>`
 | 
			
		||||
.. |index-updates-e3b970bb69ce| replace:: :ref:`Updates and Upgrades <index-updates-e3b970bb69ce>`
 | 
			
		||||
.. |update-orchestration-cli| replace:: :ref:`Update Orchestration CLI <update-orchestration-cli>`
 | 
			
		||||
.. |about-kubernetes-orchestrated-upgrades| replace:: :ref:`About Kubernetes Version Upgrade Cloud Orchestration <about-kubernetes-orchestrated-upgrades>`
 | 
			
		||||
.. |managing-software-updates| replace:: :ref:`Manage Software Updates <managing-software-updates>`
 | 
			
		||||
.. |update-status-and-lifecycle| replace:: :ref:`Update Status and Lifecycle <update-status-and-lifecycle>`
 | 
			
		||||
.. |the-kubernetes-update-orchestration-process| replace:: :ref:`Kubernetes Version Upgrade Cloud Orchestration Overview <the-kubernetes-update-orchestration-process>`
 | 
			
		||||
.. |identifying-the-software-version-and-update-level-using-horizon| replace:: :ref:`Identify the Software Version and Update Level Using Horizon <identifying-the-software-version-and-update-level-using-horizon>`
 | 
			
		||||
.. |removing-reboot-required-software-updates| replace:: :ref:`Remove Reboot-Required Software Updates <removing-reboot-required-software-updates>`
 | 
			
		||||
.. |installing-reboot-required-software-updates-using-horizon| replace:: :ref:`Install Reboot-Required Software Updates Using Horizon <installing-reboot-required-software-updates-using-horizon>`
 | 
			
		||||
.. |performing-an-orchestrated-upgrade| replace:: :ref:`Perform an Orchestrated Upgrade <performing-an-orchestrated-upgrade>`
 | 
			
		||||
.. |orchestration-upgrade-overview| replace:: :ref:`Upgrade Orchestration Overview <orchestration-upgrade-overview>`
 | 
			
		||||
.. |handle-firmware-update-orchestration-failures| replace:: :ref:`Handle Firmware Update Orchestration Failures <handle-firmware-update-orchestration-failures>`
 | 
			
		||||
.. |configuring-update-orchestration| replace:: :ref:`Configure Update Orchestration <configuring-update-orchestration>`
 | 
			
		||||
.. |manual-upgrade-overview| replace:: :ref:`Manual Upgrade Overview <manual-upgrade-overview>`
 | 
			
		||||
.. |upgrading-all-in-one-simplex| replace:: :ref:`Upgrade All-in-One Simplex <upgrading-all-in-one-simplex>`
 | 
			
		||||
.. |software-update-space-reclamation| replace:: :ref:`Software Update Space Reclamation <software-update-space-reclamation>`
 | 
			
		||||
.. |aborting-simplex-system-upgrades| replace:: :ref:`Abort Simplex System Upgrades <aborting-simplex-system-upgrades>`
 | 
			
		||||
.. |rolling-back-a-software-upgrade-after-the-second-controller-upgrade| replace:: :ref:`Roll Back a Software Upgrade After the Second Controller Upgrade <rolling-back-a-software-upgrade-after-the-second-controller-upgrade>`
 | 
			
		||||
.. |overview-of-upgrade-abort-procedure| replace:: :ref:`Overview of Upgrade Abort Procedure <overview-of-upgrade-abort-procedure>`
 | 
			
		||||
.. |rolling-back-a-software-upgrade-before-the-second-controller-upgrade| replace:: :ref:`Roll Back a Software Upgrade Before the Second Controller Upgrade <rolling-back-a-software-upgrade-before-the-second-controller-upgrade>`
 | 
			
		||||
.. |firmware-update-operations-requiring-manual-migration| replace:: :ref:`Firmware Update Operations Requiring Manual Migration <firmware-update-operations-requiring-manual-migration>`
 | 
			
		||||
.. |reclaiming-disk-space| replace:: :ref:`Reclaim Disk Space <reclaiming-disk-space>`
 | 
			
		||||
.. |firmware-update-orchestration-using-the-cli| replace:: :ref:`Firmware Update Orchestration Using the CLI <firmware-update-orchestration-using-the-cli>`
 | 
			
		||||
.. |configure-firmware-update-orchestration| replace:: :ref:`Configure Firmware Update Orchestration <configure-firmware-update-orchestration>`
 | 
			
		||||
.. |configuring-kubernetes-update-orchestration| replace:: :ref:`Create Kubernetes Version Upgrade Cloud Orchestration Strategy <configuring-kubernetes-update-orchestration>`
 | 
			
		||||
.. |identifying-the-software-version-and-update-level-using-the-cli| replace:: :ref:`Identify the Software Version and Update Level Using the CLI <identifying-the-software-version-and-update-level-using-the-cli>`
 | 
			
		||||
.. |software-upgrades| replace:: :ref:`Software Upgrades <software-upgrades>`
 | 
			
		||||
.. |performing-an-orchestrated-upgrade-using-the-cli| replace:: :ref:`Perform an Orchestrated Upgrade Using the CLI <performing-an-orchestrated-upgrade-using-the-cli>`
 | 
			
		||||
.. |installing-software-updates-before-initial-commissioning| replace:: :ref:`Install Software Updates Before Initial Commissioning <installing-software-updates-before-initial-commissioning>`
 | 
			
		||||
.. |update-orchestration-overview| replace:: :ref:`Update Orchestration Overview <update-orchestration-overview>`
 | 
			
		||||
.. |in-service-versus-reboot-required-software-updates| replace:: :ref:`In-Service Versus Reboot-Required Software Updates <in-service-versus-reboot-required-software-updates>`
 | 
			
		||||
.. |installing-in-service-software-updates-using-the-cli| replace:: :ref:`Install In-Service Software Updates Using the CLI <installing-in-service-software-updates-using-the-cli>`
 | 
			
		||||
.. |installing-in-service-software-update-using-horizon| replace:: :ref:`Install In-Service Software Update Using Horizon <installing-in-service-software-update-using-horizon>`
 | 
			
		||||
.. |populating-the-storage-area| replace:: :ref:`Populate the Storage Area <populating-the-storage-area>`
 | 
			
		||||
.. |configuring-kubernetes-multi-version-upgrade-orchestration-aio-b0b59a346466| replace:: :ref:`Configure Kubernetes Multi-Version Upgrade Cloud Orchestration for AIO-SX <configuring-kubernetes-multi-version-upgrade-orchestration-aio-b0b59a346466>`
 | 
			
		||||
.. |manual-kubernetes-components-upgrade| replace:: :ref:`Manual Kubernetes Version Upgrade <manual-kubernetes-components-upgrade>`
 | 
			
		||||
.. |overview-of-firmware-update-orchestration| replace:: :ref:`Overview <overview-of-firmware-update-orchestration>`
 | 
			
		||||
.. |handling-kubernetes-update-orchestration-failures| replace:: :ref:`Handle Kubernetes Version Upgrade Orchestration Failures <handling-kubernetes-update-orchestration-failures>`
 | 
			
		||||
.. |upgrading-all-in-one-duplex-or-standard| replace:: :ref:`Upgrade All-in-One Duplex / Standard <upgrading-all-in-one-duplex-or-standard>`
 | 
			
		||||
.. |installing-reboot-required-software-updates-using-the-cli| replace:: :ref:`Install Reboot-Required Software Updates Using the CLI <installing-reboot-required-software-updates-using-the-cli>`
 | 
			
		||||
.. |the-firmware-update-orchestration-process| replace:: :ref:`The Firmware Update Orchestration Process <the-firmware-update-orchestration-process>`
 | 
			
		||||
.. |software-updates-and-upgrades-software-updates| replace:: :ref:`Software Updates <software-updates-and-upgrades-software-updates>`
 | 
			
		||||
.. |manual-kubernetes-multi-version-upgrade-in-aio-sx-13e05ba19840| replace:: :ref:`Manual Kubernetes Multi-Version Upgrade in AIO-SX <manual-kubernetes-multi-version-upgrade-in-aio-sx-13e05ba19840>`
 | 
			
		||||
 
 | 
			
		||||
@@ -329,8 +329,9 @@ individual subclouds.
 | 
			
		||||
 | 
			
		||||
    **alarm restriction type**
 | 
			
		||||
        relaxed or strict — determines whether the orchestration is aborted for
 | 
			
		||||
        alarms that are not management-affecting. For more information, refer
 | 
			
		||||
        to |updates-doc|: :ref:`configuring-update-orchestration`.
 | 
			
		||||
        alarms that are not management-affecting.
 | 
			
		||||
 | 
			
		||||
    .. For more information, refer to |updates-doc|: :ref:`configuring-update-orchestration`.
 | 
			
		||||
 | 
			
		||||
    **default instance action**
 | 
			
		||||
        .. note::
 | 
			
		||||
 
 | 
			
		||||
@@ -77,8 +77,6 @@ Follow the steps below to manually upgrade the system controller:
 | 
			
		||||
          :start-after: wrsbegin
 | 
			
		||||
          :end-before: wrsend
 | 
			
		||||
 | 
			
		||||
    For more information, see |updates-doc|: :ref:`Managing Software Updates <managing-software-updates>`.
 | 
			
		||||
 | 
			
		||||
#.  Confirm that the system is healthy.
 | 
			
		||||
 | 
			
		||||
    Check the current system health status, resolve any alarms and other issues
 | 
			
		||||
 
 | 
			
		||||
@@ -50,8 +50,9 @@ Update the RegionOne
 | 
			
		||||
 | 
			
		||||
To fully deploy the Central Cloud's RegionOne through Horizon:
 | 
			
		||||
 | 
			
		||||
#.  Upload and apply updates to SystemController region, for more details see
 | 
			
		||||
    :ref:`configuring-update-orchestration`.
 | 
			
		||||
#.  Upload and apply updates to SystemController region.
 | 
			
		||||
 | 
			
		||||
    .. For more details see :ref:`configuring-update-orchestration`.
 | 
			
		||||
 | 
			
		||||
#.  Update the RegionOne region:
 | 
			
		||||
 | 
			
		||||
@@ -69,11 +70,10 @@ To fully deploy the Central Cloud's RegionOne through Horizon:
 | 
			
		||||
 | 
			
		||||
    #.  Click **Apply Strategy** to apply the update strategy.
 | 
			
		||||
 | 
			
		||||
To update the RegionOne using the CLI see :ref:`update-orchestration-cli`.
 | 
			
		||||
.. To update the RegionOne using the CLI see :ref:`update-orchestration-cli`.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    This procedure closely resembles what is described in
 | 
			
		||||
   .. This procedure closely resembles what is described in
 | 
			
		||||
    :ref:`configuring-update-orchestration`. The key difference lies in the
 | 
			
		||||
    necessity to preselect RegionOne.
 | 
			
		||||
 | 
			
		||||
@@ -81,4 +81,4 @@ To update the RegionOne using the CLI see :ref:`update-orchestration-cli`.
 | 
			
		||||
 | 
			
		||||
To update the software on the System Controller and subclouds, you must use the
 | 
			
		||||
|prod-dc| Update Orchestration. For more information, see
 | 
			
		||||
:ref:`update-orchestration-of-central-clouds-regionone-and-subclouds`.
 | 
			
		||||
:ref:`update-orchestration-of-central-clouds-regionone-and-subclouds`.
 | 
			
		||||
 
 | 
			
		||||
@@ -1,110 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. syj1592947192958
 | 
			
		||||
.. _aborting-simplex-system-upgrades:
 | 
			
		||||
 | 
			
		||||
=============================
 | 
			
		||||
Abort Simplex System Upgrades
 | 
			
		||||
=============================
 | 
			
		||||
 | 
			
		||||
You can abort a Simplex System upgrade before or after upgrading controller-0.
 | 
			
		||||
The upgrade abort procedure can only be applied before the
 | 
			
		||||
:command:`upgrade-complete` command is issued. Once this command is issued the
 | 
			
		||||
upgrade can not be aborted. If you must return to the previous release, then
 | 
			
		||||
restore the system using the backup data taken prior to the upgrade.
 | 
			
		||||
 | 
			
		||||
Before starting, verify the upgrade data under ``/opt/platform-backup``. This
 | 
			
		||||
data must be present to perform the abort process.
 | 
			
		||||
 | 
			
		||||
.. _aborting-simplex-system-upgrades-section-N10025-N1001B-N10001:
 | 
			
		||||
 | 
			
		||||
.. contents:: |minitoc|
 | 
			
		||||
   :local:
 | 
			
		||||
   :depth: 1
 | 
			
		||||
 | 
			
		||||
-----------------------------
 | 
			
		||||
Before upgrading controller-0
 | 
			
		||||
-----------------------------
 | 
			
		||||
 | 
			
		||||
.. _aborting-simplex-system-upgrades-ol-nlw-zbp-xdb:
 | 
			
		||||
 | 
			
		||||
#.  Abort the upgrade with the upgrade-abort command.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)$ system upgrade-abort
 | 
			
		||||
 | 
			
		||||
    The upgrade state is set to ``aborting``. Once this is executed, it cannot
 | 
			
		||||
    be cancelled; the upgrade must be completely aborted.
 | 
			
		||||
 | 
			
		||||
#.  Complete the upgrade.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)$ system upgrade-complete
 | 
			
		||||
 | 
			
		||||
    At this time any upgrade data generated as part of the upgrade-start
 | 
			
		||||
    command will be deleted. This includes the upgrade data in
 | 
			
		||||
    ``/opt/platform-backup``.
 | 
			
		||||
 | 
			
		||||
.. _aborting-simplex-system-upgrades-section-N10063-N1001B-N10001:
 | 
			
		||||
 | 
			
		||||
----------------------------
 | 
			
		||||
After upgrading controller-0
 | 
			
		||||
----------------------------
 | 
			
		||||
 | 
			
		||||
After controller-0 has been upgraded, it is possible to roll back the software
 | 
			
		||||
upgrade. This involves performing a system restore with the previous release.
 | 
			
		||||
 | 
			
		||||
.. _aborting-simplex-system-upgrades-ol-jmw-kcp-xdb:
 | 
			
		||||
 | 
			
		||||
#.  Install the previous release of |prod-long| Simplex software via network or
 | 
			
		||||
    USB manually.
 | 
			
		||||
 | 
			
		||||
#.  Verify and configure IP connectivity. External connectivity is required to
 | 
			
		||||
    run the Ansible restore playbook. The |prod-long| boot image will |DHCP| out
 | 
			
		||||
    all interfaces so the server may have obtained an IP address and have
 | 
			
		||||
    external IP connectivity if a |DHCP| server is present in your environment.
 | 
			
		||||
    Verify this using the :command:`ip addr` command. Otherwise, manually
 | 
			
		||||
    configure an IP address and default IP route.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
 | 
			
		||||
        If there are patches on the |AIO-SX| system prior to the upgrade,
 | 
			
		||||
        Ansible restore playbook will install the patches and cause a reboot
 | 
			
		||||
        of the system. The reboot will lead to the loss of IP connectivity
 | 
			
		||||
        configuration. Verify and re-configure IP connectivity and
 | 
			
		||||
        re-run the Ansible restore playbook to complete the platform restore.
 | 
			
		||||
 | 
			
		||||
#.  Restore the system data. The restore is preserved in ``/opt/platform-backup``.
 | 
			
		||||
 | 
			
		||||
    The system will be restored to the state when the :command:`upgrade-start`
 | 
			
		||||
    command was issued. Follow the process in :ref:`Run Restore Playbook Locally
 | 
			
		||||
    on the Controller <running-restore-playbook-locally-on-the-controller>`.
 | 
			
		||||
 | 
			
		||||
    Specify the upgrade data filename as `backup_filename` and the
 | 
			
		||||
    `initial_backup_dir` as ``/opt/platform-backup``.
 | 
			
		||||
 | 
			
		||||
    The user images will also need to be restored as described in the
 | 
			
		||||
    Postrequisites section.
 | 
			
		||||
 | 
			
		||||
#.  Unlock controller-0
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)$ system host-unlock controller-0
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
#.  Abort the upgrade with the :command:`upgrade-abort` command.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)$ system upgrade-abort
 | 
			
		||||
 | 
			
		||||
    The upgrade state is set to ``aborting``. Once this is executed, it cannot
 | 
			
		||||
    be cancelled; the upgrade must be completely aborted.
 | 
			
		||||
 | 
			
		||||
#.  Complete the upgrade.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)$ system upgrade-complete
 | 
			
		||||
@@ -39,8 +39,9 @@ ignored even when the default strict restrictions are selected:
 | 
			
		||||
 | 
			
		||||
-   Hosts that need to be updated must be in the ``unlocked-enabled`` state.
 | 
			
		||||
 | 
			
		||||
-   The firmware update image must be in the ``applied`` state. For more
 | 
			
		||||
    information, see :ref:`Managing Software Updates <managing-software-updates>`.
 | 
			
		||||
-   The firmware update image must be in the ``applied`` state.
 | 
			
		||||
 | 
			
		||||
    .. For more information, see :ref:`Managing Software Updates <managing-software-updates>`.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
 
 | 
			
		||||
@@ -1,194 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. gep1552920534437
 | 
			
		||||
.. _configuring-update-orchestration:
 | 
			
		||||
 | 
			
		||||
==============================
 | 
			
		||||
Configure Update Orchestration
 | 
			
		||||
==============================
 | 
			
		||||
 | 
			
		||||
You can configure update orchestration using the Horizon Web interface.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |context|
 | 
			
		||||
 | 
			
		||||
The update orchestration interface is found in Horizon on the Patch
 | 
			
		||||
Orchestration tab, available from **Admin** \> **Platform** \> **Software
 | 
			
		||||
Management** in the left-hand pane.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
    Management-affecting alarms cannot be ignored at the indicated severity
 | 
			
		||||
    level or higher by using relaxed alarm rules during an orchestrated update
 | 
			
		||||
    operation. For a list of management-affecting alarms, see |fault-doc|:
 | 
			
		||||
    :ref:`Alarm Messages <100-series-alarm-messages-starlingx>`. To display
 | 
			
		||||
    management-affecting active alarms, use the following command:
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ fm alarm-list --mgmt_affecting
 | 
			
		||||
 | 
			
		||||
    During an orchestrated update operation, the following alarms are ignored
 | 
			
		||||
    even when strict restrictions are selected:
 | 
			
		||||
 | 
			
		||||
    -   200.001, Maintenance host lock alarm
 | 
			
		||||
 | 
			
		||||
    -   900.001, Patch in progress
 | 
			
		||||
 | 
			
		||||
    -   900.005, Upgrade in progress
 | 
			
		||||
 | 
			
		||||
    -   900.101, Software patch auto apply in progress
 | 
			
		||||
 | 
			
		||||
.. _configuring-update-orchestration-ul-qhy-q1p-v1b:
 | 
			
		||||
 | 
			
		||||
.. rubric:: |prereq|
 | 
			
		||||
 | 
			
		||||
You cannot successfully create an update (patch) strategy if any hosts show
 | 
			
		||||
**Patch Current** = **Pending**, indicating that the update status of these
 | 
			
		||||
hosts has not yet been updated. The creation attempt fails, and you must try
 | 
			
		||||
again. You can use :command:`sw-patch query-hosts` to review the current update
 | 
			
		||||
status before creating an update strategy.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#.  Upload and apply your updates as described in :ref:`Manage Software Updates
 | 
			
		||||
    <managing-software-updates>` (do not lock any hosts or use
 | 
			
		||||
    :command:`host-install` to install the updates on any hosts).
 | 
			
		||||
 | 
			
		||||
#.  Select **Platform** \> **Software Management**, then select the **Patch
 | 
			
		||||
    Orchestration** tab.
 | 
			
		||||
 | 
			
		||||
#.  Click the **Create Strategy** button.
 | 
			
		||||
 | 
			
		||||
    The Create Strategy dialog appears.
 | 
			
		||||
 | 
			
		||||
    .. image:: figures/zcj1567178380908.png
 | 
			
		||||
       :height: 365px
 | 
			
		||||
       :width: 475px
 | 
			
		||||
 | 
			
		||||
#.  Create an update strategy by specifying settings for the parameters in the
 | 
			
		||||
    Create Strategy dialog box.
 | 
			
		||||
 | 
			
		||||
    **Description**
 | 
			
		||||
        Provides information about current alarms, including whether an alarm
 | 
			
		||||
        is Management Affecting.
 | 
			
		||||
 | 
			
		||||
    **Controller Apply Type**
 | 
			
		||||
        -   Serial (default): controllers will be updated one at a time
 | 
			
		||||
            (standby controller first)
 | 
			
		||||
 | 
			
		||||
        -   Ignore: controllers will not be updated
 | 
			
		||||
 | 
			
		||||
    **Storage Apply Type**
 | 
			
		||||
        -   Serial (default): storage hosts will be updated one at a time
 | 
			
		||||
 | 
			
		||||
        -   Parallel: storage hosts will be updated in parallel, ensuring that
 | 
			
		||||
            only one storage node in each replication group is updated at a
 | 
			
		||||
            time.
 | 
			
		||||
 | 
			
		||||
        -   Ignore: storage hosts will not be updated
 | 
			
		||||
 | 
			
		||||
    **Worker Apply Type**
 | 
			
		||||
        -   Serial (default): worker hosts will be updated one at a time
 | 
			
		||||
 | 
			
		||||
        -   Parallel: worker hosts will be updated in parallel
 | 
			
		||||
 | 
			
		||||
            -   At most, **Parallel** will be updated at the same time.
 | 
			
		||||
 | 
			
		||||
            -   For a reboot parallel update only, worker hosts with no pods
 | 
			
		||||
                are updated before worker hosts with pods.
 | 
			
		||||
 | 
			
		||||
        -   Parallel: specify the maximum worker hosts to update in parallel
 | 
			
		||||
            (minimum: 2, maximum: 100)
 | 
			
		||||
 | 
			
		||||
        -   Ignore: Worker hosts will not be updated
 | 
			
		||||
 | 
			
		||||
    **Default Instance Action**
 | 
			
		||||
        This parameter only applies for systems with the |prefix|-openstack
 | 
			
		||||
        application.
 | 
			
		||||
 | 
			
		||||
        -   Stop-Start (default): hosted applications VMs will be stopped
 | 
			
		||||
            before a host is updated (applies to reboot updates only)
 | 
			
		||||
 | 
			
		||||
        -   Migrate: hosted application VMs will be migrated off a host before
 | 
			
		||||
            it is updated (applies to reboot updates only).
 | 
			
		||||
 | 
			
		||||
    **Alarm Restrictions**
 | 
			
		||||
        This option lets you specify how update orchestration behaves when
 | 
			
		||||
        alarms are present.
 | 
			
		||||
 | 
			
		||||
        You can use the CLI command :command:`fm alarm-list --mgmt_affecting`
 | 
			
		||||
        to view the alarms that are management affecting.
 | 
			
		||||
 | 
			
		||||
        **Strict**
 | 
			
		||||
           The default strict option will result in update orchestration
 | 
			
		||||
           failing if there are any alarms present in the system (except for a
 | 
			
		||||
           small list of alarms).
 | 
			
		||||
 | 
			
		||||
        **Relaxed**
 | 
			
		||||
           This option allows orchestration to proceed if alarms are present,
 | 
			
		||||
           as long as none of these alarms are management affecting.
 | 
			
		||||
 | 
			
		||||
#.  Click **Create Strategy** to save the update orchestration strategy.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        The update orchestration process ensures that no hosts are reported as
 | 
			
		||||
        **Patch Status** = **Pending**. If any hosts have this status, the
 | 
			
		||||
        creation attempt fails with an error message. Wait a few minutes and
 | 
			
		||||
        try again. You can also use :command:`sw-patch query-hosts` to review
 | 
			
		||||
        the current update status.
 | 
			
		||||
 | 
			
		||||
    Examine the update strategy. Pay careful attention to:
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
    -   The sets of hosts that will be updated together in each stage.
 | 
			
		||||
 | 
			
		||||
    -   The sets of hosted application pods that will be impacted in each stage.
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
    The update strategy has one or more stages, with each stage consisting of
 | 
			
		||||
    one or more hosts to be updated at the same time. Each stage is split into
 | 
			
		||||
    steps (for example, :command:`query-alarms`, :command:`lock-hosts`,
 | 
			
		||||
    :command:`sw-patch-hosts`). Note the following about stages:
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
 | 
			
		||||
        -   Controller hosts are updated first, followed by storage hosts and
 | 
			
		||||
            then worker hosts.
 | 
			
		||||
 | 
			
		||||
        -   Worker hosts with no hosted application pods are updated before
 | 
			
		||||
            worker hosts with hosted application pods.
 | 
			
		||||
 | 
			
		||||
        -   The final step in each stage is ``system-stabilize``, which waits
 | 
			
		||||
            for a period of time (up to several minutes) and ensures that the
 | 
			
		||||
            system is free of alarms. This ensures that the update orchestrator
 | 
			
		||||
            does not continue to update more hosts if the update application has
 | 
			
		||||
            caused an issue resulting in an alarm.
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
#.  Click the **Apply Strategy** button to apply the update strategy. You can
 | 
			
		||||
    optionally apply a single stage at a time by clicking the **Apply Stage**
 | 
			
		||||
    button.
 | 
			
		||||
 | 
			
		||||
    When applying a single stage, you can only apply the next stage; you cannot
 | 
			
		||||
    skip stages.
 | 
			
		||||
 | 
			
		||||
#.  To abort the update, click the **Abort Strategy** button.
 | 
			
		||||
 | 
			
		||||
    -   While an update-strategy is being applied, it can be aborted. This
 | 
			
		||||
        results in:
 | 
			
		||||
 | 
			
		||||
        -   The current step being allowed to complete.
 | 
			
		||||
 | 
			
		||||
        -   If necessary an abort phase will be created and applied, which will
 | 
			
		||||
            attempt to unlock any hosts that were locked.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        If an update strategy is aborted after hosts were locked, but before
 | 
			
		||||
        they were updated, the hosts will not be unlocked, as this would result
 | 
			
		||||
        in the updates being installed. You must either install the updates on
 | 
			
		||||
        the hosts or remove the updates before unlocking the hosts.
 | 
			
		||||
 | 
			
		||||
#.  Delete the update strategy.
 | 
			
		||||
 | 
			
		||||
    After an update strategy has been applied (or aborted) it must be deleted
 | 
			
		||||
    before another update strategy can be created. If an update strategy
 | 
			
		||||
    application fails, you must address the issue that caused the failure, then
 | 
			
		||||
    delete and re-create the strategy before attempting to apply it again.
 | 
			
		||||
@@ -1,35 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. kiv1552920729184
 | 
			
		||||
.. _identifying-the-software-version-and-update-level-using-horizon:
 | 
			
		||||
 | 
			
		||||
============================================================
 | 
			
		||||
Identify the Software Version and Update Level Using Horizon
 | 
			
		||||
============================================================
 | 
			
		||||
 | 
			
		||||
You can view the current software version and update level from the Horizon Web
 | 
			
		||||
interface. The system type is also shown.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#.  In the |prod| Horizon, open the **System Configuration** page.
 | 
			
		||||
 | 
			
		||||
    The **System Configuration** page is available from **Admin** \>
 | 
			
		||||
    **Platform** \> **System Configuration** in the left-hand pane.
 | 
			
		||||
 | 
			
		||||
#.  Select the **Systems** tab to view the software version.
 | 
			
		||||
 | 
			
		||||
    The software version is shown in the **Version** field.
 | 
			
		||||
 | 
			
		||||
    The type of system selected at installation (Standard or All-in-one) is
 | 
			
		||||
    shown in the **System Type** field. The mode (**simplex**, **duplex**, or
 | 
			
		||||
    **standard**) is shown in the **System Mode** field.
 | 
			
		||||
 | 
			
		||||
#.  In the |prod| Horizon interface, open the **Software Management** page.
 | 
			
		||||
 | 
			
		||||
    The **Software Management** page is available from **Admin** \> **Platform**
 | 
			
		||||
    \> **Software Management** in the left-hand pane.
 | 
			
		||||
 | 
			
		||||
#.  Select the **Patches** tab to view update information.
 | 
			
		||||
 | 
			
		||||
    The **Patches** tab shows the Patch ID, a Summary description, the Status
 | 
			
		||||
    of the Patch, and an Actions button to use to select an appropriate action.
 | 
			
		||||
@@ -1,58 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. lob1552920716157
 | 
			
		||||
.. _identifying-the-software-version-and-update-level-using-the-cli:
 | 
			
		||||
 | 
			
		||||
============================================================
 | 
			
		||||
Identify the Software Version and Update Level Using the CLI
 | 
			
		||||
============================================================
 | 
			
		||||
 | 
			
		||||
You can view the current software version and update level from the CLI. The
 | 
			
		||||
system type is also shown.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |context|
 | 
			
		||||
 | 
			
		||||
For more about working with software updates, see :ref:`Manage Software Updates
 | 
			
		||||
<managing-software-updates>`
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
.. _identifying-the-software-version-and-update-level-using-the-cli-steps-smg-b4r-hkb:
 | 
			
		||||
 | 
			
		||||
-   To find the software version from the CLI, use the :command:`system show`
 | 
			
		||||
    command.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system show
 | 
			
		||||
        +----------------------+----------------------------------------------------+
 | 
			
		||||
        | Property             | Value                                              |
 | 
			
		||||
        +----------------------+----------------------------------------------------+
 | 
			
		||||
        | contact              | None                                               |
 | 
			
		||||
        | created_at           | 2020-02-27T15:29:26.140606+00:00                   |
 | 
			
		||||
        | description          | yow-cgcs-ironpass-1_4                              |
 | 
			
		||||
        | https_enabled        | False                                              |
 | 
			
		||||
        | location             | None                                               |
 | 
			
		||||
        | name                 | yow-cgcs-ironpass-1-4                              |
 | 
			
		||||
        | region_name          | RegionOne                                          |
 | 
			
		||||
        | sdn_enabled          | False                                              |
 | 
			
		||||
        | security_feature     | spectre_meltdown_v1                                |
 | 
			
		||||
        | service_project_name | services                                           |
 | 
			
		||||
        | software_version     | nn.nn                                              |
 | 
			
		||||
        | system_mode          | duplex                                             |
 | 
			
		||||
        | system_type          | Standard                                           |
 | 
			
		||||
        | timezone             | UTC                                                |
 | 
			
		||||
        | updated_at           | 2020-02-28T16:19:56.987581+00:00                   |
 | 
			
		||||
        | uuid                 | 90212c98-7e27-4a14-8981-b8f5b777b26b               |
 | 
			
		||||
        | vswitch_type         | none                                               |
 | 
			
		||||
        +----------------------+----------------------------------------------------+
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        The **system_mode** field is shown only for a |prod| Simplex or Duplex
 | 
			
		||||
        system.
 | 
			
		||||
 | 
			
		||||
-   To list applied software updates from the CLI, use the :command:`sw-patch
 | 
			
		||||
    query` command.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sudo sw-patch query
 | 
			
		||||
@@ -1,23 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. gwe1552920505159
 | 
			
		||||
.. _in-service-versus-reboot-required-software-updates:
 | 
			
		||||
 | 
			
		||||
==================================================
 | 
			
		||||
In-Service Versus Reboot-Required Software Updates
 | 
			
		||||
==================================================
 | 
			
		||||
 | 
			
		||||
In-Service (Reboot-not-Required) and a Reboot-Required software updates are
 | 
			
		||||
available depending on the nature of the update to be performed.
 | 
			
		||||
 | 
			
		||||
In-Service software updates provide a mechanism to issue updates that do not
 | 
			
		||||
require a reboot, allowing the update to be installed on in-service nodes and
 | 
			
		||||
restarting affected processes as needed.
 | 
			
		||||
 | 
			
		||||
Depending on the area of software being updated and the type of software change,
 | 
			
		||||
installation of the update may or may not require the |prod| hosts to be
 | 
			
		||||
rebooted. For example, a software update to the kernel would require the host to
 | 
			
		||||
be rebooted in order to apply the update. Software updates are classified as
 | 
			
		||||
reboot-required or reboot-not-required (also referred to as
 | 
			
		||||
in-service) type updates to indicate this. For reboot-required updates, the
 | 
			
		||||
hosted application pods are automatically relocated to an alternate host as part
 | 
			
		||||
of the update procedure, prior to applying the update and rebooting the host.
 | 
			
		||||
@@ -19,42 +19,61 @@ Introduction
 | 
			
		||||
   software-updates-and-upgrades-software-updates
 | 
			
		||||
   software-upgrades
 | 
			
		||||
 | 
			
		||||
-----------------------
 | 
			
		||||
Manual software updates
 | 
			
		||||
-----------------------
 | 
			
		||||
------------------------
 | 
			
		||||
Host software deployment
 | 
			
		||||
------------------------
 | 
			
		||||
 | 
			
		||||
.. toctree::
 | 
			
		||||
   :maxdepth: 1
 | 
			
		||||
 | 
			
		||||
   managing-software-updates
 | 
			
		||||
   in-service-versus-reboot-required-software-updates
 | 
			
		||||
   identifying-the-software-version-and-update-level-using-horizon
 | 
			
		||||
   identifying-the-software-version-and-update-level-using-the-cli
 | 
			
		||||
   populating-the-storage-area
 | 
			
		||||
   update-status-and-lifecycle
 | 
			
		||||
   installing-software-updates-before-initial-commissioning
 | 
			
		||||
   installing-reboot-required-software-updates-using-horizon
 | 
			
		||||
   installing-reboot-required-software-updates-using-the-cli
 | 
			
		||||
   installing-in-service-software-update-using-horizon
 | 
			
		||||
   installing-in-service-software-updates-using-the-cli
 | 
			
		||||
   removing-reboot-required-software-updates
 | 
			
		||||
   software-update-space-reclamation
 | 
			
		||||
   reclaiming-disk-space
 | 
			
		||||
   manual-host-software-deployment-ee17ec6f71a4
 | 
			
		||||
   manual-rollback-host-software-deployment-9295ce1e6e29
 | 
			
		||||
   manual-removal-host-software-deployment-24f47e80e518
 | 
			
		||||
   orchestrated-deployment-host-software-deployment-d234754c7d20
 | 
			
		||||
   orchestrated-rollback-host-software-deployment-c6b12f13a8a1
 | 
			
		||||
   orchestrated-removal-host-software-deployment-3f542895daf8
 | 
			
		||||
 | 
			
		||||
----------------------------
 | 
			
		||||
Orchestrated Software Update
 | 
			
		||||
----------------------------
 | 
			
		||||
--------------------------
 | 
			
		||||
Kubernetes Version Upgrade
 | 
			
		||||
--------------------------
 | 
			
		||||
 | 
			
		||||
******
 | 
			
		||||
Manual
 | 
			
		||||
******
 | 
			
		||||
 | 
			
		||||
.. toctree::
 | 
			
		||||
   :maxdepth: 1
 | 
			
		||||
 | 
			
		||||
   update-orchestration-overview
 | 
			
		||||
   configuring-update-orchestration
 | 
			
		||||
   update-orchestration-cli
 | 
			
		||||
   manual-kubernetes-components-upgrade
 | 
			
		||||
   manual-kubernetes-multi-version-upgrade-in-aio-sx-13e05ba19840
 | 
			
		||||
 | 
			
		||||
----------------------------------------
 | 
			
		||||
************
 | 
			
		||||
Orchestrated
 | 
			
		||||
************
 | 
			
		||||
 | 
			
		||||
.. toctree::
 | 
			
		||||
   :maxdepth: 1
 | 
			
		||||
 | 
			
		||||
   about-kubernetes-orchestrated-upgrades
 | 
			
		||||
   the-kubernetes-update-orchestration-process
 | 
			
		||||
   configuring-kubernetes-update-orchestration
 | 
			
		||||
   configuring-kubernetes-multi-version-upgrade-orchestration-aio-b0b59a346466
 | 
			
		||||
   handling-kubernetes-update-orchestration-failures
 | 
			
		||||
 | 
			
		||||
--------
 | 
			
		||||
Appendix
 | 
			
		||||
--------
 | 
			
		||||
 | 
			
		||||
.. toctree::
 | 
			
		||||
   :maxdepth: 1
 | 
			
		||||
 | 
			
		||||
**********
 | 
			
		||||
Deprecated
 | 
			
		||||
**********
 | 
			
		||||
 | 
			
		||||
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
 | 
			
		||||
N3000 FPGA Firmware Update Orchestration
 | 
			
		||||
----------------------------------------
 | 
			
		||||
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
 | 
			
		||||
 | 
			
		||||
.. toctree::
 | 
			
		||||
   :maxdepth: 1
 | 
			
		||||
@@ -66,78 +85,6 @@ N3000 FPGA Firmware Update Orchestration
 | 
			
		||||
   firmware-update-orchestration-using-the-cli
 | 
			
		||||
   handle-firmware-update-orchestration-failures
 | 
			
		||||
 | 
			
		||||
---------------------------------
 | 
			
		||||
Manual Kubernetes Version Upgrade
 | 
			
		||||
---------------------------------
 | 
			
		||||
 | 
			
		||||
.. toctree::
 | 
			
		||||
   :maxdepth: 1
 | 
			
		||||
 | 
			
		||||
   manual-kubernetes-components-upgrade
 | 
			
		||||
   manual-kubernetes-multi-version-upgrade-in-aio-sx-13e05ba19840
 | 
			
		||||
 | 
			
		||||
----------------------------------------------
 | 
			
		||||
Kubernetes Version Upgrade Cloud Orchestration
 | 
			
		||||
----------------------------------------------
 | 
			
		||||
 | 
			
		||||
.. toctree::
 | 
			
		||||
   :maxdepth: 1
 | 
			
		||||
 | 
			
		||||
   about-kubernetes-orchestrated-upgrades
 | 
			
		||||
   the-kubernetes-update-orchestration-process
 | 
			
		||||
   configuring-kubernetes-update-orchestration
 | 
			
		||||
   configuring-kubernetes-multi-version-upgrade-orchestration-aio-b0b59a346466
 | 
			
		||||
   handling-kubernetes-update-orchestration-failures
 | 
			
		||||
 | 
			
		||||
----------------------------------
 | 
			
		||||
Manual Platform components upgrade
 | 
			
		||||
----------------------------------
 | 
			
		||||
 | 
			
		||||
.. toctree::
 | 
			
		||||
   :maxdepth: 1
 | 
			
		||||
 | 
			
		||||
   manual-upgrade-overview
 | 
			
		||||
 | 
			
		||||
******************
 | 
			
		||||
All-in-one Simplex
 | 
			
		||||
******************
 | 
			
		||||
 | 
			
		||||
.. toctree::
 | 
			
		||||
   :maxdepth: 1
 | 
			
		||||
 | 
			
		||||
   upgrading-all-in-one-simplex
 | 
			
		||||
   aborting-simplex-system-upgrades
 | 
			
		||||
 | 
			
		||||
******************
 | 
			
		||||
All-in-one Duplex
 | 
			
		||||
******************
 | 
			
		||||
 | 
			
		||||
.. toctree::
 | 
			
		||||
   :maxdepth: 1
 | 
			
		||||
 | 
			
		||||
   upgrading-all-in-one-duplex-or-standard
 | 
			
		||||
   overview-of-upgrade-abort-procedure
 | 
			
		||||
 | 
			
		||||
******************
 | 
			
		||||
Roll back upgrades
 | 
			
		||||
******************
 | 
			
		||||
 | 
			
		||||
.. toctree::
 | 
			
		||||
   :maxdepth: 1
 | 
			
		||||
 | 
			
		||||
   rolling-back-a-software-upgrade-before-the-second-controller-upgrade
 | 
			
		||||
   rolling-back-a-software-upgrade-after-the-second-controller-upgrade
 | 
			
		||||
 | 
			
		||||
---------------------------------------
 | 
			
		||||
Orchestrated Platform component upgrade
 | 
			
		||||
---------------------------------------
 | 
			
		||||
 | 
			
		||||
.. toctree::
 | 
			
		||||
   :maxdepth: 1
 | 
			
		||||
 | 
			
		||||
   orchestration-upgrade-overview
 | 
			
		||||
   performing-an-orchestrated-upgrade
 | 
			
		||||
   performing-an-orchestrated-upgrade-using-the-cli
 | 
			
		||||
 | 
			
		||||
------------------------------
 | 
			
		||||
Appendix - Kubernetes Platform
 | 
			
		||||
 
 | 
			
		||||
@@ -1,81 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. jfc1552920636790
 | 
			
		||||
.. _installing-in-service-software-update-using-horizon:
 | 
			
		||||
 | 
			
		||||
================================================
 | 
			
		||||
Install In-Service Software Update Using Horizon
 | 
			
		||||
================================================
 | 
			
		||||
 | 
			
		||||
The procedure for applying an in-service update is similar to that of a
 | 
			
		||||
reboot-required update, except that the host does not need to be locked and
 | 
			
		||||
unlocked as part of applying the update.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
.. _installing-in-service-software-update-using-horizon-steps-x1b-qnv-vw:
 | 
			
		||||
 | 
			
		||||
#.  Log in to the Horizon Web interface as the **admin** user.
 | 
			
		||||
 | 
			
		||||
#.  In |prod| Horizon, open the Software Management page.
 | 
			
		||||
 | 
			
		||||
    The **Software Management** page is available from **Admin** \> **Platform**
 | 
			
		||||
    \> **Software Management** in the left-hand pane.
 | 
			
		||||
 | 
			
		||||
#.  Select the **Patches** tab to see the current update status.
 | 
			
		||||
 | 
			
		||||
    The **Patches** tab shows the current status of all updates uploaded to the
 | 
			
		||||
    system. If there are no updates, an empty **Patch Table** is displayed.
 | 
			
		||||
 | 
			
		||||
#.  Upload the update (patch) file to the update storage area.
 | 
			
		||||
 | 
			
		||||
    Click the **Upload Patch** button to display an upload window from which
 | 
			
		||||
    you can browse your workstation's file system to select the update file.
 | 
			
		||||
    Click the **Upload Patch** button once the selection is done.
 | 
			
		||||
 | 
			
		||||
    The update file is transferred to the Active Controller and is copied to
 | 
			
		||||
    the update storage area, but it has yet to be applied to the cluster. This
 | 
			
		||||
    is reflected in the **Patches** tab.
 | 
			
		||||
 | 
			
		||||
#.  Apply the update.
 | 
			
		||||
 | 
			
		||||
    Click the **Apply Patch** button associated with the update. Alternatively,
 | 
			
		||||
    select the update first using the selection boxes on the left, and then
 | 
			
		||||
    click the **Apply Patches** button at the top. You can use this selection
 | 
			
		||||
    process to apply all updates, or a selected subset, in a single operation.
 | 
			
		||||
 | 
			
		||||
    The **Patches** tab is updated to report the update to be in the
 | 
			
		||||
    *Partial-Apply* state.
 | 
			
		||||
 | 
			
		||||
#.  Install the update on controller-0.
 | 
			
		||||
 | 
			
		||||
    #.  Select the **Hosts** tab.
 | 
			
		||||
 | 
			
		||||
        The **Hosts** tab on the **Host Inventory** page reflects the new status
 | 
			
		||||
        of the hosts with respect to the new update state. In this example, the
 | 
			
		||||
        update only applies to controller software, as can be seen by the
 | 
			
		||||
        worker host's status field being empty, indicating that it is 'patch
 | 
			
		||||
        current'.
 | 
			
		||||
 | 
			
		||||
        .. image:: figures/ekn1453233538504.png
 | 
			
		||||
 | 
			
		||||
    #.  Select the Install Patches option from the **Edit Host** button
 | 
			
		||||
        associated with controller-0 to install the update.
 | 
			
		||||
 | 
			
		||||
        A confirmation window is presented giving you a last opportunity to
 | 
			
		||||
        cancel the operation before proceeding.
 | 
			
		||||
 | 
			
		||||
#.  Repeat the steps 6 a,b, above with controller-1 to install the update
 | 
			
		||||
    on controller-1.
 | 
			
		||||
 | 
			
		||||
#.  Repeat the steps 6 a,b above for the worker and/or storage hosts (if
 | 
			
		||||
    present).
 | 
			
		||||
 | 
			
		||||
    This step does not apply for |prod| Simplex or Duplex systems.
 | 
			
		||||
 | 
			
		||||
#.  Verify the state of the update.
 | 
			
		||||
 | 
			
		||||
    Visit the **Patches** tab again. The update is now in the *Applied* state.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |result|
 | 
			
		||||
 | 
			
		||||
The update is now applied, and all affected hosts have been updated.
 | 
			
		||||
@@ -1,131 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. hfj1552920618138
 | 
			
		||||
.. _installing-in-service-software-updates-using-the-cli:
 | 
			
		||||
 | 
			
		||||
=================================================
 | 
			
		||||
Install In-Service Software Updates Using the CLI
 | 
			
		||||
=================================================
 | 
			
		||||
 | 
			
		||||
The procedure for applying an in-service update is similar to that of a
 | 
			
		||||
reboot-required update, except that the host does not need to be locked and
 | 
			
		||||
unlocked as part of applying the update.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#.  Upload the update (patch).
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch upload INSVC_HORIZON_SYSINV.patch
 | 
			
		||||
        INSVC_HORIZON_SYSINV is now available
 | 
			
		||||
 | 
			
		||||
#.  Confirm that the update is available.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch query
 | 
			
		||||
              Patch ID        RR  Release  Patch State
 | 
			
		||||
        ====================  ==  =======  ===========
 | 
			
		||||
        INSVC_HORIZON_SYSINV  N    nn.nn    Available
 | 
			
		||||
 | 
			
		||||
#.  Check the status of the hosts.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch query-hosts
 | 
			
		||||
          Hostname      IP Address    Patch Current  Reboot Required  Release  State
 | 
			
		||||
        ============  ==============  =============  ===============  =======  =====
 | 
			
		||||
        worker-0      192.168.204.24       Yes             No          nn.nn   idle
 | 
			
		||||
        controller-0  192.168.204.3        Yes             No          nn.nn   idle
 | 
			
		||||
        controller-1  192.168.204.4        Yes             No          nn.nn   idle
 | 
			
		||||
 | 
			
		||||
#.  Ensure that the original update files have been deleted from the root drive.
 | 
			
		||||
 | 
			
		||||
    After they are uploaded to the storage area, the original files are no
 | 
			
		||||
    longer required. You must use the command-line interface to delete them, in
 | 
			
		||||
    order to ensure enough disk space to complete the installation.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ rm </path/patchfile>
 | 
			
		||||
 | 
			
		||||
    .. caution::
 | 
			
		||||
        If the original files are not deleted before the updates are applied,
 | 
			
		||||
        the installation may fail due to a full disk.
 | 
			
		||||
 | 
			
		||||
#.  Apply the update (patch).
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch apply INSVC_HORIZON_SYSINV
 | 
			
		||||
        INSVC_HORIZON_SYSINV is now in the repo
 | 
			
		||||
 | 
			
		||||
    The update state transitions to Partial-Apply:
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch query
 | 
			
		||||
        Patch ID              RR  Release   Patch State
 | 
			
		||||
        ====================  ==  =======  =============
 | 
			
		||||
        INSVC_HORIZON_SYSINV  N    nn.nn   Partial-Apply
 | 
			
		||||
 | 
			
		||||
    As it is an in-service update, the hosts report that they are not 'patch
 | 
			
		||||
    current', but they do not require a reboot.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch query-hosts
 | 
			
		||||
        Hostname      IP Address      Patch Current  Reboot Required  Release  State
 | 
			
		||||
        ============  ==============  =============  ===============  =======  =====
 | 
			
		||||
        worker-0      192.168.204.24       No              No          nn.nn   idle
 | 
			
		||||
        controller-0  192.168.204.3        No              No          nn.nn   idle
 | 
			
		||||
        controller-1  192.168.204.4        No              No          nn.nn   idle
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
#.  Install the update on controller-0.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch host-install controller-0
 | 
			
		||||
        .............
 | 
			
		||||
        Installation was successful.
 | 
			
		||||
 | 
			
		||||
#.  Query the hosts to check status.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch query-hosts
 | 
			
		||||
        Hostname      IP Address    Patch Current  Reboot Required    Release  State
 | 
			
		||||
        ============  ==============  =============  ===============  =======  =====
 | 
			
		||||
        worker-0      192.168.204.24       No              No          nn.nn   idle
 | 
			
		||||
        controller-0  192.168.204.3        Yes             No          nn.nn   idle
 | 
			
		||||
        controller-1  192.168.204.4        No              No          nn.nn   idle
 | 
			
		||||
 | 
			
		||||
    The controller-1 host reports it is now 'patch current' and does not
 | 
			
		||||
    require a reboot, without having been locked or rebooted
 | 
			
		||||
 | 
			
		||||
#.  Install the update on worker-0 (and other worker nodes and storage nodes,
 | 
			
		||||
    if present)
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch host-install worker-0
 | 
			
		||||
        ....
 | 
			
		||||
        Installation was successful.
 | 
			
		||||
 | 
			
		||||
    You can query the hosts to confirm that all nodes are now 'patch current',
 | 
			
		||||
    and that the update has transitioned to the Applied state.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch query-hosts
 | 
			
		||||
        Hostname      IP Address      Patch Current  Reboot Required  Release  State
 | 
			
		||||
        ============  ==============  =============  ===============  =======  =====
 | 
			
		||||
        worker-0      192.168.204.24       Yes             No          nn.nn   idle
 | 
			
		||||
        controller-0  192.168.204.3        Yes             No          nn.nn   idle
 | 
			
		||||
        controller-1  192.168.204.4        Yes             No          nn.nn   idle
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch query
 | 
			
		||||
        Patch ID              RR  Release  Patch State
 | 
			
		||||
        ====================  ==  =======  ===========
 | 
			
		||||
        INSVC_HORIZON_SYSINV  N    nn.nn     Applied
 | 
			
		||||
@@ -1,126 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. phg1552920664442
 | 
			
		||||
.. _installing-reboot-required-software-updates-using-horizon:
 | 
			
		||||
 | 
			
		||||
======================================================
 | 
			
		||||
Install Reboot-Required Software Updates Using Horizon
 | 
			
		||||
======================================================
 | 
			
		||||
 | 
			
		||||
You can use the Horizon Web interface to upload, delete, apply, and remove
 | 
			
		||||
software updates.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |context|
 | 
			
		||||
 | 
			
		||||
This section presents an example of a software update workflow using a single
 | 
			
		||||
update. The main steps of the procedure are:
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
.. _installing-reboot-required-software-updates-using-horizon-ul-mbr-wsr-s5:
 | 
			
		||||
 | 
			
		||||
-   Upload the updates.
 | 
			
		||||
 | 
			
		||||
-   Lock the host\(s).
 | 
			
		||||
 | 
			
		||||
-   Install updates; any unlocked nodes will reject the request.
 | 
			
		||||
 | 
			
		||||
-   Unlock the host\(s). Unlocking the host\(s) automatically triggers a
 | 
			
		||||
    reboot.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
.. _installing-reboot-required-software-updates-using-horizon-steps-lnt-14y-hjb:
 | 
			
		||||
 | 
			
		||||
#.  Log in to the Horizon Web interface as the **admin** user.
 | 
			
		||||
 | 
			
		||||
#.  In Horizon, open the **Software Management** page.
 | 
			
		||||
 | 
			
		||||
    The **Software Management** page is available from **Admin** \> **Platform**
 | 
			
		||||
    \> **Software Management** in the left-hand pane.
 | 
			
		||||
 | 
			
		||||
#.  Select the **Patches** tab to see the current status.
 | 
			
		||||
 | 
			
		||||
    The **Patches** tab shows the current status of all updates uploaded to the
 | 
			
		||||
    system. If there are no updates, an empty **Patch Table** is displayed.
 | 
			
		||||
 | 
			
		||||
#.  Upload the update (patch) file to the update storage area.
 | 
			
		||||
 | 
			
		||||
    Click the **Upload Patches** button to display an upload window from which
 | 
			
		||||
    you can browse your workstation's file system to select the update file.
 | 
			
		||||
    Click the **Upload Patches** button once the selection is done.
 | 
			
		||||
 | 
			
		||||
    The update file is transferred to the Active Controller and is copied to
 | 
			
		||||
    the storage area, but it has yet to be applied to the cluster. This is
 | 
			
		||||
    reflected on the **Patches** tab.
 | 
			
		||||
 | 
			
		||||
#.  Apply the update.
 | 
			
		||||
 | 
			
		||||
    Click the **Apply Patch** button associated with the update. Alternatively,
 | 
			
		||||
    select the update first using the selection boxes on the left, and then
 | 
			
		||||
    click the **Apply Patches** button at the top. You can use this selection
 | 
			
		||||
    process to apply all updates, or a selected subset, in a single operation.
 | 
			
		||||
 | 
			
		||||
    The Patches page is updated to report the update to be in the
 | 
			
		||||
    *Partial-Apply* state.
 | 
			
		||||
 | 
			
		||||
#.  Install the update on controller-0.
 | 
			
		||||
 | 
			
		||||
    .. _installing-reboot-required-software-updates-using-horizon-step-N10107-N10028-N1001C-N10001:
 | 
			
		||||
 | 
			
		||||
    #.  Select the **Hosts** tab.
 | 
			
		||||
 | 
			
		||||
        The **Hosts** tab on the **Host Inventory** page reflects the new status
 | 
			
		||||
        of the hosts with respect to the new update state. As shown below, both
 | 
			
		||||
        controllers are now reported as not 'patch current' and requiring
 | 
			
		||||
        reboot.
 | 
			
		||||
 | 
			
		||||
        .. image:: figures/ekn1453233538504.png
 | 
			
		||||
 | 
			
		||||
    #.  Transfer active services to the standby controller by selecting the
 | 
			
		||||
        **Swact Host** option from the **Edit Host** button associated with the
 | 
			
		||||
        active controller host.
 | 
			
		||||
 | 
			
		||||
        .. note::
 | 
			
		||||
            Access to Horizon may be lost briefly during the active controller
 | 
			
		||||
            transition. You may have to log in again.
 | 
			
		||||
 | 
			
		||||
    #.  Select the **Lock Host** option from the **Edit Host** button associated
 | 
			
		||||
        with **controller-0**.
 | 
			
		||||
 | 
			
		||||
    #.  Select the **Install Patches** option from the **Edit Host** button
 | 
			
		||||
        associated with **controller-0** to install the update.
 | 
			
		||||
 | 
			
		||||
        A confirmation window is presented giving you a last opportunity to
 | 
			
		||||
        cancel the operation before proceeding.
 | 
			
		||||
 | 
			
		||||
        Wait for the update install to complete.
 | 
			
		||||
 | 
			
		||||
    #.  Select the **Unlock Host** option from the **Edit Host** button
 | 
			
		||||
        associated with controller-0.
 | 
			
		||||
 | 
			
		||||
#.  Repeat steps :ref:`6
 | 
			
		||||
    <installing-reboot-required-software-updates-using-horizon-step-N10107-N10028-N1001C-N10001>`
 | 
			
		||||
    a to e, with **controller-1** to install the update on controller-1.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        For |prod| Simplex systems, this step does not apply.
 | 
			
		||||
 | 
			
		||||
#.  Repeat steps :ref:`6
 | 
			
		||||
    <installing-reboot-required-software-updates-using-horizon-step-N10107-N10028-N1001C-N10001>`
 | 
			
		||||
    a to e, for the worker and/or storage hosts.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        For |prod| Simplex or Duplex systems, this step does not apply.
 | 
			
		||||
 | 
			
		||||
#.  Verify the state of the update.
 | 
			
		||||
 | 
			
		||||
    Visit the **Patches** page. The update is now in the *Applied* state.
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
.. rubric:: |result|
 | 
			
		||||
 | 
			
		||||
The update is now applied, and all affected hosts have been updated.
 | 
			
		||||
 | 
			
		||||
Updates can be removed using the **Remove Patches** button from the **Patches**
 | 
			
		||||
tab. The workflow is similar to the one presented in this section, with the
 | 
			
		||||
exception that updates are being removed from each host instead of being
 | 
			
		||||
applied.
 | 
			
		||||
@@ -1,300 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. ffh1552920650754
 | 
			
		||||
.. _installing-reboot-required-software-updates-using-the-cli:
 | 
			
		||||
 | 
			
		||||
======================================================
 | 
			
		||||
Install Reboot-Required Software Updates Using the CLI
 | 
			
		||||
======================================================
 | 
			
		||||
 | 
			
		||||
You can install reboot-required software updates using the CLI.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
.. _installing-reboot-required-software-updates-using-the-cli-steps-v1q-vlv-vw:
 | 
			
		||||
 | 
			
		||||
#.  Log in as user **sysadmin** to the active controller and source the script
 | 
			
		||||
    ``/etc/platform/openrc`` to obtain administrative privileges.
 | 
			
		||||
 | 
			
		||||
#.  Verify that the updates are available using the :command:`sw-patch query`
 | 
			
		||||
    command.
 | 
			
		||||
 | 
			
		||||
    .. parsed-literal::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sudo sw-patch query
 | 
			
		||||
 | 
			
		||||
        Patch ID                Patch State
 | 
			
		||||
        =====================   ===========
 | 
			
		||||
        |pn|-nn.nn_PATCH_0001   Available
 | 
			
		||||
        |pn|-nn.nn_PATCH_0002   Available
 | 
			
		||||
        |pn|-nn.nn_PATCH_0003   Available
 | 
			
		||||
 | 
			
		||||
    where *nn.nn* in the update (patch) filename is the |prod| release number.
 | 
			
		||||
 | 
			
		||||
#.  Ensure the original update files have been deleted from the root drive.
 | 
			
		||||
 | 
			
		||||
    After the updates are uploaded to the storage area, the original files are
 | 
			
		||||
    no longer required. You must use the command-line interface to delete them,
 | 
			
		||||
    in order to ensure enough disk space to complete the installation.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ rm </path/patchfile>
 | 
			
		||||
 | 
			
		||||
    .. caution::
 | 
			
		||||
        If the original files are not deleted before the updates are applied,
 | 
			
		||||
        the installation may fail due to a full disk.
 | 
			
		||||
 | 
			
		||||
#.  Apply the update.
 | 
			
		||||
 | 
			
		||||
    .. parsed-literal::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sudo sw-patch apply |pn|-<nn>.<nn>_PATCH_0001
 | 
			
		||||
        |pn|-<nn>.<nn>_PATCH_0001 is now in the repo
 | 
			
		||||
 | 
			
		||||
    where <nn>.<nn> in the update filename is the |prod-long| release number.
 | 
			
		||||
 | 
			
		||||
    The update is now in the Partial-Apply state, ready for installation from
 | 
			
		||||
    the software updates repository on the impacted hosts.
 | 
			
		||||
 | 
			
		||||
#.  Apply all available updates in a single operation, for example:
 | 
			
		||||
 | 
			
		||||
    .. parsed-literal::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sudo sw-patch apply --all
 | 
			
		||||
        |pn|-|pvr|-PATCH_0001 is now in the repo
 | 
			
		||||
        |pn|-|pvr|-PATCH_0002 is now in the repo
 | 
			
		||||
        |pn|-|pvr|-PATCH_0003 is now in the repo
 | 
			
		||||
 | 
			
		||||
    In this example, there are three updates ready for installation from the
 | 
			
		||||
    software updates repository.
 | 
			
		||||
 | 
			
		||||
#.  Query the updating status of all hosts in the cluster.
 | 
			
		||||
 | 
			
		||||
    You can query the updating status of all hosts at any time as illustrated
 | 
			
		||||
    below.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        The reported status is the accumulated result of all applied and
 | 
			
		||||
        removed updates in the software updates repository, and not just the
 | 
			
		||||
        status due to a particular update.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sudo sw-patch query-hosts
 | 
			
		||||
 | 
			
		||||
          Hostname      IP Address    Patch Current  Reboot Required  Release  State
 | 
			
		||||
        ============  ==============  =============  ===============  =======  =====
 | 
			
		||||
        worker-0      192.168.204.12       Yes              No          nn.nn   idle
 | 
			
		||||
        controller-0  192.168.204.3        Yes              Yes         nn.nn   idle
 | 
			
		||||
        controller-1  192.168.204.4        Yes              Yes         nn.nn   idle
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
    For each host in the cluster, the following status fields are displayed:
 | 
			
		||||
 | 
			
		||||
    **Patch Current**
 | 
			
		||||
        Indicates whether there are updates pending for installation or removal
 | 
			
		||||
        on the host or not. If *Yes*, then all relevant updates in the software
 | 
			
		||||
        updates repository have been installed on, or removed from, the host
 | 
			
		||||
        already. If *No*, then there is at least one update in either the
 | 
			
		||||
        Partial-Apply or Partial-Remove state that has not been applied to the
 | 
			
		||||
        host.
 | 
			
		||||
 | 
			
		||||
        The **Patch Current** field of the :command:`query-hosts` command will
 | 
			
		||||
        briefly report *Pending* after you apply or remove an update, until
 | 
			
		||||
        that host has checked against the repository to see if it is impacted
 | 
			
		||||
        by the patching operation.
 | 
			
		||||
 | 
			
		||||
    **Reboot Required**
 | 
			
		||||
        Indicates whether the host must be rebooted or not as a result of one
 | 
			
		||||
        or more updates that have been either applied or removed, or because it
 | 
			
		||||
        is not 'patch current'.
 | 
			
		||||
 | 
			
		||||
    **Release**
 | 
			
		||||
        Indicates the running software release version.
 | 
			
		||||
 | 
			
		||||
    **State**
 | 
			
		||||
        There are four possible states:
 | 
			
		||||
 | 
			
		||||
        **idle**
 | 
			
		||||
           In a wait state.
 | 
			
		||||
 | 
			
		||||
        **installing**
 | 
			
		||||
           Installing (or removing) updates.
 | 
			
		||||
 | 
			
		||||
        **install-failed**
 | 
			
		||||
           The operation failed, either due to an update error or something
 | 
			
		||||
           killed the process. Check the ``patching.log`` on the node in
 | 
			
		||||
           question.
 | 
			
		||||
 | 
			
		||||
        **install-rejected**
 | 
			
		||||
           The node is unlocked, therefore the request to install has been
 | 
			
		||||
           rejected. This state persists until there is another install
 | 
			
		||||
           request, or the node is reset.
 | 
			
		||||
 | 
			
		||||
        Once the state has gone back to idle, the install operation is complete
 | 
			
		||||
        and you can safely unlock the node.
 | 
			
		||||
 | 
			
		||||
    In this example, **worker-0** is up to date, no updates need to be
 | 
			
		||||
    installed and no reboot is required. By contrast, the controllers are not
 | 
			
		||||
    'patch current', and therefore a reboot is required as part of installing
 | 
			
		||||
    the update.
 | 
			
		||||
 | 
			
		||||
#.  Install all pending updates on **controller-0**.
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
    #.  Switch the active controller services.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-swact controller-0
 | 
			
		||||
 | 
			
		||||
        Before updating a controller node, you must transfer any active
 | 
			
		||||
        services running on the host to the other controller. Only then it is
 | 
			
		||||
        safe to lock the host.
 | 
			
		||||
 | 
			
		||||
    #.  Lock the host.
 | 
			
		||||
 | 
			
		||||
        You must lock the target host, controller, worker, or storage, before
 | 
			
		||||
        installing updates.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-lock controller-0
 | 
			
		||||
 | 
			
		||||
    #.  Install the update.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ sudo sw-patch host-install <controller-0>
 | 
			
		||||
 | 
			
		||||
        .. note::
 | 
			
		||||
            You can use the :command:`sudo sw-patch host-install-async <hostname>`
 | 
			
		||||
            command if you are launching multiple installs in
 | 
			
		||||
            parallel.
 | 
			
		||||
 | 
			
		||||
    #.  Unlock the host.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-unlock controller-0
 | 
			
		||||
 | 
			
		||||
        Unlocking the host forces a reset of the host followed by a reboot.
 | 
			
		||||
        This ensures that the host is restarted in a known state.
 | 
			
		||||
 | 
			
		||||
    All updates are now installed on controller-0. Querying the current
 | 
			
		||||
    update status displays the following information:
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sudo sw-patch query-hosts
 | 
			
		||||
 | 
			
		||||
           Hostname      IP Address    Patch Current  Reboot Required  Release  State
 | 
			
		||||
        ============  ==============  =============  ===============  =======  =====
 | 
			
		||||
        worker-0      192.168.204.95       Yes             No          nn.nn   idle
 | 
			
		||||
        worker-1      192.168.204.63       Yes             No          nn.nn   idle
 | 
			
		||||
        worker-2      192.168.204.99       Yes             No          nn.nn   idle
 | 
			
		||||
        worker-3      192.168.204.49       Yes             No          nn.nn   idle
 | 
			
		||||
        controller-0  192.168.204.3        Yes             No          nn.nn   idle
 | 
			
		||||
        controller-1  192.168.204.4        Yes             No          nn.nn   idle
 | 
			
		||||
        storage-0     192.168.204.37       Yes             No          nn.nn   idle
 | 
			
		||||
        storage-1     192.168.204.90       Yes             No          nn.nn   idle
 | 
			
		||||
 | 
			
		||||
#.  Install all pending updates on controller-1.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        For |prod| Simplex systems, this step does not apply.
 | 
			
		||||
 | 
			
		||||
    Repeat the previous step targeting controller-1.
 | 
			
		||||
 | 
			
		||||
    All updates are now installed on controller-1 as well. Querying the
 | 
			
		||||
    current updating status displays the following information:
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sudo sw-patch query-hosts
 | 
			
		||||
 | 
			
		||||
           Hostname      IP Address    Patch Current  Reboot Required  Release  State
 | 
			
		||||
        ============  ==============  =============  ===============  =======  =====
 | 
			
		||||
        worker-0      192.168.204.95       Yes             No          nn.nn   idle
 | 
			
		||||
        worker-1      192.168.204.63       Yes             No          nn.nn   idle
 | 
			
		||||
        worker-2      192.168.204.99       Yes             No          nn.nn   idle
 | 
			
		||||
        worker-3      192.168.204.49       Yes             No          nn.nn   idle
 | 
			
		||||
        controller-0  192.168.204.3        Yes             No          nn.nn   idle
 | 
			
		||||
        controller-1  192.168.204.4        Yes             No          nn.nn   idle
 | 
			
		||||
        storage-0     192.168.204.37       Yes             No          nn.nn   idle
 | 
			
		||||
        storage-1     192.168.204.90       Yes             No          nn.nn   idle
 | 
			
		||||
 | 
			
		||||
#.  Install any pending updates for the worker or storage hosts.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
         This step does not apply for |prod| Simplex or Duplex systems.
 | 
			
		||||
 | 
			
		||||
    All hosted application pods currently running on a worker host are
 | 
			
		||||
    re-located to another host.
 | 
			
		||||
 | 
			
		||||
    If the **Patch Current** status for a worker or storage host is *No*,
 | 
			
		||||
    apply the pending updates using the following commands:
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-lock <hostname>
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sudo sw-patch host-install-async <hostname>
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-unlock <hostname>
 | 
			
		||||
 | 
			
		||||
    where <hostname> is the name of the host (for example, ``worker-0``).
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        Update installations can be triggered in parallel.
 | 
			
		||||
 | 
			
		||||
        The :command:`sw-patch host-install-async` command ( corresponding to
 | 
			
		||||
        **install patches** on the Horizon Web interface) can be run on all
 | 
			
		||||
        locked nodes, without waiting for one node to complete the install
 | 
			
		||||
        before triggering the install on the next. If you can lock the nodes at
 | 
			
		||||
        the same time, without impacting hosted application services, you can
 | 
			
		||||
        update them at the same time.
 | 
			
		||||
 | 
			
		||||
        Likewise, you can install an update to the standby controller and a
 | 
			
		||||
        worker node at the same time. The only restrictions are those of the
 | 
			
		||||
        lock: 
 | 
			
		||||
        
 | 
			
		||||
        * You cannot lock both controllers.
 | 
			
		||||
        
 | 
			
		||||
        * You cannot lock a worker node if you do not have enough free resources
 | 
			
		||||
          to relocate the hosted applications from it. 
 | 
			
		||||
          
 | 
			
		||||
        Also, in a Ceph configuration (with storage nodes), you cannot lock
 | 
			
		||||
        more than one of controller-0/controller-1/storage-0 at the same time,
 | 
			
		||||
        as these nodes are running Ceph monitors and you must have at least two
 | 
			
		||||
        in service at all times.
 | 
			
		||||
 | 
			
		||||
#.  Confirm that all updates are installed and the |prod| is up-to-date.
 | 
			
		||||
 | 
			
		||||
    Use the :command:`sw-patch query` command to verify that all updates are
 | 
			
		||||
    *Applied*.
 | 
			
		||||
 | 
			
		||||
    .. parsed-literal::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sudo sw-patch query
 | 
			
		||||
 | 
			
		||||
        Patch ID                    Patch State
 | 
			
		||||
        =========================   ===========
 | 
			
		||||
        |pn|-<nn>.<nn>_PATCH_0001   Applied
 | 
			
		||||
 | 
			
		||||
    where <nn>.<nn> in the update filename is the |prod| release number.
 | 
			
		||||
 | 
			
		||||
    If the **Patch State** for any update is still shown as *Available* or
 | 
			
		||||
    *Partial-Apply*, use the :command:`sw-patch query-hosts`` command to identify
 | 
			
		||||
    which hosts are not *Patch Current*, and then apply updates to them as
 | 
			
		||||
    described in the preceding steps.
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
.. rubric:: |result|
 | 
			
		||||
 | 
			
		||||
The |prod| is up to date now. All updates are installed.
 | 
			
		||||
@@ -1,105 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. tla1552920677022
 | 
			
		||||
.. _installing-software-updates-before-initial-commissioning:
 | 
			
		||||
 | 
			
		||||
=====================================================
 | 
			
		||||
Install Software Updates Before Initial Commissioning
 | 
			
		||||
=====================================================
 | 
			
		||||
 | 
			
		||||
This section describes installing software updates before you can commission
 | 
			
		||||
|prod-long|.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |context|
 | 
			
		||||
 | 
			
		||||
This procedure assumes that the software updates to install are available on a
 | 
			
		||||
USB flash drive, or from a server reachable by controller-0.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |prereq|
 | 
			
		||||
 | 
			
		||||
When initially installing the |prod-long| software, it is required that you
 | 
			
		||||
install the latest available updates on controller-0 before running Ansible
 | 
			
		||||
Bootstrap Playbook, and before installing the software on other hosts. This
 | 
			
		||||
ensures that:
 | 
			
		||||
 | 
			
		||||
.. _installing-software-updates-before-initial-commissioning-ul-gsq-1ht-vp:
 | 
			
		||||
 | 
			
		||||
-   The software on controller-0, and all other hosts, is up to date when
 | 
			
		||||
    the cluster comes alive.
 | 
			
		||||
 | 
			
		||||
-   You reduce installation time by avoiding updating the system right after an
 | 
			
		||||
    out-of-date software installation is complete.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#.  Install software on controller-0.
 | 
			
		||||
 | 
			
		||||
    Use the |prod-long| bootable ISO image to initialize controller-0.
 | 
			
		||||
 | 
			
		||||
    This step takes you to the point where you use the console port to log in
 | 
			
		||||
    to controller-0 as user **sysadmin**.
 | 
			
		||||
 | 
			
		||||
#.  Populate the storage area.
 | 
			
		||||
 | 
			
		||||
    Upload the updates from the USB flash drive using the command
 | 
			
		||||
    :command:`sw-patch upload` or :command:`sw-patch upload-dir` as described
 | 
			
		||||
    in :ref:`Populating the Storage Area <populating-the-storage-area>`.
 | 
			
		||||
 | 
			
		||||
#.  Delete the update files from the root drive.
 | 
			
		||||
 | 
			
		||||
    After the updates are uploaded to the storage area, the original files are
 | 
			
		||||
    no longer required. You must delete them to ensure enough disk space to
 | 
			
		||||
    complete the installation.
 | 
			
		||||
 | 
			
		||||
    .. caution::
 | 
			
		||||
        If the original files are not deleted before the updates are applied,
 | 
			
		||||
        the installation may fail due to a full disk.
 | 
			
		||||
 | 
			
		||||
#.  Apply the updates.
 | 
			
		||||
 | 
			
		||||
    Apply the updates using the command :command:`sw-patch apply --all`.
 | 
			
		||||
 | 
			
		||||
    The updates are now in the repository, ready to be installed.
 | 
			
		||||
 | 
			
		||||
#.  Install the updates on the controller.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch install-local
 | 
			
		||||
        Patch installation is complete.
 | 
			
		||||
        Please reboot before continuing with configuration.
 | 
			
		||||
 | 
			
		||||
    This command installs all applied updates on controller-0.
 | 
			
		||||
 | 
			
		||||
#.  Reboot controller-0.
 | 
			
		||||
 | 
			
		||||
    You must reboot the controller to ensure that it is running with the
 | 
			
		||||
    software fully updated.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo reboot
 | 
			
		||||
 | 
			
		||||
#.  Bootstrap system on controller-0.
 | 
			
		||||
 | 
			
		||||
    #.  Configure an IP interface.
 | 
			
		||||
 | 
			
		||||
        .. note::
 | 
			
		||||
            The |prod| software will automatically enable all interfaces and
 | 
			
		||||
            send out a |DHCP| request, so this may happen automatically if a
 | 
			
		||||
            |DHCP| Server is present on the network. Otherwise, you must
 | 
			
		||||
            manually configure an IP interface.
 | 
			
		||||
 | 
			
		||||
    #.  Run the Ansible Bootstrap Playbook. This can be run remotely or locally
 | 
			
		||||
        on controller-0.
 | 
			
		||||
 | 
			
		||||
.. include:: /_includes/installing-software-updates-before-initial-commissioning.rest
 | 
			
		||||
 | 
			
		||||
.. rubric:: |result|
 | 
			
		||||
 | 
			
		||||
Once all hosts in the cluster are initialized and they are all running fully
 | 
			
		||||
updated software. The |prod-long| cluster is up to date.
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
.. xbooklink From step 1
 | 
			
		||||
    For details, see :ref:`Install Software on controller-0
 | 
			
		||||
    <installing-software-on-controller-0>` for your system.
 | 
			
		||||
@@ -1,112 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. kol1552920779041
 | 
			
		||||
.. _managing-software-updates:
 | 
			
		||||
 | 
			
		||||
=======================
 | 
			
		||||
Manage Software Updates
 | 
			
		||||
=======================
 | 
			
		||||
 | 
			
		||||
Updates (also known as patches) to the system software become available as
 | 
			
		||||
needed to address issues associated with a current |prod-long| software release.
 | 
			
		||||
Software updates must be uploaded to the active controller and applied to all
 | 
			
		||||
required hosts in the cluster.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
    Updating |prod-dc| is distinct from updating other |prod| configurations.
 | 
			
		||||
    
 | 
			
		||||
.. xbooklink    For information on updating |prod-dc|, see |distcloud-doc|: :ref:`Update
 | 
			
		||||
    Management for Distributed Cloud
 | 
			
		||||
    <update-management-for-distributed-cloud>`.
 | 
			
		||||
 | 
			
		||||
The following elements form part of the software update environment:
 | 
			
		||||
 | 
			
		||||
**Reboot-Required Software Updates**
 | 
			
		||||
    Reboot-required updates are typically major updates that require hosts to be
 | 
			
		||||
    locked during the update process and rebooted to complete the process.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        When a |prod| host is locked and rebooted for updates, the hosted
 | 
			
		||||
        application pods are re-located to an alternate host in order to
 | 
			
		||||
        minimize the impact to the hosted application service.
 | 
			
		||||
 | 
			
		||||
**In-Service Software Updates**
 | 
			
		||||
    In-service (reboot-not-required), software updates are updates that do not
 | 
			
		||||
    require the locking and rebooting of hosts. The required |prod| software is
 | 
			
		||||
    updated and any required |prod| processes are re-started. Hosted
 | 
			
		||||
    applications pods and services are completely unaffected.
 | 
			
		||||
 | 
			
		||||
**Software Update Commands**
 | 
			
		||||
    The :command:`sw-patch` command is available on both active controllers. It
 | 
			
		||||
    must be run as root using :command:`sudo`. It provides the user interface to
 | 
			
		||||
    process the updates, including querying the state of an update, listing
 | 
			
		||||
    affected hosts, and applying, installing, and removing updates.
 | 
			
		||||
 | 
			
		||||
**Software Update Storage Area**
 | 
			
		||||
    A central storage area maintained by the update controller. Software updates
 | 
			
		||||
    are initially uploaded to the storage area and remains there until they are
 | 
			
		||||
    deleted.
 | 
			
		||||
 | 
			
		||||
**Software Update Repository**
 | 
			
		||||
    A central repository of software updates associated with any updates applied
 | 
			
		||||
    to the system. This repository is used by all hosts in the cluster to
 | 
			
		||||
    identify the software updates and rollbacks required on each host.
 | 
			
		||||
 | 
			
		||||
**Software Update Logs**
 | 
			
		||||
    The following logs are used to record software update activity:
 | 
			
		||||
 | 
			
		||||
    **patching.log**
 | 
			
		||||
        This records software update agent activity on each host.
 | 
			
		||||
 | 
			
		||||
    **patching-api.log**
 | 
			
		||||
        This records user actions that involve software updates, performed
 | 
			
		||||
        using either the CLI or the REST API.
 | 
			
		||||
 | 
			
		||||
    **patching-insvc.log**
 | 
			
		||||
        This records the execution of patch scripts while in-service patches are
 | 
			
		||||
        applied.
 | 
			
		||||
 | 
			
		||||
The overall flow for installing a software update from the command line
 | 
			
		||||
interface on a working |prod| cluster is the following:
 | 
			
		||||
 | 
			
		||||
.. _managing-software-updates-ol-vgf-yzz-jp:
 | 
			
		||||
 | 
			
		||||
#.  Consult the |org| support personnel for details on the availability of new
 | 
			
		||||
    software updates.
 | 
			
		||||
 | 
			
		||||
#.  Download the software update from the |org| servers to a workstation that
 | 
			
		||||
    can reach the active controller through the |OAM| network.
 | 
			
		||||
 | 
			
		||||
#.  Copy the software update to the active controller using the cluster's |OAM|
 | 
			
		||||
    floating IP address as the destination point.
 | 
			
		||||
 | 
			
		||||
    You can use a command such as :command:`scp` to copy the software update.
 | 
			
		||||
    The software update workflows presented in this document assume that this
 | 
			
		||||
    step is complete already, that is, they assume that the software update is
 | 
			
		||||
    already available on the file system of the active controller.
 | 
			
		||||
 | 
			
		||||
#.  Upload the new software update to the storage area.
 | 
			
		||||
 | 
			
		||||
    This step makes the new software update available within the system, but
 | 
			
		||||
    does not install it to the cluster yet. For all purposes, the software
 | 
			
		||||
    update is dormant.
 | 
			
		||||
 | 
			
		||||
#.  Apply the software update.
 | 
			
		||||
 | 
			
		||||
    This step adds the updates to the repository, making it visible to all
 | 
			
		||||
    hosts in the cluster.
 | 
			
		||||
 | 
			
		||||
#.  Install the software updates on each of the affected hosts in the cluster.
 | 
			
		||||
    This can be done manually or by using upgrade orchestration. For more
 | 
			
		||||
    information, see :ref:`Update Orchestration Overview
 | 
			
		||||
    <update-orchestration-overview>`.
 | 
			
		||||
 | 
			
		||||
Updating software in the system can be done using the Horizon Web interface or
 | 
			
		||||
the command line interface on the active controller. When using Horizon you
 | 
			
		||||
upload the software update directly from your workstation using a file browser
 | 
			
		||||
window provided by the software update upload facility.
 | 
			
		||||
 | 
			
		||||
A special case occurs during the initial provisioning of a cluster when you
 | 
			
		||||
want to update controller-0 before the system software is configured. This
 | 
			
		||||
can only be done from the command line interface. See :ref:`Install Software
 | 
			
		||||
Updates Before Initial Commissioning
 | 
			
		||||
<installing-software-updates-before-initial-commissioning>` for details.
 | 
			
		||||
@@ -0,0 +1,674 @@
 | 
			
		||||
.. WARNING: Add no lines of text between the label immediately following
 | 
			
		||||
.. and the title.
 | 
			
		||||
 | 
			
		||||
.. _manual-host-software-deployment-ee17ec6f71a4:
 | 
			
		||||
 | 
			
		||||
===============================
 | 
			
		||||
Manual Host Software Deployment
 | 
			
		||||
===============================
 | 
			
		||||
 | 
			
		||||
|prod| software management enables you to upversion the |prod| software to a
 | 
			
		||||
new patch release or a new major release using a manual procedure of
 | 
			
		||||
step-by-step host-by-host commands.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |context|
 | 
			
		||||
 | 
			
		||||
This procedure describes upversioning to either a new patch release (in-service
 | 
			
		||||
or reboot-required) or a new major release.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    Upversioning can also be performed to a new major release that has been
 | 
			
		||||
    pre-patched with the current patches for the major release. This is
 | 
			
		||||
    packaged and delivered as a pre-patched major release ISO. All the comments in
 | 
			
		||||
    this section that are specific to a major release also apply to a
 | 
			
		||||
    pre-patched major release.
 | 
			
		||||
 | 
			
		||||
This procedure covers all standalone configurations:  |AIO-SX|, |AIO-DX| and
 | 
			
		||||
standard configuration.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    For a major release software deployment, the following procedure can be
 | 
			
		||||
    aborted and rolled back at any time between the :command:`software deploy start` and
 | 
			
		||||
    :command:`software deploy delete`. For procedure on rolling back, see
 | 
			
		||||
    Manual Rollback Host Software Deployment.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |prereq|
 | 
			
		||||
 | 
			
		||||
- A recent full backup is available. It is not explicitly required for software
 | 
			
		||||
  deployment, however, it is a good practice to have a recent full backup
 | 
			
		||||
  available prior to performing major changes to the system.
 | 
			
		||||
 | 
			
		||||
- Highly recommended to not have any active alarms on the system, otherwise
 | 
			
		||||
  upgrades will not proceed.
 | 
			
		||||
 | 
			
		||||
- If you are using a private container image registry for installs/updates/upgrades,
 | 
			
		||||
 | 
			
		||||
  - The private registry must be populated with any new container images
 | 
			
		||||
    required for the new software release.
 | 
			
		||||
 | 
			
		||||
  - The list of container images required by the new software release can be
 | 
			
		||||
    found in your software distribution site.
 | 
			
		||||
 | 
			
		||||
- For a new major release software deployment only,
 | 
			
		||||
 | 
			
		||||
  - All hosts are unlocked and enabled/available.
 | 
			
		||||
 | 
			
		||||
  - The system should be patch current, that is, all the available patch
 | 
			
		||||
    releases for the current major release should be deployed.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#. For a duplex (dual controller) system, switch the activity from
 | 
			
		||||
   controller-1 such that controller-0 becomes active.
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       This step is not required for an |AIO-SX| system.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ system host-swact controller-1
 | 
			
		||||
 | 
			
		||||
   Wait for the activity to switch to controller-0. This may take up to a
 | 
			
		||||
   minute depending on the hardware.
 | 
			
		||||
 | 
			
		||||
   Reconnect to the system.
 | 
			
		||||
 | 
			
		||||
#. Transfer the new software release files to the active controller-0.
 | 
			
		||||
 | 
			
		||||
   - For major release, it includes major release install ISO, software
 | 
			
		||||
     signature file, and license file.
 | 
			
		||||
 | 
			
		||||
   - For patch release, it includes the patch release `.patch` archive file.
 | 
			
		||||
 | 
			
		||||
#. For major release only, install the license file for the release you are upgrading to.
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       This step is not required for a patch release deployment.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ system license-install <new-release-license-file>
 | 
			
		||||
 | 
			
		||||
#. Upload the new software release into the system.
 | 
			
		||||
 | 
			
		||||
   #. For major release
 | 
			
		||||
 | 
			
		||||
      .. code-block::
 | 
			
		||||
 | 
			
		||||
          ~(keystone_admin)]$ software upload [ --local ] <new-release>.iso <new-release>.sig
 | 
			
		||||
          <new-release-id> is now uploaded
 | 
			
		||||
          +-------------------------------+-------------------+
 | 
			
		||||
          | Uploaded File                 | Release           |
 | 
			
		||||
          +-------------------------------+-------------------+
 | 
			
		||||
          | <new-release>.iso             | <new-release-id>  |
 | 
			
		||||
          +-------------------------------+-------------------+
 | 
			
		||||
 | 
			
		||||
      where `--local`` can be used when running this command in an |SSH| session on
 | 
			
		||||
      the active controller to optimize performance. With this option, the
 | 
			
		||||
      system will read files directly from the local disk rather than
 | 
			
		||||
      transferring files over REST APIs backing the |CLI|.
 | 
			
		||||
 | 
			
		||||
      This command may take 5-10 mins depending on the hardware.
 | 
			
		||||
 | 
			
		||||
   #. For patch release
 | 
			
		||||
 | 
			
		||||
      .. code-block::
 | 
			
		||||
 | 
			
		||||
          ~(keystone_admin)]$ software upload <filename>.patch
 | 
			
		||||
          <release-id> is now uploaded
 | 
			
		||||
          +-------------------------------+-------------------+
 | 
			
		||||
          | Uploaded File                 | Release           |
 | 
			
		||||
          +-------------------------------+-------------------+
 | 
			
		||||
          | <new-release>.patch           | <new-release-id>  |
 | 
			
		||||
          +-------------------------------+-------------------+
 | 
			
		||||
 | 
			
		||||
   #. Ensure that the new software release was successfully uploaded.
 | 
			
		||||
 | 
			
		||||
      .. code-block::
 | 
			
		||||
 | 
			
		||||
          ~(keystone_admin)]$ software list
 | 
			
		||||
          +--------------------------+-------+-----------+
 | 
			
		||||
          | Release                  | RR    |   State   |
 | 
			
		||||
          +--------------------------+-------+-----------+
 | 
			
		||||
          | starlingx-10.0.0         | True  | deployed  |
 | 
			
		||||
          | <new-release-id>         | True  | available |
 | 
			
		||||
          +--------------------------+-------+-----------+
 | 
			
		||||
 | 
			
		||||
#. Run software deployment prechecks and confirm that the system is healthy.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy precheck [ -f ] <new-release-id>
 | 
			
		||||
       System Health:
 | 
			
		||||
       All hosts are provisioned: [OK]
 | 
			
		||||
       All hosts are unlocked/enabled: [OK]
 | 
			
		||||
       All hosts have current configurations: [OK]
 | 
			
		||||
       All hosts are patch current: [OK]
 | 
			
		||||
       Ceph Storage Healthy: [OK]
 | 
			
		||||
       No alarms: [OK]
 | 
			
		||||
       All kubernetes nodes are ready: [OK]
 | 
			
		||||
       All kubernetes control plane pods are ready: [OK]
 | 
			
		||||
       All PodSecurityPolicies are removed: [OK]
 | 
			
		||||
       All kubernetes applications are in a valid state: [OK]
 | 
			
		||||
       Installed license is valid: [OK]
 | 
			
		||||
       Required patches are applied: [OK]
 | 
			
		||||
 | 
			
		||||
   Resolve any checks that are not ok and re-run the :command:`software deploy precheck` command.
 | 
			
		||||
   Use the `-f` option to ignore non-management affecting alarms.
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       The failed prechecks must be cleared before software deployment is
 | 
			
		||||
       allowed to proceed.
 | 
			
		||||
 | 
			
		||||
#. Start the software deployment procedure.
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       The :command:`software deploy start` command will automatically run
 | 
			
		||||
       the prechecks of previous steps if the prechecks have not been run or
 | 
			
		||||
       have not passed.
 | 
			
		||||
 | 
			
		||||
   By default, the software deployment procedure cannot be started unless
 | 
			
		||||
   prechecks pass.
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       The failed prechecks must be cleared before software deployment is
 | 
			
		||||
       allowed to proceed.
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       Configuration cannot be changed during the software deployment process.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy start [ -f ] <new-release-id>
 | 
			
		||||
       Deployment for <new-release-id> started
 | 
			
		||||
 | 
			
		||||
   Then, monitor the progress of :command:`software deploy start` using the
 | 
			
		||||
   following commands:
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy show
 | 
			
		||||
       +--------------+------------------+------+---------------+
 | 
			
		||||
       | From Release | To Release       |  RR  | State         |
 | 
			
		||||
       +--------------+------------------+------+---------------+
 | 
			
		||||
       | 10.0.0       | <new-release-id> | True | deploy-start  |
 | 
			
		||||
       +--------------+------------------+------+---------------+
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy show
 | 
			
		||||
       +--------------+------------------+------+-------------------+
 | 
			
		||||
       | From Release | To Release       |  RR  |    State          |
 | 
			
		||||
       +--------------+------------------+------+-------------------+
 | 
			
		||||
       | 10.0.0       | <new-release-id> | True | deploy-start-done |
 | 
			
		||||
       +--------------+------------------+------+-------------------+
 | 
			
		||||
 | 
			
		||||
   The :command:`software deploy start` command may take 5-10 mins to reach
 | 
			
		||||
   the ``deploy-start-done`` state depending on hardware.
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       If :command:`software deploy start` fails, that is, if the state is
 | 
			
		||||
       `deploy-start-failed`, review ``/var/log/software.log`` on the active
 | 
			
		||||
       controller for failure details, address the issues, and run the
 | 
			
		||||
       :command:`software deploy delete` command to delete the deploy and
 | 
			
		||||
       re-execute the :command:`software deploy start` command.
 | 
			
		||||
 | 
			
		||||
#. Deploy the new software release to all hosts.
 | 
			
		||||
 | 
			
		||||
   - For an |AIO-SX| system
 | 
			
		||||
 | 
			
		||||
     #. Deploy the new software release to controller-0.
 | 
			
		||||
 | 
			
		||||
        #. Only if the software deployment is ``RR=True`` (reboot required),
 | 
			
		||||
           lock controller-0.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ system host-lock controller-0
 | 
			
		||||
 | 
			
		||||
        #. Deploy the new software release to controller-0.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ software deploy host controller-0
 | 
			
		||||
               Host installation request sent to controller-0.
 | 
			
		||||
               Host installation was successful on controller-0.
 | 
			
		||||
 | 
			
		||||
           After this command completes:
 | 
			
		||||
 | 
			
		||||
           - If ``RR=TRUE``, the host is still running the old software
 | 
			
		||||
             release, however boot parameters have been updated to boot into
 | 
			
		||||
             the new software release on the next host reboot, which will occur
 | 
			
		||||
             in the next step which unlocks the host.
 | 
			
		||||
 | 
			
		||||
           - If ``RR=FALSE``, the host is running the new software release.
 | 
			
		||||
 | 
			
		||||
        #. Only if the software deployment is ``RR=True``, unlock controller-0.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ system host-unlock controller-0
 | 
			
		||||
 | 
			
		||||
           The host will now reboot into the new software release. Wait for the
 | 
			
		||||
           host to finish rebooting and become enabled. This may take 3-5 mins
 | 
			
		||||
           depending on hardware.
 | 
			
		||||
 | 
			
		||||
     #. Proceed to step :ref:`8 <manual-host-software-deployment-ee17ec6f71a4-step>` (software
 | 
			
		||||
        deploy activate) of the main procedure.
 | 
			
		||||
 | 
			
		||||
   - For an |AIO-DX| system or standard system
 | 
			
		||||
 | 
			
		||||
     #. Deploy the new software release to controller-1 (standby controller).
 | 
			
		||||
 | 
			
		||||
        #. Only if the software deployment is ``RR=True``, lock controller-1.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ system host-lock controller-1
 | 
			
		||||
 | 
			
		||||
        #. Deploy the new software release to controller-1.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ software deploy host controller-1
 | 
			
		||||
               Host installation request sent to controller-1.
 | 
			
		||||
               Host installation was successful on controller-1.
 | 
			
		||||
 | 
			
		||||
           After this command completes:
 | 
			
		||||
 | 
			
		||||
           -  If ``RR=TRUE``, the host is still running the old software
 | 
			
		||||
              release, however boot parameters have been updated to boot into
 | 
			
		||||
              the new software release on the next host reboot, which will
 | 
			
		||||
              occur in the next step which unlocks the host.
 | 
			
		||||
 | 
			
		||||
           -  If ``RR=FALSE``, the host is running the new software release.
 | 
			
		||||
 | 
			
		||||
        #. Only if the software deployment is ``RR=True``, unlock controller-1.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ system host-unlock controller-1
 | 
			
		||||
 | 
			
		||||
           The host will now reboot into the new software release. Wait for the
 | 
			
		||||
           host to finish rebooting and become enabled.
 | 
			
		||||
 | 
			
		||||
           This may take 3-5 mins depending on hardware.
 | 
			
		||||
 | 
			
		||||
        #. Display state of software deployment.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ software deploy show
 | 
			
		||||
               +--------------+------------------+------+-------------+
 | 
			
		||||
               | From Release | To Release       |  RR  | State       |
 | 
			
		||||
               +--------------+------------------+------+-------------+
 | 
			
		||||
               | 10.0.0       | <new-release-id> | True | deploy-host |
 | 
			
		||||
               +--------------+------------------+------+-------------+
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ software deploy host-list
 | 
			
		||||
               +--------------+--------------+-------------------+-------+----------------------+
 | 
			
		||||
               | Host         | From Release | To Release        |  RR   |  State               |
 | 
			
		||||
               +--------------+--------------+-------------------+-------+----------------------+
 | 
			
		||||
               | controller-0 | 10.0.0       |  <new-release-id> | True  | deploy-host-pending  |
 | 
			
		||||
               | controller-1 | 10.0.0       |  <new-release-id> | True  | deploy-host-deployed |
 | 
			
		||||
               | storage-0    | 10.0.0       |  <new-release-id> | True  | deploy-host-pending  |
 | 
			
		||||
               | storage-1    | 10.0.0       |  <new-release-id> | True  | deploy-host-pending  |
 | 
			
		||||
               | worker-0     | 10.0.0       |  <new-release-id> | True  | deploy-host-pending  |
 | 
			
		||||
               | worker-1     | 10.0.0       |  <new-release-id> | True  | deploy-host-pending  |
 | 
			
		||||
               +--------------+--------------+-------------------+-------+----------------------+
 | 
			
		||||
 | 
			
		||||
     #. Switch the activity from controller-0 such that controller-1 becomes active.
 | 
			
		||||
 | 
			
		||||
        .. code-block::
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-swact controller-0
 | 
			
		||||
 | 
			
		||||
        Wait for the activity to switch to controller-1.
 | 
			
		||||
 | 
			
		||||
        This may take up to a minute depending on hardware.
 | 
			
		||||
 | 
			
		||||
        Reconnect to system.
 | 
			
		||||
 | 
			
		||||
     #. Deploy the new software release to controller-0 (now the standby controller).
 | 
			
		||||
 | 
			
		||||
        #. Only if the software deployment is ``RR=True``, lock controller-0.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ system host-lock controller-0
 | 
			
		||||
 | 
			
		||||
        #. Deploy the new software release to controller-0.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ software deploy host controller-0
 | 
			
		||||
               Host installation request sent to controller-0.
 | 
			
		||||
               Host installation was successful on controller-0.
 | 
			
		||||
 | 
			
		||||
           After this command completes:
 | 
			
		||||
 | 
			
		||||
           - If ``RR=TRUE``, the host is still running the old software
 | 
			
		||||
             release, however boot parameters have been updated to boot into
 | 
			
		||||
             the new software release on the next host reboot, which will occur
 | 
			
		||||
             in the next step which unlocks the host.
 | 
			
		||||
 | 
			
		||||
           - If ``RR=FALSE``, the host is running the new software release.
 | 
			
		||||
 | 
			
		||||
        #. Only if the software deployment is ``RR=True``, unlock controller-0.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ system host-unlock controller-0
 | 
			
		||||
 | 
			
		||||
           The host will now reboot into the new software release. Wait for the
 | 
			
		||||
           host to finish rebooting and become enabled.
 | 
			
		||||
 | 
			
		||||
           This may take 3-5 mins depending on hardware.
 | 
			
		||||
 | 
			
		||||
        #. Display state of software deployment.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ software deploy show
 | 
			
		||||
               +--------------+------------------+------+-------------+
 | 
			
		||||
               | From Release | To Release       |  RR  | State       |
 | 
			
		||||
               +--------------+------------------+------+-------------+
 | 
			
		||||
               | 10.0.0       | <new-release-id> | True | deploy-host |
 | 
			
		||||
               +--------------+------------------+------+-------------+
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ software deploy host-list
 | 
			
		||||
               +--------------+--------------+-------------------+-------+----------------------+
 | 
			
		||||
               | Host         | From Release | To Release        |  RR   |  State               |
 | 
			
		||||
               +--------------+--------------+-------------------+-------+----------------------+
 | 
			
		||||
               | controller-0 | 10.0.0       |  <new-release-id> | True  | deploy-host-deployed |
 | 
			
		||||
               | controller-1 | 10.0.0       |  <new-release-id> | True  | deploy-host-deployed |
 | 
			
		||||
               | storage-0    | 10.0.0       |  <new-release-id> | True  | deploy-host-pending  |
 | 
			
		||||
               | storage-1    | 10.0.0       |  <new-release-id> | True  | deploy-host-pending  |
 | 
			
		||||
               | worker-0     | 10.0.0       |  <new-release-id> | True  | deploy-host-pending  |
 | 
			
		||||
               | worker-1     | 10.0.0       |  <new-release-id> | True  | deploy-host-pending  |
 | 
			
		||||
               +--------------+--------------+-------------------+-------+----------------------+
 | 
			
		||||
 | 
			
		||||
     #. Check the system health to ensure that there are no unexpected alarms.
 | 
			
		||||
 | 
			
		||||
        .. code-block::
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ fm alarm-list
 | 
			
		||||
 | 
			
		||||
        Clear all the alarms unrelated to the upgrade process.
 | 
			
		||||
 | 
			
		||||
     #. If storage hosts are present, deploy the new software release to the
 | 
			
		||||
        storage hosts one at a time.
 | 
			
		||||
 | 
			
		||||
        #. Deploy the new software release to storage-0.
 | 
			
		||||
 | 
			
		||||
           #. Only if the software deployment is ``RR=True``, lock storage-0.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                   ~(keystone_admin)]$ system host-lock storage-0
 | 
			
		||||
 | 
			
		||||
           #. Deploy the new software release to storage-0.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ software deploy host storage-0
 | 
			
		||||
                  Host installation request sent to storage-0.
 | 
			
		||||
                  Host installation was successful on storage-0.
 | 
			
		||||
 | 
			
		||||
              After this command completes:
 | 
			
		||||
 | 
			
		||||
              - If ``RR=TRUE``, the host is still running the old software
 | 
			
		||||
                release, however boot parameters have been updated to boot into
 | 
			
		||||
                the new software release on the next host reboot, which will
 | 
			
		||||
                occur in the next step which unlocks the host.
 | 
			
		||||
 | 
			
		||||
              - If ``RR=FALSE``, the host is running the new software release.
 | 
			
		||||
 | 
			
		||||
           #. Only if the software deployment is ``RR=True``, unlock storage-0.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ system host-unlock storage-0
 | 
			
		||||
 | 
			
		||||
              The host will now reboot into the new software release. Wait for
 | 
			
		||||
              the host to finish rebooting and become enabled. Wait for all the
 | 
			
		||||
              alarms to clear after the unlock before proceeding to the next
 | 
			
		||||
              storage host.
 | 
			
		||||
 | 
			
		||||
              This may take 3-5 mins depending on hardware.
 | 
			
		||||
 | 
			
		||||
           #. Display state of software deployment.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ software deploy show
 | 
			
		||||
                  +--------------+------------------+------+--------------+
 | 
			
		||||
                  | From Release | To Release       |  RR  | State        |
 | 
			
		||||
                  +--------------+------------------+------+--------------+
 | 
			
		||||
                  | 10.0.0       | <new-release-id> | True | deploy-host  |
 | 
			
		||||
                  +--------------+------------------+------+--------------+
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ software deploy host-list
 | 
			
		||||
                  +--------------+--------------+-------------------+-------+----------------------+
 | 
			
		||||
                  | Host         | From Release | To Release        |  RR   |  State               |
 | 
			
		||||
                  +--------------+--------------+-------------------+-------+----------------------+
 | 
			
		||||
                  | controller-0 | 10.0.0       |  <new-release-id> | True  | deploy-host-deployed |
 | 
			
		||||
                  | controller-1 | 10.0.0       |  <new-release-id> | True  | deploy-host-deployed |
 | 
			
		||||
                  | storage-0    | 10.0.0       |  <new-release-id> | True  | deploy-host-deployed |
 | 
			
		||||
                  | storage-1    | 10.0.0       |  <new-release-id> | True  | deploy-host-pending  |
 | 
			
		||||
                  | worker-0     | 10.0.0       |  <new-release-id> | True  | deploy-host-pending  |
 | 
			
		||||
                  | worker-1     | 10.0.0       |  <new-release-id> | True  | deploy-host-pending  |
 | 
			
		||||
                  +--------------+--------------+-------------------+-------+----------------------+
 | 
			
		||||
 | 
			
		||||
        #. Repeat the above steps for each storage host.
 | 
			
		||||
 | 
			
		||||
           .. note::
 | 
			
		||||
 | 
			
		||||
               After upgrading the first storage host, you can expect
 | 
			
		||||
               alarm 800.003. The alarm is cleared after all the storage hosts are
 | 
			
		||||
               upgraded.
 | 
			
		||||
 | 
			
		||||
     #. If worker hosts are present, deploy the new software release to worker
 | 
			
		||||
        hosts one at a time.
 | 
			
		||||
 | 
			
		||||
        #. Deploy the new software release to worker-0.
 | 
			
		||||
 | 
			
		||||
           #. Only if the software deployment is ``RR=True``, lock worker-0.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ system host-lock worker-0
 | 
			
		||||
 | 
			
		||||
           #. Deploy the new software release to worker-0.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ software deploy host worker-0
 | 
			
		||||
                  Host installation request sent to worker-0.
 | 
			
		||||
                  Host installation was successful on worker-0.
 | 
			
		||||
 | 
			
		||||
              After this command completes:
 | 
			
		||||
 | 
			
		||||
              - If ``RR=TRUE``, the host is still running the old software
 | 
			
		||||
                release, however boot parameters have been updated to boot into
 | 
			
		||||
                the new software release on the next host reboot, which will
 | 
			
		||||
                occur in the next step which unlocks the host.
 | 
			
		||||
 | 
			
		||||
              - If ``RR=FALSE``, the host is running the new software release.
 | 
			
		||||
 | 
			
		||||
           #. Only if the software deployment is ``RR=True``, unlock worker-0.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ system host-unlock worker-0
 | 
			
		||||
 | 
			
		||||
              The host will now reboot into the new software release. Wait for
 | 
			
		||||
              the host to finish rebooting and become enabled. Wait for all the
 | 
			
		||||
              alarms to clear after the unlock before proceeding to the next
 | 
			
		||||
              worker host.
 | 
			
		||||
 | 
			
		||||
              This may take 3-5 mins depending on hardware.
 | 
			
		||||
 | 
			
		||||
           #. Display state of software deployment.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ software deploy show
 | 
			
		||||
                  +--------------+------------------+------+--------------+
 | 
			
		||||
                  | From Release | To Release       |  RR  | State        |
 | 
			
		||||
                  +--------------+------------------+------+--------------+
 | 
			
		||||
                  | 10.0.0       | <new-release-id> | True | deploy-host  |
 | 
			
		||||
                  +--------------+------------------+------+--------------+
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ software deploy host-list
 | 
			
		||||
                  +--------------+--------------+-------------------+-------+----------------------+
 | 
			
		||||
                  | Host         | From Release | To Release        |  RR   |  State               |
 | 
			
		||||
                  +--------------+--------------+-------------------+-------+----------------------+
 | 
			
		||||
                  | controller-0 | 10.0.0       |  <new-release-id> | True  | deploy-host-deployed |
 | 
			
		||||
                  | controller-1 | 10.0.0       |  <new-release-id> | True  | deploy-host-deployed |
 | 
			
		||||
                  | storage-0    | 10.0.0       |  <new-release-id> | True  | deploy-host-deployed |
 | 
			
		||||
                  | storage-1    | 10.0.0       |  <new-release-id> | True  | deploy-host-deployed |
 | 
			
		||||
                  | worker-0     | 10.0.0       |  <new-release-id> | True  | deploy-host-deployed |
 | 
			
		||||
                  | worker-1     | 10.0.0       |  <new-release-id> | True  | deploy-host-pending  |
 | 
			
		||||
                  +--------------+--------------+-------------------+-------+----------------------+
 | 
			
		||||
 | 
			
		||||
        #. Repeat the above steps for each worker host.
 | 
			
		||||
 | 
			
		||||
     #. Switch the activity from controller-1 such that controller-0 becomes active.
 | 
			
		||||
 | 
			
		||||
        .. code-block::
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-swact controller-1
 | 
			
		||||
 | 
			
		||||
        Wait for the activity to switch to controller-0.
 | 
			
		||||
 | 
			
		||||
        This may take up to a minute depending on hardware.
 | 
			
		||||
 | 
			
		||||
        Reconnect to system.
 | 
			
		||||
 | 
			
		||||
#. Activate the software deployment.
 | 
			
		||||
 | 
			
		||||
   .. _manual-host-software-deployment-ee17ec6f71a4-step:
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy activate
 | 
			
		||||
       Deploy activate has started
 | 
			
		||||
 | 
			
		||||
   When running the :command:`software deploy activate` command, new configurations are
 | 
			
		||||
   applied to the controller. The 250.001 (Configuration is out-of-date)
 | 
			
		||||
   alarms are raised and are cleared as the configurations are applied.
 | 
			
		||||
 | 
			
		||||
   The software deployment state goes from ``deploy-activate`` to
 | 
			
		||||
   ``deploy-activate-done`` once deployment is activated. For a major release
 | 
			
		||||
   software deployment, this may take up to 15-30 mins to complete depending on
 | 
			
		||||
   system configuration and hardware.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy show
 | 
			
		||||
       +--------------+------------------+------+---------------------+
 | 
			
		||||
       | From Release | To Release       |  RR  |    State            |
 | 
			
		||||
       +--------------+------------------+------+---------------------+
 | 
			
		||||
       | 10.0.0       | <new-release-id> | True | deploy-activate-done|
 | 
			
		||||
       +--------------+------------------+------+---------------------+
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       If :command:`software deploy activate` fails, that is, if the state is
 | 
			
		||||
       ``deploy-activate-failed``, review ``/var/log/software.log`` on the active
 | 
			
		||||
       controller for failure details, address the issues, and re-execute the
 | 
			
		||||
       :command:`software deploy activate` command.
 | 
			
		||||
 | 
			
		||||
#. Complete the software deployment.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy complete
 | 
			
		||||
       Deployment has been completed
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy show
 | 
			
		||||
       +--------------+------------------+------+-------------------+
 | 
			
		||||
       | From Release | To Release       |  RR  |    State          |
 | 
			
		||||
       +--------------+------------------+------+-------------------+
 | 
			
		||||
       | 10.0.0       | <new-release-id> | True | deploy-completed  |
 | 
			
		||||
       +--------------+------------------+------+-------------------+
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       After this command is executed, you can run the Kubernetes version
 | 
			
		||||
       upgrade procedure, if desired to upversion to new Kubernetes versions
 | 
			
		||||
       available in the new software release.
 | 
			
		||||
 | 
			
		||||
#. Delete the software deployment.
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       If it is a system controller, the deployment should not be deleted
 | 
			
		||||
       until the subclouds are up-to-date.
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       For a major release deployment, after this command is executed, the
 | 
			
		||||
       major release software deployment cannot be rolled back.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy delete
 | 
			
		||||
       Deployment has been deleted
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy show
 | 
			
		||||
       No deploy in progress
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    After the deploy delete, if there are previous release entries in the
 | 
			
		||||
    unavailable state, the alarm 900.024 ``Obsolete release in system`` is
 | 
			
		||||
    raised.
 | 
			
		||||
 | 
			
		||||
#. Delete the old major release.
 | 
			
		||||
 | 
			
		||||
   In the case of software deployment of a new major release, you should remove
 | 
			
		||||
   the old major release to reclaim disk space.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software list
 | 
			
		||||
       +--------------------------+-------+-------------+
 | 
			
		||||
       | Release                  | RR    |   State     |
 | 
			
		||||
       +--------------------------+-------+-------------+
 | 
			
		||||
       | starlingx-10.0.0         | True  | unavailable |
 | 
			
		||||
       | <new-major-release-id>   | True  | deployed    |
 | 
			
		||||
       +--------------------------+-------+-------------+
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software delete starlingx-10.0.0
 | 
			
		||||
       starlingx-10.0.0 has been deleted.
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software list
 | 
			
		||||
       +--------------------------+-------+-------------+
 | 
			
		||||
       | Release                  | RR    |   State     |
 | 
			
		||||
       +--------------------------+-------+-------------+
 | 
			
		||||
       | <new-major-release-id>   | True  | deployed    |
 | 
			
		||||
       +--------------------------+-------+-------------+
 | 
			
		||||
 | 
			
		||||
@@ -0,0 +1,86 @@
 | 
			
		||||
.. WARNING: Add no lines of text between the label immediately following
 | 
			
		||||
.. and the title.
 | 
			
		||||
 | 
			
		||||
.. _manual-removal-host-software-deployment-24f47e80e518:
 | 
			
		||||
 | 
			
		||||
=======================================
 | 
			
		||||
Manual Removal Host Software Deployment
 | 
			
		||||
=======================================
 | 
			
		||||
 | 
			
		||||
A fully deployed patch release can be removed (un-deployed) by using the
 | 
			
		||||
the :ref:`manual-host-software-deployment-ee17ec6f71a4` procedure and deploying a
 | 
			
		||||
previous patch release or the major release.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    A fully deployed major release cannot be removed (un-deployed).
 | 
			
		||||
 | 
			
		||||
For example, the following shows the current software releases deployed:
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ software list
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
    | Release                  | RR    |    State  |
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
    | starlingx-10.0.0         | True  | deployed  |
 | 
			
		||||
    | starlingx-10.0.1         | False | deployed  |
 | 
			
		||||
    | starlingx-10.0.2         | True  | deployed  |
 | 
			
		||||
    | starlingx-10.0.3         | False | deployed  |
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
 | 
			
		||||
To remove patch releases `starlingx-10.0.3` and `starlingx-10.0.2`, follow the
 | 
			
		||||
:ref:`manual-host-software-deployment-ee17ec6f71a4` procedure, and deploy (or
 | 
			
		||||
go back to) the `starlingx-10.0.1` software release in the software deployment
 | 
			
		||||
start step.
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ software deploy start starlingx-10.0.1
 | 
			
		||||
    Deployment for starlingx-10.0.1 started
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ software deploy show
 | 
			
		||||
    +--------------+------------------+------+-------+
 | 
			
		||||
    | From Release | To Release       |   RR | State |
 | 
			
		||||
    +--------------+------------------+------+-------+
 | 
			
		||||
    | 10.0.3       | 10.0.1           | True | start |
 | 
			
		||||
    +--------------+------------------+------+-------+
 | 
			
		||||
 | 
			
		||||
On the completion of the :ref:`manual-host-software-deployment-ee17ec6f71a4`
 | 
			
		||||
procedure, run the following command:
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ software list
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
    | Release                  | RR    |    State  |
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
    | starlingx-10.0.0         | True  | deployed  |
 | 
			
		||||
    | starlingx-10.0.1         | False | deployed  |
 | 
			
		||||
    | starlingx-10.0.2         | True  | available |
 | 
			
		||||
    | starlingx-10.0.3         | False | available |
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
 | 
			
		||||
If the removed patches are no longer required on the system, you can delete them.
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ software delete starlingx-10.0.3
 | 
			
		||||
    starlingx-10.0.3 has been deleted.
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ software delete starlingx-10.0.2
 | 
			
		||||
    starlingx-10.0.2 has been deleted.
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ software list
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
    | Release                  | RR    |    State  |
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
    | starlingx-10.0.0         | True  | deployed  |
 | 
			
		||||
    | starlingx-10.0.1         | False | deployed  |
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
@@ -0,0 +1,460 @@
 | 
			
		||||
.. WARNING: Add no lines of text between the label immediately following
 | 
			
		||||
.. and the title.
 | 
			
		||||
 | 
			
		||||
.. _manual-rollback-host-software-deployment-9295ce1e6e29:
 | 
			
		||||
 | 
			
		||||
========================================
 | 
			
		||||
Manual Rollback Host Software Deployment
 | 
			
		||||
========================================
 | 
			
		||||
 | 
			
		||||
For a major release software deployment, you can roll back the
 | 
			
		||||
:ref:`manual-host-software-deployment-ee17ec6f71a4` procedure at any time
 | 
			
		||||
between :command:`software deploy start` and :command:`software deploy delete`.
 | 
			
		||||
After the software deploy deletion step, aborting and rolling back of the major
 | 
			
		||||
release deployment is not possible.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
   This section also covers the abort and rollback of a new patched major
 | 
			
		||||
   release deployment.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |prereq|
 | 
			
		||||
 | 
			
		||||
You are in the middle of the
 | 
			
		||||
:ref:`manual-host-software-deployment-ee17ec6f71a4` procedure for a major
 | 
			
		||||
release between :command:`software deploy start` and :command:`software deploy
 | 
			
		||||
delete`.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#. Abort the current in-progress major release software deployment.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy abort
 | 
			
		||||
       Deployment has been aborted
 | 
			
		||||
 | 
			
		||||
#. If the current deploy state is ``deploy-activate-rollback-pending``, then roll back the
 | 
			
		||||
   activate of the aborted deployment, otherwise proceed to :ref:`3 <manual-rollback-host-software-deployment-9295ce1e6e29-step>`.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy show
 | 
			
		||||
       +------------------+------------+------+----------------------------------+
 | 
			
		||||
       | From Release     | To Release |  RR  |    State                         |
 | 
			
		||||
       +------------------+------------+------+----------------------------------+
 | 
			
		||||
       | <new-maj-rel-id> | 10.0.0     | True | deploy-activate-rollback-pending |
 | 
			
		||||
       +------------------+------------+------+----------------------------------+
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy activate-rollback
 | 
			
		||||
       Deploy activate-rollback has started
 | 
			
		||||
 | 
			
		||||
   When running the :command:`software deploy activate-rollback` command, previous
 | 
			
		||||
   configurations are applied to the controller.
 | 
			
		||||
 | 
			
		||||
   Alarm 250.001 (Configuration is out-of-date) is raised and cleared as the
 | 
			
		||||
   configurations are applied.
 | 
			
		||||
 | 
			
		||||
   The software deployment state goes from ``activate-rollback-done`` to ``host-rollback``.
 | 
			
		||||
 | 
			
		||||
   This may take up to 30 mins to complete depending on system configuration
 | 
			
		||||
   and hardware.
 | 
			
		||||
 | 
			
		||||
   ..  code-block::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ software deploy show
 | 
			
		||||
        +------------------+------------+------+---------------+
 | 
			
		||||
        | From Release     | To Release |  RR  |    State      |
 | 
			
		||||
        +------------------+------------+------+---------------+
 | 
			
		||||
        | <new-maj-rel-id> | 10.0.0     | True | host-rollback |
 | 
			
		||||
        +------------------+------------+------+---------------+
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       If :command:`software deploy activate-rollback` fails, that is, if the state is
 | 
			
		||||
       ``activate-rollback-failed``, review ``/var/log/software.log`` on the
 | 
			
		||||
       active controller for failure details, address the issues, and
 | 
			
		||||
       re-execute the :command:`software deploy activate-rollback` command.
 | 
			
		||||
 | 
			
		||||
#. If the current deploy state is ``host-rollback``, then roll back the
 | 
			
		||||
   deployment of all the hosts.
 | 
			
		||||
 | 
			
		||||
   .. _manual-rollback-host-software-deployment-9295ce1e6e29-step:
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy show
 | 
			
		||||
       +------------------+------------+------+-------------------+
 | 
			
		||||
       | From Release     | To Release |  RR  |    State          |
 | 
			
		||||
       +------------------+------------+------+-------------------+
 | 
			
		||||
       | <new-maj-rel-id> | 10.0.0     | True | host-rollback     |
 | 
			
		||||
       +------------------+------------+------+-------------------+
 | 
			
		||||
 | 
			
		||||
   If the state is ``host-rollback``, then proceed with the rest of this step,
 | 
			
		||||
   otherwise proceed to :ref:`4 <manual-rollback-host-software-deployment-9295ce1e6e29-deletestep>`.
 | 
			
		||||
 | 
			
		||||
   - For an |AIO-SX| system
 | 
			
		||||
 | 
			
		||||
     #. Roll back the software release on controller-0.
 | 
			
		||||
 | 
			
		||||
        #. Lock controller-0.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ system host-lock controller-0
 | 
			
		||||
 | 
			
		||||
        #. Roll back the software release on controller-0.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ software deploy host-rollback controller-0
 | 
			
		||||
               Host installation request sent to controller-0.
 | 
			
		||||
               Host installation was successful on controller-0
 | 
			
		||||
 | 
			
		||||
            The host is still running the new software release, however boot
 | 
			
		||||
            parameters have been updated to boot into the previous software
 | 
			
		||||
            release on the next host reboot, which will occur in the next step
 | 
			
		||||
            which unlocks the host.
 | 
			
		||||
 | 
			
		||||
        #. Unlock controller-0.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ system host-unlock controller-0
 | 
			
		||||
 | 
			
		||||
           The host will now reboot into the previous software release. Wait for
 | 
			
		||||
           the host to finish rebooting and become available.
 | 
			
		||||
 | 
			
		||||
           This may take 3-5 mins depending on hardware.
 | 
			
		||||
 | 
			
		||||
     #. Proceed to step :ref:`4
 | 
			
		||||
        <manual-rollback-host-software-deployment-9295ce1e6e29-deletestep>` of
 | 
			
		||||
        the main procedure.
 | 
			
		||||
 | 
			
		||||
   - For an |AIO-DX| system or standard system
 | 
			
		||||
 | 
			
		||||
     #. If worker hosts are present, and one or more are in the ``pending-rollback``
 | 
			
		||||
        state, then roll back the software release on all worker hosts in the
 | 
			
		||||
        ``pending-rollback`` state one at a time. Otherwise, proceed to step :ref:`b <manual-rollback-host-software-deployment-9295ce1e6e29-storagehost>`.
 | 
			
		||||
 | 
			
		||||
        .. code-block::
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ software deploy host-list
 | 
			
		||||
            +--------------+------------------+------------+-------+------------------------------+
 | 
			
		||||
            | Host         | From Release     | To Release |  RR   |  State                       |
 | 
			
		||||
            +--------------+------------------+------------+-------+------------------------------+
 | 
			
		||||
            | controller-0 | <new-maj-rel-id> |  10.0.0    | True  | deploy-host-rollback-pending |
 | 
			
		||||
            | controller-1 | <new-maj-rel-id> |  10.0.0    | True  | deploy-host-rollback-pending |
 | 
			
		||||
            | storage-0    | <new-maj-rel-id> |  10.0.0    | True  | deploy-host-rollback-pending |
 | 
			
		||||
            | storage-1    | <new-maj-rel-id> |  10.0.0    | True  | deploy-host-rollback-pending |
 | 
			
		||||
            | storage-2    | <new-maj-rel-id> |  10.0.0    | True  | deploy-host-rollback-pending |
 | 
			
		||||
            | storage-3    | <new-maj-rel-id> |  10.0.0    | True  | deploy-host-rollback-pending |
 | 
			
		||||
            | worker-0     | <new-maj-rel-id> |  10.0.0    | True  | deploy-host-rollback-pending |
 | 
			
		||||
            | worker-1     | <new-maj-rel-id> |  10.0.0    | True  | deploy-host-rollback-pending |
 | 
			
		||||
            | worker-2     | <new-maj-rel-id> |  10.0.0    | True  | deploy-host-rollback-pending |
 | 
			
		||||
            | worker-3     | <new-maj-rel-id> |  10.0.0    | True  | deploy-host-rollback-deployed|
 | 
			
		||||
            +--------------+------------------+------------+-------+------------------------------+
 | 
			
		||||
 | 
			
		||||
        #. Roll back the software release on worker-0.
 | 
			
		||||
 | 
			
		||||
           #. Lock worker-0.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ system host-lock worker-0
 | 
			
		||||
 | 
			
		||||
           #. Roll back the software release on worker-0.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ software deploy host-rollback worker-0
 | 
			
		||||
                  Host installation request sent to worker-0
 | 
			
		||||
                  Host installation was successful on worker-0.
 | 
			
		||||
 | 
			
		||||
              The host is still running the new software release, however boot parameters
 | 
			
		||||
              have been updated to boot into the previous software release on the next
 | 
			
		||||
              host reboot, which will occur in the next step which unlocks the host.
 | 
			
		||||
 | 
			
		||||
           #. Unlock worker-0.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ system host-unlock worker-0
 | 
			
		||||
 | 
			
		||||
              The host will now reboot into the previous software release. Wait
 | 
			
		||||
              for the host to finish rebooting and become available. Wait
 | 
			
		||||
              for all the alarms to clear after the unlock before proceeding to the
 | 
			
		||||
              next worker host.
 | 
			
		||||
 | 
			
		||||
              This may take 3-5 mins depending on hardware.
 | 
			
		||||
 | 
			
		||||
           #. Display the state of software deployment.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ software deploy host-list
 | 
			
		||||
               +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
               | Host         | From Release     | To Release |  RR   |  State           |
 | 
			
		||||
               +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
               | controller-0 | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
               | controller-1 | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
               | storage-0    | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
               | storage-1    | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
               | storage-2    | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
               | storage-3    | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
               | worker-0     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
               | worker-1     | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
               | worker-2     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
               | worker-3     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
               +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
 | 
			
		||||
        #. Repeat the above steps for any remaining worker hosts in the ``pending-rollback`` state.
 | 
			
		||||
 | 
			
		||||
     #. If storage hosts are present, and one or more are in the ``pending-rollback`` state,
 | 
			
		||||
        then roll back the software release on all storage hosts in the ``pending-rollback`` state,
 | 
			
		||||
        one at a time. Otherwise, proceed to step :ref:`c <manual-rollback-host-software-deployment-9295ce1e6e29-bothcontrollers>`.
 | 
			
		||||
 | 
			
		||||
        .. _manual-rollback-host-software-deployment-9295ce1e6e29-storagehost:
 | 
			
		||||
 | 
			
		||||
        .. code-block::
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ software deploy host-list
 | 
			
		||||
            +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
            | Host         | From Release     | To Release |  RR   |  State           |
 | 
			
		||||
            +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
            | controller-0 | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
            | controller-1 | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
            | storage-0    | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
            | storage-1    | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
            | storage-2    | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
            | storage-3    | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
            | worker-0     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
            | worker-1     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
            | worker-2     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
            | worker-3     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
            +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
 | 
			
		||||
        #. Roll back the software release on storage-0.
 | 
			
		||||
 | 
			
		||||
           #. Lock storage-0.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ system host-lock storage-0
 | 
			
		||||
 | 
			
		||||
           #. Roll back the software release on storage-0.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ software deploy host-rollback storage-0
 | 
			
		||||
                  Host installation request sent to storage-0
 | 
			
		||||
                  Host installation was successful on storage-0.
 | 
			
		||||
 | 
			
		||||
              The host is still running the new software release,
 | 
			
		||||
              however boot parameters have been updated to boot into
 | 
			
		||||
              the previous software release on the next host reboot, which
 | 
			
		||||
              will occur in the next step which unlocks the host.
 | 
			
		||||
 | 
			
		||||
           #. Unlock storage-0.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ system host-unlock storage-0
 | 
			
		||||
 | 
			
		||||
              The host will now reboot into the previous software release. Wait
 | 
			
		||||
              for the host to finish rebooting and become available. Wait for
 | 
			
		||||
              all the alarms to clear after the unlock before proceeding to the next
 | 
			
		||||
              storage host.
 | 
			
		||||
 | 
			
		||||
              This may take 3-5 mins depending on hardware.
 | 
			
		||||
 | 
			
		||||
           #. Display the state of software deployment.
 | 
			
		||||
 | 
			
		||||
              ..  code-block::
 | 
			
		||||
 | 
			
		||||
                   ~(keystone_admin)]$ software deploy host-list
 | 
			
		||||
                   +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
                   | Host         | From Release     | To Release |  RR   |  State           |
 | 
			
		||||
                   +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
                   | controller-0 | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
                   | controller-1 | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
                   | storage-0    | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   | storage-1    | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
                   | storage-2    | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
                   | storage-3    | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
                   | worker-0     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   | worker-1     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   | worker-2     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   | worker-3     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
 | 
			
		||||
        #. Repeat the above steps for any remaining storage hosts in the
 | 
			
		||||
      	   ``pending-rollback`` state.
 | 
			
		||||
 | 
			
		||||
           .. note::
 | 
			
		||||
 | 
			
		||||
               After rolling back the first storage host, you can expect alarm
 | 
			
		||||
               800.003. The alarm is cleared after all the storage hosts are rolled
 | 
			
		||||
               back.
 | 
			
		||||
 | 
			
		||||
     #. If both the controllers are in the ``pending-rollback`` state, then roll back
 | 
			
		||||
        controller-0 first.
 | 
			
		||||
 | 
			
		||||
        .. _manual-rollback-host-software-deployment-9295ce1e6e29-bothcontrollers:
 | 
			
		||||
 | 
			
		||||
        #. Ensure that controller-1 is active by switching activity from
 | 
			
		||||
           controller-0.
 | 
			
		||||
 | 
			
		||||
           ..  code-block::
 | 
			
		||||
 | 
			
		||||
                ~(keystone_admin)]$ system host-swact controller-0
 | 
			
		||||
 | 
			
		||||
           Wait for the activity to switch to controller-1. This may take up to a
 | 
			
		||||
           minute depending on hardware. Reconnect to the system.
 | 
			
		||||
 | 
			
		||||
        #. Roll back the software release on controller-0 (the standby controller).
 | 
			
		||||
 | 
			
		||||
           #. Lock controller-0.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ system host-lock controller-0
 | 
			
		||||
 | 
			
		||||
           #. Rollback the software release on controller-0.
 | 
			
		||||
 | 
			
		||||
              ..  code-block::
 | 
			
		||||
 | 
			
		||||
                   ~(keystone_admin)]$ software deploy host controller-0
 | 
			
		||||
                   Host installation request sent to controller-0.
 | 
			
		||||
                   Host installation was successful on controller-0.
 | 
			
		||||
 | 
			
		||||
              The host is still running the new software release,
 | 
			
		||||
              however boot parameters have been updated to boot into
 | 
			
		||||
              the previous software release on the next host reboot, which
 | 
			
		||||
              will occur in the next step which unlocks the host.
 | 
			
		||||
 | 
			
		||||
           #. Unlock controller-0.
 | 
			
		||||
 | 
			
		||||
              ..  code-block::
 | 
			
		||||
 | 
			
		||||
                   ~(keystone_admin)]$ system host-unlock controller-0
 | 
			
		||||
 | 
			
		||||
              The host will now reboot into the new software release. Wait for
 | 
			
		||||
              the host to finish rebooting and become available.
 | 
			
		||||
 | 
			
		||||
              This may take 3-5 mins depending on hardware.
 | 
			
		||||
 | 
			
		||||
           #. Display the state of software deployment.
 | 
			
		||||
 | 
			
		||||
              ..  code-block::
 | 
			
		||||
 | 
			
		||||
                   ~(keystone_admin)]$ software deploy host-list
 | 
			
		||||
                   +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
                   | Host         | From Release     | To Release |  RR   |  State           |
 | 
			
		||||
                   +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
                   | controller-0 | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   | controller-1 | <new-maj-rel-id> |  10.0.0    | True  | pending-rollback |
 | 
			
		||||
                   | storage-0    | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   | storage-1    | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   | storage-2    | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   | storage-3    | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   | worker-0     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   | worker-1     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   | worker-2     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   | worker-3     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                   +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
 | 
			
		||||
     #. If only controller-1 is in the ``pending-rollback`` state, then roll
 | 
			
		||||
        back controller-1.
 | 
			
		||||
 | 
			
		||||
        #. Ensure that controller-0 is active by switching activity from
 | 
			
		||||
           controller-1.
 | 
			
		||||
 | 
			
		||||
           .. code-block::
 | 
			
		||||
 | 
			
		||||
               ~(keystone_admin)]$ system host-swact controller-1
 | 
			
		||||
 | 
			
		||||
           Wait for the activity to switch to controller-0.
 | 
			
		||||
 | 
			
		||||
           This may take up to a minute depending on hardware.
 | 
			
		||||
 | 
			
		||||
           Reconnect to the system.
 | 
			
		||||
 | 
			
		||||
        #. Roll back the software release on controller-1 (the standby controller).
 | 
			
		||||
 | 
			
		||||
           #. Lock controller-1
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ system host-lock controller-1
 | 
			
		||||
 | 
			
		||||
           #. Roll back the software release on controller-1.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ software deploy host controller-1
 | 
			
		||||
                  Host installation request sent to controller-1.
 | 
			
		||||
                  Host installation was successful on controller-1.
 | 
			
		||||
 | 
			
		||||
              The host is still running the new software release, however boot
 | 
			
		||||
              parameters have been updated to boot into the previous software
 | 
			
		||||
              release on the next host reboot, which will occur in the next step
 | 
			
		||||
              which unlocks the host.
 | 
			
		||||
 | 
			
		||||
           #. Unlock controller-1.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ system host-unlock controller-1
 | 
			
		||||
 | 
			
		||||
              The host will now reboot into the new software release. Wait for
 | 
			
		||||
              the host to finish rebooting and become available.
 | 
			
		||||
 | 
			
		||||
              This may take 3-5 mins depending on hardware.
 | 
			
		||||
 | 
			
		||||
           #. Display the state of software deployment.
 | 
			
		||||
 | 
			
		||||
              .. code-block::
 | 
			
		||||
 | 
			
		||||
                  ~(keystone_admin)]$ software deploy host-list
 | 
			
		||||
                  +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
                  | Host         | From Release     | To Release |  RR   |  State           |
 | 
			
		||||
                  +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
                  | controller-0 | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                  | controller-1 | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                  | storage-0    | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                  | storage-1    | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                  | storage-2    | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                  | storage-3    | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                  | worker-0     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                  | worker-1     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                  | worker-2     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                  | worker-3     | <new-maj-rel-id> |  10.0.0    | True  | rolled back      |
 | 
			
		||||
                  +--------------+------------------+------------+-------+------------------+
 | 
			
		||||
 | 
			
		||||
#. Delete the software deployment to complete the rollback.
 | 
			
		||||
 | 
			
		||||
   .. _manual-rollback-host-software-deployment-9295ce1e6e29-deletestep:
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy delete
 | 
			
		||||
       Deployment has been deleted
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software deploy show
 | 
			
		||||
       No deploy in progress
 | 
			
		||||
 | 
			
		||||
#. Confirm that the previous software release is now deployed.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ software list
 | 
			
		||||
       +--------------------------+-------+-----------+
 | 
			
		||||
       | Release                  | RR    |   State   |
 | 
			
		||||
       +--------------------------+-------+-----------+
 | 
			
		||||
       | starlingx-10.0.0         | True  | deployed  |
 | 
			
		||||
       | <new-maj-rel-id>         | True  | available |
 | 
			
		||||
       +--------------------------+-------+-----------+
 | 
			
		||||
@@ -1,47 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. mzg1592854560344
 | 
			
		||||
.. _manual-upgrade-overview:
 | 
			
		||||
 | 
			
		||||
=======================
 | 
			
		||||
Manual Upgrade Overview
 | 
			
		||||
=======================
 | 
			
		||||
 | 
			
		||||
|prod-long| enables you to upgrade the software across your Simplex, Duplex,
 | 
			
		||||
Standard, |prod-dc|, and subcloud deployments.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
    Upgrading |prod-dc| is distinct from upgrading other |prod| configurations.
 | 
			
		||||
 | 
			
		||||
.. xbooklink    For information on updating |prod-dc|, see |distcloud-doc|: :ref:`Upgrade
 | 
			
		||||
    Management <upgrade-management-overview>`.
 | 
			
		||||
 | 
			
		||||
An upgrade can be performed manually or using the Upgrade Orchestrator, which
 | 
			
		||||
automates a rolling install of an update across all of the |prod-long| hosts.
 | 
			
		||||
This section describes the manual upgrade procedures.
 | 
			
		||||
 | 
			
		||||
.. xbooklink For the orchestrated
 | 
			
		||||
   procedure, see |distcloud-doc|: :ref:`Orchestration Upgrade Overview
 | 
			
		||||
   <orchestration-upgrade-overview>`.
 | 
			
		||||
 | 
			
		||||
Before starting the upgrade process, ensure that the following conditions are
 | 
			
		||||
met:
 | 
			
		||||
 | 
			
		||||
-   The system is patch current.
 | 
			
		||||
 | 
			
		||||
-   There are no management-affecting alarms and the :command:`system
 | 
			
		||||
    health-query-upgrade` check passes.
 | 
			
		||||
 | 
			
		||||
-   The new software load has been imported.
 | 
			
		||||
 | 
			
		||||
-   A valid license file has been installed.
 | 
			
		||||
 | 
			
		||||
The upgrade procedure is different for the All-in-One Simplex configuration
 | 
			
		||||
versus the All-in-One Duplex, and Standard configurations. For more
 | 
			
		||||
information, see:
 | 
			
		||||
 | 
			
		||||
.. _manual-upgrade-overview-ul-bcp-ght-cmb:
 | 
			
		||||
 | 
			
		||||
-   :ref:`Upgrading All-in-One Simplex <upgrading-all-in-one-simplex>`
 | 
			
		||||
 | 
			
		||||
-   :ref:`Upgrading All-in-One Duplex / Standard <upgrading-all-in-one-duplex-or-standard>`
 | 
			
		||||
 | 
			
		||||
@@ -0,0 +1,670 @@
 | 
			
		||||
.. WARNING: Add no lines of text between the label immediately following
 | 
			
		||||
.. and the title.
 | 
			
		||||
 | 
			
		||||
.. _orchestrated-deployment-host-software-deployment-d234754c7d20:
 | 
			
		||||
 | 
			
		||||
================================================
 | 
			
		||||
Orchestrated Deployment Host Software Deployment
 | 
			
		||||
================================================
 | 
			
		||||
 | 
			
		||||
Software deployment orchestration automates the process of upversioning the
 | 
			
		||||
|prod| software to a new major release or new patch release (In-Service or
 | 
			
		||||
Reboot Required (RR)). It automates the execution of all :command:`software deploy`
 | 
			
		||||
steps across all the hosts in a cluster, based on the configured policies.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    Software deployment orchestration also covers the orchestrated upversioning
 | 
			
		||||
    to a new patched major release, that is, all the comments in this section
 | 
			
		||||
    that are specific to major release also apply to a patched major release.
 | 
			
		||||
 | 
			
		||||
Software deployment Orchestration supports all standalone configurations:
 | 
			
		||||
|AIO-SX|, |AIO-DX| and standard configuration.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    Orchestrating the software deployment of a |DC| system is different from
 | 
			
		||||
    orchestrating the software deployment of standalone |prod| configurations.
 | 
			
		||||
 | 
			
		||||
Software deployment orchestration automatically iterates through all the hosts
 | 
			
		||||
and deploys the new software load on each host: first the controller hosts,
 | 
			
		||||
then the storage hosts, and lastly the worker hosts, and finally activates and
 | 
			
		||||
completes the software deployment. During software deployment on a worker host
 | 
			
		||||
(and duplex |AIO| controllers), pods or |VMs| are automatically moved to the
 | 
			
		||||
alternate worker hosts. After software deployment orchestration has deployed
 | 
			
		||||
the new software on all hosts, it will activate, complete, and delete the new
 | 
			
		||||
software deployment.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    Software deployment orchestration completes and deletes the new software
 | 
			
		||||
    deployment only when the ``-delete`` option is selected by the user during
 | 
			
		||||
    create strategy. In case of a Major Release, if the software deployment is
 | 
			
		||||
    deleted, it can no longer be rolled back.
 | 
			
		||||
 | 
			
		||||
To perform a software deployment orchestration, first create an upgrade
 | 
			
		||||
orchestration strategy for the automated software deployment procedure. This
 | 
			
		||||
provides polices to perform the software deployment orchestration using the following
 | 
			
		||||
parameters:
 | 
			
		||||
 | 
			
		||||
-   The host types to be software deployed.
 | 
			
		||||
 | 
			
		||||
-   Whether to deploy the software to hosts serially or in parallel.
 | 
			
		||||
 | 
			
		||||
    -   The maximum number of hosts to deploy in parallel.
 | 
			
		||||
 | 
			
		||||
-   Maintenance action (stop-start or migrate) for hosted OpenStack |VMs|
 | 
			
		||||
    on a host that is about to have its software updated.
 | 
			
		||||
 | 
			
		||||
-   Alarm restrictions, that is, options to specify how the orchestration behaves
 | 
			
		||||
    when alarms occur.
 | 
			
		||||
 | 
			
		||||
Based on these parameters and the state of the hosts, software deployment
 | 
			
		||||
orchestration creates a number of stages for the overall software deployment
 | 
			
		||||
strategy. Each stage generally consists of deploying software on hosts for a
 | 
			
		||||
subset of the hosts on the system.  In the case of a reboot required (RR)
 | 
			
		||||
software release, each stage consists of moving pods or |VMs|, locking hosts,
 | 
			
		||||
deploying software on hosts, and unlocking hosts for a subset of the hosts on
 | 
			
		||||
the system. After creating the software deployment orchestration strategy, you
 | 
			
		||||
can either apply the entire strategy automatically or apply individual stages
 | 
			
		||||
to control and monitor their progress manually.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |prereq|
 | 
			
		||||
 | 
			
		||||
- No other orchestration strategy exists. Firmware-upgrade,
 | 
			
		||||
  kubernetes-version-upgrade, system-config-update-strategy, and
 | 
			
		||||
  kube-rootca-update are other types of orchestration. A software deployment
 | 
			
		||||
  cannot be orchestrated while another orchestration is in progress.
 | 
			
		||||
 | 
			
		||||
- You have the administrator role privileges.
 | 
			
		||||
 | 
			
		||||
- The system is clear of alarms except the software deployment in progress alarm.
 | 
			
		||||
 | 
			
		||||
- All the hosts are unlocked, enabled, and available.
 | 
			
		||||
 | 
			
		||||
- For Duplex systems, the system should be fully redundant. There should be two controller
 | 
			
		||||
  nodes available, at least one complete storage replication group available
 | 
			
		||||
  for systems with Ceph backend.
 | 
			
		||||
 | 
			
		||||
- Sufficient free capacity or unused worker resources must be available
 | 
			
		||||
  across the cluster. A rough calculation is:
 | 
			
		||||
 | 
			
		||||
  ``Required spare capacity ( %) = (<Number-of-hosts-to-upgrade-in-parallel> / <total-number-of-hosts>) * 100``
 | 
			
		||||
 | 
			
		||||
- For a major release deployment, the license for the new release has been installed using
 | 
			
		||||
  :command:`system license-install <license-for-new-major-release>`.
 | 
			
		||||
 | 
			
		||||
- The software release to be deployed has been uploaded.
 | 
			
		||||
 | 
			
		||||
  - For a major release:
 | 
			
		||||
 | 
			
		||||
    .. code-block::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ software upload [ --local ] <new-release>.iso
 | 
			
		||||
        <new-release>.sig <new-release-id> is now uploaded
 | 
			
		||||
        +-------------------------------+-------------------+
 | 
			
		||||
        | Uploaded File                 | Release           |
 | 
			
		||||
        +-------------------------------+-------------------+
 | 
			
		||||
        | <new-release>.iso             | <new-release-id>  |
 | 
			
		||||
        +-------------------------------+-------------------+
 | 
			
		||||
 | 
			
		||||
    This command may take 5-10 mins depending on hardware.
 | 
			
		||||
 | 
			
		||||
    where `--local` can be used when running this command in an |SSH| session
 | 
			
		||||
    on the active controller to optimize performance. With this option, the
 | 
			
		||||
    system will read files directly from the local disk rather than
 | 
			
		||||
    transferring files over REST APIs backing the |CLI|.
 | 
			
		||||
 | 
			
		||||
  - For a patch release:
 | 
			
		||||
 | 
			
		||||
    .. code-block::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ software upload <filename>.patch
 | 
			
		||||
        <release-id> is now uploaded
 | 
			
		||||
        +-------------------------------+-------------------+
 | 
			
		||||
        | Uploaded File                 | Release           |
 | 
			
		||||
        +-------------------------------+-------------------+
 | 
			
		||||
        | <new-release>.patch           | <new-release-id>  |
 | 
			
		||||
        +-------------------------------+-------------------+
 | 
			
		||||
 | 
			
		||||
  - Ensure that the new software release was successfully uploaded.
 | 
			
		||||
 | 
			
		||||
    .. code-block::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ software list
 | 
			
		||||
        +--------------------------+-------+-----------+
 | 
			
		||||
        | Release                  | RR    |   State   |
 | 
			
		||||
        +--------------------------+-------+-----------+
 | 
			
		||||
        | starlingx-10.0.0         | True  | deployed  |
 | 
			
		||||
        | <new-release-id>         | True  | available |
 | 
			
		||||
        +--------------------------+-------+-----------+
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#. Create a software deployment orchestration strategy for a specified software
 | 
			
		||||
   release with desired policies.
 | 
			
		||||
 | 
			
		||||
   .. _orchestrated-deployment-host-software-deployment-d234754c7d20-step:
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ sw-manager sw-deploy-strategy create [--controller-apply-type {serial,ignore}]
 | 
			
		||||
                                                                [--storage-apply-type {serial,parallel,ignore}]
 | 
			
		||||
                                                                [--worker-apply-type {serial,parallel,ignore}]
 | 
			
		||||
                                                                [--max-parallel-worker-hosts {2,3,4,5,6,7,8,9,10}]
 | 
			
		||||
                                                                [--instance-action {stop-start,migrate}]
 | 
			
		||||
                                                                [--alarm-restrictions {strict,relaxed}]
 | 
			
		||||
                                                                [--delete]
 | 
			
		||||
                                                                <software-release-id>
 | 
			
		||||
 | 
			
		||||
       strategy-uuid:                          5435e049-7002-4403-acfb-7886f6da14af
 | 
			
		||||
       release-id:                             <software-release-id>
 | 
			
		||||
       controller-apply-type:                  serial
 | 
			
		||||
       storage-apply-type:                     serial
 | 
			
		||||
       worker-apply-type:                      serial
 | 
			
		||||
       default-instance-action:                stop-start
 | 
			
		||||
       alarm-restrictions:                     strict
 | 
			
		||||
       current-phase:                          build
 | 
			
		||||
       current-phase-completion:               0%
 | 
			
		||||
       state:                                  building
 | 
			
		||||
       inprogress:                             true
 | 
			
		||||
 | 
			
		||||
   where,
 | 
			
		||||
 | 
			
		||||
   ``<software-release-id>``
 | 
			
		||||
       Specifies the specific software release to deploy. This can be a patch
 | 
			
		||||
       release or a major release.
 | 
			
		||||
 | 
			
		||||
   ``[--controller-apply-type {serial,ignore}]``
 | 
			
		||||
       (Optional) Specifies whether software should be deployed to controller
 | 
			
		||||
       hosts in serial or ignored. By default, it is serial. ``ignore`` should
 | 
			
		||||
       be used only when re-creating and applying a strategy after an abort or
 | 
			
		||||
       failure.
 | 
			
		||||
 | 
			
		||||
   ``[--storage-apply-type {serial,parallel,ignore}]``
 | 
			
		||||
       (Optional) Specifies whether software should be deployed to storage
 | 
			
		||||
       hosts in serial, in parallel, or ignored. By default, it is serial.
 | 
			
		||||
       Software is deployed to storage hosts in parallel by software deploying
 | 
			
		||||
       a storage host from each storage redundancy group. ``ignore`` should be
 | 
			
		||||
       used only when re-creating and applying a strategy after an abort or
 | 
			
		||||
       failure.
 | 
			
		||||
 | 
			
		||||
       .. note::
 | 
			
		||||
 | 
			
		||||
           If parallel apply for storage is used, it will be automatically
 | 
			
		||||
           replaced with the serial apply for ``--storage-apply-type``.
 | 
			
		||||
 | 
			
		||||
   ``[--worker-apply-type {serial,parallel,ignore}]``
 | 
			
		||||
       (Optional) Specifies whether software should be deployed to worker hosts
 | 
			
		||||
       in serial, in parallel or ignored. By default, it is serial. The number
 | 
			
		||||
       of worker hosts that are software deployed in parallel is specified by
 | 
			
		||||
       ``[--max-parallel-worker-hosts {2,3,4,5,6,7,8,9,10}]``. The default is
 | 
			
		||||
       2. ``ignore`` should be used only when re-creating and applying a
 | 
			
		||||
       strategy after an abort or failure.
 | 
			
		||||
 | 
			
		||||
   ``[--max-parallel-worker-hosts {2,3,4,5,6,7,8,9,10}]``
 | 
			
		||||
       Specifies the number of worker hosts that are software deployed in
 | 
			
		||||
       parallel that is specified by ``[--max-parallel-worker-hosts
 | 
			
		||||
       {2,3,4,5,6,7,8,9,10}]``. The default is 2.
 | 
			
		||||
 | 
			
		||||
   ``[--instance-action {stop-start,migrate}]``
 | 
			
		||||
       Applies only to OpenStack |VM| hosted guests. It specifies the action
 | 
			
		||||
       performed to hosted OpenStack |VMs| on a worker host (or |AIO|
 | 
			
		||||
       controller) prior to deploying the new software to the host. The default
 | 
			
		||||
       is ``stop-start``.
 | 
			
		||||
 | 
			
		||||
       - ``stop-start``
 | 
			
		||||
 | 
			
		||||
         Before deploying the software release to the host, all the hosted
 | 
			
		||||
         OpenStack |VMs| are stopped or shutdown.
 | 
			
		||||
 | 
			
		||||
         After deploying the software release to the host, all the hosted
 | 
			
		||||
         OpenStack |VMs| are restarted.
 | 
			
		||||
 | 
			
		||||
       - ``migrate``
 | 
			
		||||
 | 
			
		||||
         Before deploying the software release to the host, all the hosted
 | 
			
		||||
         OpenStack |VMs| are migrated to another host capable of hosting the
 | 
			
		||||
         hosted OpenStack |VM| and that is not part of the current stage.
 | 
			
		||||
 | 
			
		||||
         - Hosts whose software is already updated are preferred over the hosts
 | 
			
		||||
           whose software has not been updated yet.
 | 
			
		||||
 | 
			
		||||
         - Live migration is attempted first. If live migration is not
 | 
			
		||||
           possible for the OpenStack |VM|, cold migration is performed.
 | 
			
		||||
 | 
			
		||||
   ``[--alarm-restrictions {strict,relaxed}]``
 | 
			
		||||
       Lets you determine how to handle alarm restrictions based on the
 | 
			
		||||
       management affecting statuses of any existing alarms, which takes into
 | 
			
		||||
       account the alarm type as well as the alarm's current severity. Default
 | 
			
		||||
       is strict. If set to relaxed, orchestration will be allowed to proceed
 | 
			
		||||
       if there are no management affecting alarms present.
 | 
			
		||||
 | 
			
		||||
       Performing management actions without specifically relaxing the alarm
 | 
			
		||||
       checks will still fail if there are any alarms present in the system
 | 
			
		||||
       (except for a small list of basic alarms for the orchestration actions,
 | 
			
		||||
       such as an upgrade operation in progress alarm not impeding upgrade
 | 
			
		||||
       orchestration). You can use the CLI command :command:`fm alarm-list
 | 
			
		||||
       --mgmt_affecting` to view the alarms that are management affecting.
 | 
			
		||||
 | 
			
		||||
       - ``Strict`` maintains alarm restrictions.
 | 
			
		||||
 | 
			
		||||
       - ``Relaxed`` relaxes the usual alarm restrictions and allows the action to
 | 
			
		||||
         proceed if there are no alarms present in the system with a severity equal
 | 
			
		||||
         to or greater than its management affecting severity. That is, it will use
 | 
			
		||||
         the ``-f`` (force) option on the precheck or start of the deployment.
 | 
			
		||||
 | 
			
		||||
    ``[--delete]``
 | 
			
		||||
        (Optional) Specifies if the software deployment needs to be deleted or not.
 | 
			
		||||
 | 
			
		||||
#. Wait for the ``build`` phase of the software deployment orchestration
 | 
			
		||||
   strategy create to be 100% complete and its state to be ``ready-to-apply``.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ sw-manager sw-deploy-strategy show
 | 
			
		||||
       Strategy Software Deploy Strategy:
 | 
			
		||||
         strategy-uuid:                          6282f049-bb9e-46f0-9ca8-97bf626884e0
 | 
			
		||||
         release-id:                             <software-release-id>
 | 
			
		||||
         controller-apply-type:                  serial
 | 
			
		||||
         storage-apply-type:                     serial
 | 
			
		||||
         worker-apply-type:                      serial
 | 
			
		||||
         default-instance-action:                stop-start
 | 
			
		||||
         alarm-restrictions:                     strict
 | 
			
		||||
         current-phase:                          build
 | 
			
		||||
         current-phase-completion:               100%
 | 
			
		||||
         state:                                  ready-to-apply
 | 
			
		||||
         build-result:                           success
 | 
			
		||||
         build-reason:
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       If the build phase fails (``build-result:  failed`` that will appear in
 | 
			
		||||
       the show command), determine the issue from the build error reason
 | 
			
		||||
       (``build-reason: <Error information>`` that will appear in the show
 | 
			
		||||
       command) and/or in ``/var/log/nfv-vim*.log`` on the active controller,
 | 
			
		||||
       address the issues, delete the strategy, and retry the create.
 | 
			
		||||
 | 
			
		||||
#. (Optional) Displays ``--error-details`` (phases and steps) of the build strategy.
 | 
			
		||||
 | 
			
		||||
   The software deploy strategy consists of one or more stages, which consist
 | 
			
		||||
   of one or more hosts to have the new software deployed at the same time.
 | 
			
		||||
 | 
			
		||||
   Each stage will be split into steps (for example, query-alarms, lock-hosts,
 | 
			
		||||
   upgrade-hosts).
 | 
			
		||||
 | 
			
		||||
   The new software is deployed on the controller hosts first, followed by the
 | 
			
		||||
   storage hosts, and then the worker hosts.
 | 
			
		||||
 | 
			
		||||
   The new software is deployed on the worker hosts with no hosted guests
 | 
			
		||||
   (Kubernetes pods or OpenStack |VMs|) and before the worker hosts with hosted guests
 | 
			
		||||
   (Kubernetes pods or OpenStack |VMs|).
 | 
			
		||||
 | 
			
		||||
   Hosted Kubernetes pods will be relocated off each worker host
 | 
			
		||||
   (AIO-Controller) if another worker host capable of hosting the Kubernetes
 | 
			
		||||
   pods is available before the new software is deployed to the worker host
 | 
			
		||||
   (AIO-Controller).
 | 
			
		||||
 | 
			
		||||
   Hosted OpenStack |VMs| will be managed according to the requested
 | 
			
		||||
   ``--instance-action`` on each worker host (AIO-Controller) before the new
 | 
			
		||||
   software is deployed to the worker host (AIO-Controller).
 | 
			
		||||
 | 
			
		||||
   The final step in each stage is one of the following:
 | 
			
		||||
 | 
			
		||||
   ``system-stabilize``
 | 
			
		||||
 | 
			
		||||
   This waits for a period of time (up to several minutes) and ensures that the
 | 
			
		||||
   system is free of alarms.
 | 
			
		||||
 | 
			
		||||
   This ensures that we do not continue to deploy the new software to more
 | 
			
		||||
   hosts if the software deployment has caused an issue resulting in an alarm.
 | 
			
		||||
 | 
			
		||||
   ``wait-data-sync``
 | 
			
		||||
 | 
			
		||||
   This waits for a period of time (up to many hours) and ensures that data
 | 
			
		||||
   synchronization has completed after the upgrade of a controller or storage
 | 
			
		||||
   node.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ sw-manager sw-deploy-strategy show --details
 | 
			
		||||
 | 
			
		||||
       Strategy Software Deploy Strategy:
 | 
			
		||||
        strategy-uuid:                          6282f049-bb9e-46f0-9ca8-97bf626884e0
 | 
			
		||||
        release-id:                             <software-release-id>
 | 
			
		||||
        controller-apply-type:                  serial
 | 
			
		||||
        storage-apply-type:                     serial
 | 
			
		||||
        worker-apply-type:                      serial
 | 
			
		||||
        default-instance-action:                stop-start
 | 
			
		||||
        alarm-restrictions:                     strict
 | 
			
		||||
        current-phase:                          build
 | 
			
		||||
        current-phase-completion:               100%
 | 
			
		||||
        state:                                  ready-to-apply
 | 
			
		||||
 | 
			
		||||
        build-phase:
 | 
			
		||||
          ...
 | 
			
		||||
          stages:
 | 
			
		||||
            ...
 | 
			
		||||
            steps:
 | 
			
		||||
              ...
 | 
			
		||||
 | 
			
		||||
        apply-phase:
 | 
			
		||||
          ...
 | 
			
		||||
          stages:
 | 
			
		||||
            ...
 | 
			
		||||
            steps:
 | 
			
		||||
              ...
 | 
			
		||||
 | 
			
		||||
#. Apply and monitor the software deployment orchestration.
 | 
			
		||||
 | 
			
		||||
   You can either apply the entire strategy automatically or apply the
 | 
			
		||||
   individual stages to control and monitor their progress manually.
 | 
			
		||||
 | 
			
		||||
   #. Apply the entire strategy automatically and monitor its progress:
 | 
			
		||||
 | 
			
		||||
      .. code-block::
 | 
			
		||||
 | 
			
		||||
          ~(keystone_admin)]$ sw-manager sw-deploy-strategy apply
 | 
			
		||||
          Strategy Software Deploy Strategy:
 | 
			
		||||
            strategy-uuid:                          52873771-fc1a-48cd-b322-ab921d34d01c
 | 
			
		||||
            release-id:                             <software-release-id>
 | 
			
		||||
            controller-apply-type:                  serial
 | 
			
		||||
            storage-apply-type:                     serial
 | 
			
		||||
            worker-apply-type:                      serial
 | 
			
		||||
            default-instance-action:                stop-start
 | 
			
		||||
            alarm-restrictions:                     strict
 | 
			
		||||
            current-phase:                          apply
 | 
			
		||||
            current-phase-completion:               0%
 | 
			
		||||
            state:                                  applying
 | 
			
		||||
            inprogress:                             true
 | 
			
		||||
 | 
			
		||||
      Show high-level status of apply.
 | 
			
		||||
 | 
			
		||||
      .. code-block::
 | 
			
		||||
 | 
			
		||||
          ~(keystone_admin)]$ sw-manager sw-deploy-strategy show
 | 
			
		||||
          Strategy Software Deploy Strategy:
 | 
			
		||||
            strategy-uuid:                          35b48793-66f8-46be-8972-cc22117a93ff
 | 
			
		||||
            release-id:                             <software-release-id>
 | 
			
		||||
            controller-apply-type:                  serial
 | 
			
		||||
            storage-apply-type:                     serial
 | 
			
		||||
            worker-apply-type:                      serial
 | 
			
		||||
            default-instance-action:                stop-start
 | 
			
		||||
            alarm-restrictions:                     strict
 | 
			
		||||
            current-phase:                          apply
 | 
			
		||||
            current-phase-completion:               7%
 | 
			
		||||
            state:                                  applying
 | 
			
		||||
            inprogress:                             true
 | 
			
		||||
 | 
			
		||||
      Show details of active stage or step of apply.
 | 
			
		||||
 | 
			
		||||
      .. code-block::
 | 
			
		||||
 | 
			
		||||
          ~(keystone_admin)]$ sw-manager sw-deploy-strategy show --active
 | 
			
		||||
          Strategy Software Deploy Strategy:
 | 
			
		||||
            strategy-uuid:                          52873771-fc1a-48cd-b322-ab921d34d01c
 | 
			
		||||
            release-id:                             <software-release-id>
 | 
			
		||||
            controller-apply-type:                  serial
 | 
			
		||||
            storage-apply-type:                     serial
 | 
			
		||||
            worker-apply-type:                      serial
 | 
			
		||||
            default-instance-action:                stop-start
 | 
			
		||||
            alarm-restrictions:                     strict
 | 
			
		||||
            current-phase:                          apply
 | 
			
		||||
            current-phase-completion:               7%
 | 
			
		||||
            state:                                  applying
 | 
			
		||||
            apply-phase:
 | 
			
		||||
              total-stages:                         3
 | 
			
		||||
              current-stage:                        0
 | 
			
		||||
              stop-at-stage:                        3
 | 
			
		||||
              timeout:                              12019 seconds
 | 
			
		||||
              completion-percentage:                7%
 | 
			
		||||
              start-date-time:                      2024-06-11 12:19:51
 | 
			
		||||
              inprogress:                           true
 | 
			
		||||
              stages:
 | 
			
		||||
                  stage-id:                         0
 | 
			
		||||
                  stage-name:                       sw-upgrade-start
 | 
			
		||||
                  total-steps:                      3
 | 
			
		||||
                  current-step:                     1
 | 
			
		||||
                  timeout:                          1321 seconds
 | 
			
		||||
                  start-date-time:                  2024-06-11 12:19:51
 | 
			
		||||
                  inprogress:                       true
 | 
			
		||||
                  steps:
 | 
			
		||||
                      step-id:                      1
 | 
			
		||||
                      step-name:                    start-upgrade
 | 
			
		||||
                      timeout:                      1200 seconds
 | 
			
		||||
                      start-date-time:              2024-06-11 12:19:51
 | 
			
		||||
                      result:                       wait
 | 
			
		||||
                      reason:
 | 
			
		||||
 | 
			
		||||
   #. Apply individual stages.
 | 
			
		||||
 | 
			
		||||
      .. code-block::
 | 
			
		||||
 | 
			
		||||
          ~(keystone_admin)]$ sw-manager sw-deploy-strategy apply --stage-id <STAGE-ID>
 | 
			
		||||
          Strategy Software Deploy Strategy:
 | 
			
		||||
            strategy-uuid:                          a0277e08-93cc-4964-ba39-ebab367a547c
 | 
			
		||||
            release-id:                             <software-release-id>
 | 
			
		||||
            controller-apply-type:                  serial
 | 
			
		||||
            storage-apply-type:                     serial
 | 
			
		||||
            worker-apply-type:                      serial
 | 
			
		||||
            default-instance-action:                stop-start
 | 
			
		||||
            alarm-restrictions:                     strict
 | 
			
		||||
            current-phase:                          apply
 | 
			
		||||
            current-phase-completion:               0%
 | 
			
		||||
            state:                                  applying
 | 
			
		||||
            inprogress:                             true
 | 
			
		||||
 | 
			
		||||
      .. code-block::
 | 
			
		||||
 | 
			
		||||
          ~(keystone_admin)]$ sw-manager sw-deploy-strategy show
 | 
			
		||||
          Strategy Software Deploy Strategy:
 | 
			
		||||
            strategy-uuid:                          a0277e08-93cc-4964-ba39-ebab367a547c
 | 
			
		||||
            release-id:                             <software-release-id>
 | 
			
		||||
            controller-apply-type:                  serial
 | 
			
		||||
            storage-apply-type:                     serial
 | 
			
		||||
            worker-apply-type:                      serial
 | 
			
		||||
            default-instance-action:                stop-start
 | 
			
		||||
            alarm-restrictions:                     strict
 | 
			
		||||
            current-phase:                          apply
 | 
			
		||||
            current-phase-completion:               7%
 | 
			
		||||
            state:                                  applying
 | 
			
		||||
            inprogress:                             true
 | 
			
		||||
 | 
			
		||||
      .. code-block::
 | 
			
		||||
 | 
			
		||||
          ~(keystone_admin)]$ sw-manager sw-deploy-strategy show --active
 | 
			
		||||
          Strategy Software Deploy Strategy:
 | 
			
		||||
            strategy-uuid:                          a0277e08-93cc-4964-ba39-ebab367a547c
 | 
			
		||||
            release-id:                             <software-release-id>
 | 
			
		||||
            controller-apply-type:                  serial
 | 
			
		||||
            storage-apply-type:                     serial
 | 
			
		||||
            worker-apply-type:                      serial
 | 
			
		||||
            default-instance-action:                stop-start
 | 
			
		||||
            alarm-restrictions:                     strict
 | 
			
		||||
            current-phase:                          apply
 | 
			
		||||
            current-phase-completion:               7%
 | 
			
		||||
            state:                                  applying
 | 
			
		||||
            apply-phase:
 | 
			
		||||
              total-stages:                         3
 | 
			
		||||
              current-stage:                        0
 | 
			
		||||
              stop-at-stage:                        1
 | 
			
		||||
              timeout:                              1322 seconds
 | 
			
		||||
              completion-percentage:                7%
 | 
			
		||||
              start-date-time:                      2024-06-11 14:40:23
 | 
			
		||||
              inprogress:                           true
 | 
			
		||||
              stages:
 | 
			
		||||
                  stage-id:                         0
 | 
			
		||||
                  stage-name:                       sw-upgrade-start
 | 
			
		||||
                  total-steps:                      3
 | 
			
		||||
                  current-step:                     1
 | 
			
		||||
                  timeout:                          1321 seconds
 | 
			
		||||
                  start-date-time:                  2024-06-11 14:40:23
 | 
			
		||||
                  inprogress:                       true
 | 
			
		||||
                  steps:
 | 
			
		||||
                      step-id:                      1
 | 
			
		||||
                      step-name:                    start-upgrade
 | 
			
		||||
                      timeout:                      1200 seconds
 | 
			
		||||
                      start-date-time:              2024-06-11 14:40:23
 | 
			
		||||
                      result:                       wait
 | 
			
		||||
                      reason:
 | 
			
		||||
 | 
			
		||||
#. While a software deployment orchestration strategy is being applied, it can be aborted.
 | 
			
		||||
 | 
			
		||||
   The current step will be allowed to complete and if necessary, an abort
 | 
			
		||||
   phase will be created and applied, which will attempt to unlock any hosts
 | 
			
		||||
   that were locked.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ sw-manager sw-deploy-strategy abort
 | 
			
		||||
       Strategy Software Deploy Strategy:
 | 
			
		||||
         strategy-uuid:                          63f48dfc-f833-479b-b597-d11f9219baf5
 | 
			
		||||
         release-id:                             <software-release-id>
 | 
			
		||||
         controller-apply-type:                  serial
 | 
			
		||||
         storage-apply-type:                     serial
 | 
			
		||||
         worker-apply-type:                      serial
 | 
			
		||||
         default-instance-action:                stop-start
 | 
			
		||||
         alarm-restrictions:                     strict
 | 
			
		||||
         current-phase:                          apply
 | 
			
		||||
         current-phase-completion:               7%
 | 
			
		||||
         state:                                  aborting
 | 
			
		||||
         inprogress:                             true
 | 
			
		||||
 | 
			
		||||
   Wait for the abort to complete.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ sw-manager sw-deploy-strategy show
 | 
			
		||||
       Strategy Software Deploy Strategy:
 | 
			
		||||
         strategy-uuid:                          63f48dfc-f833-479b-b597-d11f9219baf5
 | 
			
		||||
         release-id:                             <software-release-id>
 | 
			
		||||
         controller-apply-type:                  serial
 | 
			
		||||
         storage-apply-type:                     serial
 | 
			
		||||
         worker-apply-type:                      serial
 | 
			
		||||
         default-instance-action:                stop-start
 | 
			
		||||
         alarm-restrictions:                     strict
 | 
			
		||||
         current-phase:                          abort
 | 
			
		||||
         current-phase-completion:               100%
 | 
			
		||||
         state:                                  aborted
 | 
			
		||||
         apply-result:                           failed
 | 
			
		||||
         apply-reason:
 | 
			
		||||
         abort-result:                           success
 | 
			
		||||
         abort-reason:
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       To view detailed errors, run the following commands:
 | 
			
		||||
 | 
			
		||||
       .. code-block::
 | 
			
		||||
 | 
			
		||||
           [sysadmin@controller-0 ~(keystone_admin)]$ sw-manager sw-deploy-strategy show --error-details
 | 
			
		||||
 | 
			
		||||
       .. code-block::
 | 
			
		||||
 | 
			
		||||
           ~(keystone_admin)]$ sw-manager sw-deploy-strategy show
 | 
			
		||||
           Strategy Software Deploy Strategy:
 | 
			
		||||
           strategy-uuid: <>
 | 
			
		||||
           release-id: <software-release-id>
 | 
			
		||||
           controller-apply-type: serial
 | 
			
		||||
           storage-apply-type: serial
 | 
			
		||||
           worker-apply-type: serial
 | 
			
		||||
           default-instance-action: stop-start
 | 
			
		||||
           alarm-restrictions: strict
 | 
			
		||||
           current-phase: abort
 | 
			
		||||
           current-phase-completion: 100%
 | 
			
		||||
           state: aborted
 | 
			
		||||
           apply-result: failed
 | 
			
		||||
           apply-error-response:
 | 
			
		||||
           abort-result: success
 | 
			
		||||
           abort-reason:
 | 
			
		||||
           abort-error-response:
 | 
			
		||||
 | 
			
		||||
   .. note::
 | 
			
		||||
 | 
			
		||||
       After a software deployment strategy has been applied (or aborted), it
 | 
			
		||||
       must be deleted before another software deployment strategy can be
 | 
			
		||||
       created.
 | 
			
		||||
 | 
			
		||||
#. Otherwise, wait for all the steps of all stages of the software deployment
 | 
			
		||||
   orchestration strategy to complete.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ sw-manager sw-deploy-strategy show
 | 
			
		||||
       Strategy Software Deploy Strategy:
 | 
			
		||||
         strategy-uuid:                          6282f049-bb9e-46f0-9ca8-97bf626884e0
 | 
			
		||||
         release-id:                             <software-release-id>
 | 
			
		||||
         controller-apply-type:                  serial
 | 
			
		||||
         storage-apply-type:                     serial
 | 
			
		||||
         worker-apply-type:                      serial
 | 
			
		||||
         default-instance-action:                stop-start
 | 
			
		||||
         alarm-restrictions:                     strict
 | 
			
		||||
         current-phase:                          applied
 | 
			
		||||
         current-phase-completion:               100%
 | 
			
		||||
         state:                                  applied
 | 
			
		||||
         apply-result:                           success
 | 
			
		||||
         apply-reason:
 | 
			
		||||
 | 
			
		||||
   If a software deployment strategy apply fails, you must address the issue
 | 
			
		||||
   that caused the failure, then delete/re-create the strategy before
 | 
			
		||||
   attempting to apply it again.
 | 
			
		||||
 | 
			
		||||
   For additional details, run the :command:`sw-manager sw-deploy-strategy show --error-details` command.
 | 
			
		||||
 | 
			
		||||
#. Delete the completed software deployment strategy.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ sw-manager sw-deploy-strategy delete
 | 
			
		||||
       Strategy deleted
 | 
			
		||||
 | 
			
		||||
.. rubric:: |postreq|
 | 
			
		||||
 | 
			
		||||
After a successful software deployment orchestration,
 | 
			
		||||
 | 
			
		||||
- The Kubernetes Version Upgrade procedure can be executed, if desired, to
 | 
			
		||||
  upversion to a new Kubernetes versions available in the new software release.
 | 
			
		||||
 | 
			
		||||
- You should also validate that the system and hosted applications are healthy.
 | 
			
		||||
 | 
			
		||||
- In the case of a major release software deployment:
 | 
			
		||||
 | 
			
		||||
  - If you do not need to rollback the major release software deployment, then
 | 
			
		||||
    delete the software deployment that was used by the software deployment
 | 
			
		||||
    orchestration.
 | 
			
		||||
 | 
			
		||||
    .. code-block::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ software deploy delete
 | 
			
		||||
        Deployment has been deleted
 | 
			
		||||
 | 
			
		||||
    .. code-block::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ software deploy show
 | 
			
		||||
        No deploy in progress
 | 
			
		||||
 | 
			
		||||
  - Remove the old major release to reclaim disk space.
 | 
			
		||||
 | 
			
		||||
    .. code-block::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ software list
 | 
			
		||||
        +--------------------------+-------+-------------+
 | 
			
		||||
        | Release                  | RR    |   State     |
 | 
			
		||||
        +--------------------------+-------+-------------+
 | 
			
		||||
        | starlingx-10.0.0         | True  | unavailable |
 | 
			
		||||
        | <new-major-release-id>   | True  | deployed    |
 | 
			
		||||
        +--------------------------+-------+-------------+
 | 
			
		||||
 | 
			
		||||
    .. code-block::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ software delete starlingx-10.0.0
 | 
			
		||||
        starlingx-10.0.0 has been deleted.
 | 
			
		||||
 | 
			
		||||
    .. code-block::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ software list
 | 
			
		||||
        +--------------------------+-------+-------------+
 | 
			
		||||
        | Release                  | RR    |   State     |
 | 
			
		||||
        +--------------------------+-------+-------------+
 | 
			
		||||
        | <new-major-release-id>   | True  | deployed    |
 | 
			
		||||
        +--------------------------+-------+-------------+
 | 
			
		||||
@@ -0,0 +1,135 @@
 | 
			
		||||
.. WARNING: Add no lines of text between the label immediately following
 | 
			
		||||
.. and the title.
 | 
			
		||||
 | 
			
		||||
.. _orchestrated-removal-host-software-deployment-3f542895daf8:
 | 
			
		||||
 | 
			
		||||
=============================================
 | 
			
		||||
Orchestrated Removal Host Software Deployment
 | 
			
		||||
=============================================
 | 
			
		||||
 | 
			
		||||
A fully deployed patch release can be removed (or un-deployed) by using the
 | 
			
		||||
:ref:`orchestrated-deployment-host-software-deployment-d234754c7d20` procedure and deploying a
 | 
			
		||||
previous patch release or the major release.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    A fully deployed major release cannot be removed (or un-deployed).
 | 
			
		||||
 | 
			
		||||
For example, the following shows the current software releases deployed:
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ software list
 | 
			
		||||
     +--------------------------+-------+-----------+
 | 
			
		||||
     | Release                  | RR    |   State   |
 | 
			
		||||
     +--------------------------+-------+-----------+
 | 
			
		||||
     | starlingx-10.0.0         | True  | deployed  |
 | 
			
		||||
     | starlingx-10.0.1         | False | deployed  |
 | 
			
		||||
     | starlingx-10.0.2         | True  | deployed  |
 | 
			
		||||
     | starlingx-10.0.3         | False | deployed  |
 | 
			
		||||
     +--------------------------+-------+-----------+
 | 
			
		||||
 | 
			
		||||
To remove patch releases starlingx-10.0.3 and starlingx-10.0.2, follow the
 | 
			
		||||
:ref:`orchestrated-deployment-host-software-deployment-d234754c7d20` procedure,
 | 
			
		||||
and deploy (or go back to) the starlingx-10.0.1 software release in step :ref:`<1 <orchestrated-deployment-host-software-deployment-d234754c7d20-step>`.
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ sw-manager sw-deploy-strategy create [--controller-apply-type {serial,ignore}]
 | 
			
		||||
                                                                [--storage-apply-type {serial,parallel,ignore}]
 | 
			
		||||
                                                                [--worker-apply-type {serial,parallel,ignore}]
 | 
			
		||||
                                                                [--max-parallel-worker-hosts {2,3,4,5,6,7,8,9,10}]
 | 
			
		||||
                                                                [--instance-action {stop-start,migrate}]
 | 
			
		||||
                                                                [--alarm-restrictions {strict,relaxed}]
 | 
			
		||||
                                                                starlingx-10.0.1
 | 
			
		||||
 | 
			
		||||
    strategy-uuid:                          5435e049-7002-4403-acfb-7886f6da14af
 | 
			
		||||
    release-id:                             starlingx-10.0.1
 | 
			
		||||
    controller-apply-type:                  serial
 | 
			
		||||
    storage-apply-type:                     serial
 | 
			
		||||
    worker-apply-type:                      serial
 | 
			
		||||
    default-instance-action:                stop-start
 | 
			
		||||
    alarm-restrictions:                     strict
 | 
			
		||||
    current-phase:                          build
 | 
			
		||||
    current-phase-completion:               0%
 | 
			
		||||
    state:                                  building
 | 
			
		||||
    inprogress:                             true
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ sw-manager sw-deploy-strategy show
 | 
			
		||||
    Strategy Software Deploy Strategy:
 | 
			
		||||
      strategy-uuid:                          6282f049-bb9e-46f0-9ca8-97bf626884e0
 | 
			
		||||
      release-id:                             starlingx-10.0.1
 | 
			
		||||
      controller-apply-type:                  serial
 | 
			
		||||
      storage-apply-type:                     serial
 | 
			
		||||
      worker-apply-type:                      serial
 | 
			
		||||
      default-instance-action:                stop-start
 | 
			
		||||
      alarm-restrictions:                     strict
 | 
			
		||||
      current-phase:                          build
 | 
			
		||||
      current-phase-completion:               100%
 | 
			
		||||
      state:                                  ready-to-apply
 | 
			
		||||
      build-result:                           success
 | 
			
		||||
      build-reason:
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    If parallel apply for storage is used, it will be automatically replaced
 | 
			
		||||
    with the serial apply for ``--storage-apply-type``.
 | 
			
		||||
 | 
			
		||||
Apply the software orchestration deployment strategy.
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ sw-manager sw-deploy-strategy apply
 | 
			
		||||
    Strategy Software Deploy Strategy:
 | 
			
		||||
    strategy-uuid: 92e69661-2ef2-4d7d-baf2-272b8886d95a
 | 
			
		||||
    release-id: starlingx-10.0.1
 | 
			
		||||
    controller-apply-type: serial
 | 
			
		||||
    storage-apply-type: serial
 | 
			
		||||
    worker-apply-type: serial
 | 
			
		||||
    default-instance-action: stop-start
 | 
			
		||||
    alarm-restrictions: relaxed
 | 
			
		||||
    current-phase: apply
 | 
			
		||||
    current-phase-completion: 0%
 | 
			
		||||
    state: applying
 | 
			
		||||
    inprogress: true
 | 
			
		||||
 | 
			
		||||
On completion of the
 | 
			
		||||
:ref:`orchestrated-deployment-host-software-deployment-d234754c7d20` procedure,
 | 
			
		||||
run the following command:
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ software list
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
    | Release                  | RR    |   State   |
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
    | starlingx-10.0.0         | True  | deployed  |
 | 
			
		||||
    | starlingx-10.0.1         | False | deployed  |
 | 
			
		||||
    | starlingx-10.0.2         | True  | available |
 | 
			
		||||
    | starlingx-10.0.3         | False | available |
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
 | 
			
		||||
If the removed patches are no longer required on the system, you can delete them.
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ software delete starlingx-10.0.3
 | 
			
		||||
    starlingx-10.0.3 has been deleted.
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ software delete starlingx-10.0.2
 | 
			
		||||
    starlingx-10.0.2 has been deleted.
 | 
			
		||||
 | 
			
		||||
.. code-block::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ software list
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
    | Release                  | RR    |   State   |
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
    | starlingx-10.0.0         | True  | deployed  |
 | 
			
		||||
    | starlingx-10.0.1         | False | deployed  |
 | 
			
		||||
    +--------------------------+-------+-----------+
 | 
			
		||||
 | 
			
		||||
@@ -0,0 +1,255 @@
 | 
			
		||||
.. WARNING: Add no lines of text between the label immediately following
 | 
			
		||||
.. and the title.
 | 
			
		||||
 | 
			
		||||
.. _orchestrated-rollback-host-software-deployment-c6b12f13a8a1:
 | 
			
		||||
 | 
			
		||||
==============================================
 | 
			
		||||
Orchestrated Rollback Host Software Deployment
 | 
			
		||||
==============================================
 | 
			
		||||
 | 
			
		||||
For an orchestrated software deployment, the
 | 
			
		||||
:ref:`orchestrated-deployment-host-software-deployment-d234754c7d20` procedure
 | 
			
		||||
can be aborted and rolled back as long as the postrequisite :command:`software
 | 
			
		||||
deploy delete` has not been done either manually or via orchestrated upgrade.
 | 
			
		||||
After the postrequisite :command:`software deploy delete` step, an orchestrated
 | 
			
		||||
abort and rollback of the deployment is not possible.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    This section also covers the orchestrated abort and rollback of an updated
 | 
			
		||||
    release deployment. Deployment cannot be rolled back after the activation
 | 
			
		||||
    stage. Orchestrated rollback is currently supported only for |AIO-SX|.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |prereq|
 | 
			
		||||
 | 
			
		||||
You have done either of the following:
 | 
			
		||||
 | 
			
		||||
- Aborted an :ref:`orchestrated-deployment-host-software-deployment-d234754c7d20` procedure.
 | 
			
		||||
 | 
			
		||||
  .. code-block::
 | 
			
		||||
 | 
			
		||||
      ~(keystone_admin)]$ sw-manager sw-deploy-strategy abort
 | 
			
		||||
      Strategy Software Deploy Strategy:
 | 
			
		||||
        strategy-uuid:                          63f48dfc-f833-479b-b597-d11f9219baf5
 | 
			
		||||
        release-id:                             <software-release-id>
 | 
			
		||||
        controller-apply-type:                  serial
 | 
			
		||||
        storage-apply-type:                     serial
 | 
			
		||||
        worker-apply-type:                      serial
 | 
			
		||||
        default-instance-action:                stop-start
 | 
			
		||||
        alarm-restrictions:                     strict
 | 
			
		||||
        current-phase:                          apply
 | 
			
		||||
        current-phase-completion:               7%
 | 
			
		||||
        state:                                  aborting
 | 
			
		||||
        inprogress:                             true
 | 
			
		||||
 | 
			
		||||
  and waited for the orchestration to finish its current stage/step and then
 | 
			
		||||
  abort.
 | 
			
		||||
 | 
			
		||||
  .. code-block::
 | 
			
		||||
 | 
			
		||||
      ~(keystone_admin)]$ sw-manager sw-deploy-strategy show
 | 
			
		||||
      Strategy Software Deploy Strategy:
 | 
			
		||||
        strategy-uuid:                          63f48dfc-f833-479b-b597-d11f9219baf5
 | 
			
		||||
        release-id:                             <software-release-id>
 | 
			
		||||
        controller-apply-type:                  serial
 | 
			
		||||
        storage-apply-type:                     serial
 | 
			
		||||
        worker-apply-type:                      serial
 | 
			
		||||
        default-instance-action:                stop-start
 | 
			
		||||
        alarm-restrictions:                     strict
 | 
			
		||||
        current-phase:                          abort
 | 
			
		||||
        current-phase-completion:               100%
 | 
			
		||||
        state:                                  aborted
 | 
			
		||||
        apply-result:                           aborted
 | 
			
		||||
        apply-reason:
 | 
			
		||||
        abort-result:                           success
 | 
			
		||||
        abort-reason:
 | 
			
		||||
 | 
			
		||||
- Or completed an :ref:`orchestrated-deployment-host-software-deployment-d234754c7d20` procedure:
 | 
			
		||||
 | 
			
		||||
  .. code-block::
 | 
			
		||||
 | 
			
		||||
      ~(keystone_admin)]$ sw-manager sw-deploy-strategy show
 | 
			
		||||
      Strategy Software Deploy Strategy:
 | 
			
		||||
        strategy-uuid:                          6282f049-bb9e-46f0-9ca8-97bf626884e0
 | 
			
		||||
        release-id:                             <software-release-id>
 | 
			
		||||
        controller-apply-type:                  serial
 | 
			
		||||
        torage-apply-type:                     serial
 | 
			
		||||
        worker-apply-type:                      serial
 | 
			
		||||
        default-instance-action:                stop-start
 | 
			
		||||
        alarm-restrictions:                     strict
 | 
			
		||||
        current-phase:                          apply
 | 
			
		||||
        current-phase-completion:               100%
 | 
			
		||||
        state:                                  applied
 | 
			
		||||
        apply-result:                           success
 | 
			
		||||
        apply-reason:
 | 
			
		||||
 | 
			
		||||
But, you have not executed the postrequisite :command:`software deploy delete` step.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#. Delete any old software deployment strategy.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ sw-manager sw-deploy-strategy delete
 | 
			
		||||
       Strategy deleted
 | 
			
		||||
 | 
			
		||||
#. Create a software deployment rollback orchestration strategy with desired
 | 
			
		||||
   policies to abort and rollback the current software deployment.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ sw-manager sw-deploy-strategy create [--controller-apply-type {serial,ignore}]
 | 
			
		||||
                                                                 [--storage-apply-type {serial,parallel,ignore}]
 | 
			
		||||
                                                                 [--worker-apply-type {serial,parallel,ignore}]
 | 
			
		||||
                                                                 [--max-parallel-worker-hosts {2,3,4,5,6,7,8,9,10}]
 | 
			
		||||
                                                                 [--instance-action {stop-start,migrate}]
 | 
			
		||||
                                                                 [--alarm-restrictions {strict,relaxed}]
 | 
			
		||||
                                                                 --rollback
 | 
			
		||||
 | 
			
		||||
       strategy-uuid:                          5435e049-7002-4403-acfb-7886f6da14af
 | 
			
		||||
       release-id:                             <software-release-id>
 | 
			
		||||
       controller-apply-type:                  serial
 | 
			
		||||
       storage-apply-type:                     serial
 | 
			
		||||
       worker-apply-type:                      serial
 | 
			
		||||
       default-instance-action:                migrate
 | 
			
		||||
       alarm-restrictions:                     strict
 | 
			
		||||
       current-phase:                          build
 | 
			
		||||
       current-phase-completion:               0%
 | 
			
		||||
       state:                                  building
 | 
			
		||||
       inprogress:                             true
 | 
			
		||||
 | 
			
		||||
   where,
 | 
			
		||||
 | 
			
		||||
   ``--rollback``
 | 
			
		||||
       Specifies that this is a software deployment rollback orchestration
 | 
			
		||||
       strategy for the current software deployment.
 | 
			
		||||
 | 
			
		||||
   ``[--controller-apply-type {serial,ignore}]``
 | 
			
		||||
       (Optional) Specifies whether software should be deployed to the
 | 
			
		||||
       controller hosts in serial or ignored. The default is serial.
 | 
			
		||||
       ``ignore`` should only be used when re-creating and applying a strategy
 | 
			
		||||
       after an abort or failure.
 | 
			
		||||
 | 
			
		||||
   ``[--storage-apply-type {serial,parallel,ignore}]``
 | 
			
		||||
       (Optional) Specifies whether software should be deployed to the storage
 | 
			
		||||
       hosts in serial, in parallel, or ignored. The default is serial.
 | 
			
		||||
       Software is deployed to the storage hosts in parallel by software
 | 
			
		||||
       deploying a storage host from each storage redundancy group at the same
 | 
			
		||||
       time. ``ignore`` should only be used when recreating and applying a
 | 
			
		||||
       strategy after an abort or failure.
 | 
			
		||||
 | 
			
		||||
       .. note::
 | 
			
		||||
 | 
			
		||||
           If parallel apply for storage is used, it will be automatically
 | 
			
		||||
           replaced with the serial apply for ``--storage-apply-type``.
 | 
			
		||||
 | 
			
		||||
   ``[--worker-apply-type {serial,parallel,ignore}]``
 | 
			
		||||
       (Optional) Specifies whether software should be deployed to the worker
 | 
			
		||||
       hosts in serial, in parallel, or ignored. The default is serial. The
 | 
			
		||||
       number of worker hosts that are software deployed in parallel is
 | 
			
		||||
       specified by ``[--max-parallel-worker-hosts {2,3,4,5,6,7,8,9,10}]``.
 | 
			
		||||
       The default is 2. ``ignore`` should only be used when recreating and
 | 
			
		||||
       applying a strategy after an abort or failure.
 | 
			
		||||
 | 
			
		||||
   ``[--max-parallel-worker-hosts {2,3,4,5,6,7,8,9,10}]``
 | 
			
		||||
       Specifies the number of worker hosts that are software deployed in
 | 
			
		||||
       parallel specified by ``[--max-parallel-worker-hosts
 | 
			
		||||
       {2,3,4,5,6,7,8,9,10}]``. The default is 2.
 | 
			
		||||
 | 
			
		||||
   ``[--instance-action {stop-start,migrate}]``
 | 
			
		||||
       This option only applies to OpenStack |VM| hosted guests. It specifies
 | 
			
		||||
       the action done to hosted OpenStack |VMs| on a worker host (|AIO|
 | 
			
		||||
       controller) prior to deploying the new software to the host. The default
 | 
			
		||||
       is ``stop-start``.
 | 
			
		||||
 | 
			
		||||
       - ``stop-start``
 | 
			
		||||
         Before deploying the software release to the host, all hosted
 | 
			
		||||
         OpenStack |VMs| are stopped or shutdown.
 | 
			
		||||
 | 
			
		||||
         After deploying the software release to the host, all hosted
 | 
			
		||||
         OpenStack |VMs| are restarted.
 | 
			
		||||
 | 
			
		||||
       - ``migrate``
 | 
			
		||||
         Before deploying the software release to the host, all hosted
 | 
			
		||||
         OpenStack |VMs| are migrated to another host that is capable of hosting
 | 
			
		||||
         the hosted OpenStack |VM| and that is not part of the current stage.
 | 
			
		||||
 | 
			
		||||
         Hosts whose software is already updated are preferred over
 | 
			
		||||
         hosts whose software is not yet updated. Live migration is
 | 
			
		||||
         attempted first, if not available for the OpenStack |VM|, then cold
 | 
			
		||||
         migration is performed.
 | 
			
		||||
 | 
			
		||||
   ``[--alarm-restrictions {strict,relaxed}]``
 | 
			
		||||
       This option lets you determine how to handle alarm restrictions based on
 | 
			
		||||
       the management affecting statuses of any existing alarms, which takes
 | 
			
		||||
       into account the alarm type as well as the alarm's current severity.
 | 
			
		||||
 | 
			
		||||
       The default is strict.
 | 
			
		||||
 | 
			
		||||
       If set to relaxed, orchestration will be allowed to proceed if there are
 | 
			
		||||
       no management affecting alarms present.
 | 
			
		||||
 | 
			
		||||
       Performing management actions without specifically relaxing the alarm
 | 
			
		||||
       checks will still fail if there are any alarms present in the system
 | 
			
		||||
       (except for a small list of basic alarms for the orchestration actions
 | 
			
		||||
       such as an upgrade operation in progress alarm not impeding upgrade
 | 
			
		||||
       orchestration).
 | 
			
		||||
 | 
			
		||||
       You can use the CLI command :command:`fm alarm-list --mgmt_affecting` to
 | 
			
		||||
       view the alarms that are management affecting.
 | 
			
		||||
 | 
			
		||||
       - ``Strict``
 | 
			
		||||
 | 
			
		||||
         Maintains alarm restrictions.
 | 
			
		||||
 | 
			
		||||
       - ``Relaxed``
 | 
			
		||||
 | 
			
		||||
         Relaxes the usual alarm restrictions and allows the action to proceed
 | 
			
		||||
         if there are no alarms present in the system with a severity equal to
 | 
			
		||||
         or greater than its management affecting severity.
 | 
			
		||||
 | 
			
		||||
#. Apply the software deployment rollback orchestration:
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ sw-manager sw-deploy-strategy apply
 | 
			
		||||
       Strategy Software Deploy Strategy:
 | 
			
		||||
         strategy-uuid:                          52873771-fc1a-48cd-b322-ab921d34d01c
 | 
			
		||||
         release-id:                             <software-release-id>
 | 
			
		||||
         controller-apply-type:                  serial
 | 
			
		||||
         storage-apply-type:                     serial
 | 
			
		||||
         worker-apply-type:                      serial
 | 
			
		||||
         default-instance-action:                stop-start
 | 
			
		||||
         alarm-restrictions:                     strict
 | 
			
		||||
         current-phase:                          apply
 | 
			
		||||
         current-phase-completion:               0%
 | 
			
		||||
         state:                                  applying
 | 
			
		||||
         inprogress:                             true
 | 
			
		||||
 | 
			
		||||
#. Wait for all the steps of all stages of the software deployment rollback
 | 
			
		||||
   orchestration strategy to complete.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ sw-manager sw-deploy-strategy show
 | 
			
		||||
       Strategy Software Deploy Strategy:
 | 
			
		||||
         strategy-uuid:                          6282f049-bb9e-46f0-9ca8-97bf626884e0
 | 
			
		||||
         release-id:                             <software-release-id>
 | 
			
		||||
         controller-apply-type:                  serial
 | 
			
		||||
         storage-apply-type:                     serial
 | 
			
		||||
         worker-apply-type:                      serial
 | 
			
		||||
         default-instance-action:                stop-start
 | 
			
		||||
         alarm-restrictions:                     strict
 | 
			
		||||
         current-phase:                          apply
 | 
			
		||||
         current-phase-completion:               100%
 | 
			
		||||
         state:                                  done
 | 
			
		||||
         apply-result:                           success
 | 
			
		||||
         apply-reason:
 | 
			
		||||
 | 
			
		||||
#. Delete the completed software deployment rollback orchestration strategy.
 | 
			
		||||
 | 
			
		||||
   .. code-block::
 | 
			
		||||
 | 
			
		||||
       ~(keystone_admin)]$ sw-manager sw-deploy-strategy delete
 | 
			
		||||
       Strategy deleted.
 | 
			
		||||
@@ -1,139 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. bla1593031188931
 | 
			
		||||
.. _orchestration-upgrade-overview:
 | 
			
		||||
 | 
			
		||||
==============================
 | 
			
		||||
Upgrade Orchestration Overview
 | 
			
		||||
==============================
 | 
			
		||||
 | 
			
		||||
Upgrade Orchestration automates much of the upgrade procedure, leaving a few
 | 
			
		||||
manual steps for operator oversight.
 | 
			
		||||
 | 
			
		||||
.. contents:: |minitoc|
 | 
			
		||||
   :local:
 | 
			
		||||
   :depth: 1
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
    Upgrading of |prod-dc| is distinct from upgrading other |prod|
 | 
			
		||||
    configurations.
 | 
			
		||||
    
 | 
			
		||||
.. xbooklink    For information on updating |prod-dc|, see |distcloud-doc|:
 | 
			
		||||
    :ref:`Upgrade Management <upgrade-management-overview>`.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    The upgrade orchestration commands are prefixed with :command:`sw-manager`.
 | 
			
		||||
    To use upgrade orchestration commands, you need administrator privileges.
 | 
			
		||||
    You must log in to the active controller as user **sysadmin** and source the
 | 
			
		||||
    ``/etc/platform/openrc`` script to obtain administrator privileges. Do not use
 | 
			
		||||
    :command:`sudo`.
 | 
			
		||||
 | 
			
		||||
.. code-block:: none
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ sw-manager upgrade-strategy --help
 | 
			
		||||
    usage: sw-manager upgrade-strategy [-h]  ...
 | 
			
		||||
    
 | 
			
		||||
    optional arguments:
 | 
			
		||||
      -h, --help  show this help message and exit
 | 
			
		||||
    
 | 
			
		||||
    Software Upgrade Commands:
 | 
			
		||||
      
 | 
			
		||||
        create    Create a strategy
 | 
			
		||||
        delete    Delete a strategy
 | 
			
		||||
        apply     Apply a strategy
 | 
			
		||||
        abort     Abort a strategy
 | 
			
		||||
        show      Show a strategy
 | 
			
		||||
 | 
			
		||||
.. _orchestration-upgrade-overview-section-N10029-N10026-N10001:
 | 
			
		||||
 | 
			
		||||
----------------------------------
 | 
			
		||||
Upgrade Orchestration Requirements
 | 
			
		||||
----------------------------------
 | 
			
		||||
 | 
			
		||||
Upgrade orchestration can only be done on a system that meets the following
 | 
			
		||||
conditions:
 | 
			
		||||
 | 
			
		||||
.. _orchestration-upgrade-overview-ul-blp-gcx-ry:
 | 
			
		||||
 | 
			
		||||
-   The system is clear of alarms (with the exception of the alarm upgrade in
 | 
			
		||||
    progress).
 | 
			
		||||
 | 
			
		||||
-   All hosts must be unlocked, enabled, and available.
 | 
			
		||||
 | 
			
		||||
-   The system is fully redundant (two controller nodes available, at least
 | 
			
		||||
    one complete storage replication group available for systems with Ceph
 | 
			
		||||
    backend).
 | 
			
		||||
 | 
			
		||||
-   An upgrade has been started, and controller-1 has been upgraded and is
 | 
			
		||||
    active.
 | 
			
		||||
 | 
			
		||||
-   No orchestration strategy exists. Patch, upgrade, firmware, kubernetes,
 | 
			
		||||
    and kube rootca are all types of orchestration. An upgrade cannot be
 | 
			
		||||
    orchestrated while another orchestration is in progress.
 | 
			
		||||
 | 
			
		||||
-   Sufficient free capacity or unused worker resources must be available
 | 
			
		||||
    across the cluster. A rough calculation is: 
 | 
			
		||||
    
 | 
			
		||||
    ``Required spare capacity ( %) = (<Number-of-hosts-to-upgrade-in-parallel> / <total-number-of-hosts>) * 100``
 | 
			
		||||
 | 
			
		||||
.. include:: /_includes/manual-image-cleanup-note-b43d78f2ba4a.rest
 | 
			
		||||
 | 
			
		||||
.. _orchestration-upgrade-overview-section-N10081-N10026-N10001:
 | 
			
		||||
 | 
			
		||||
---------------------------------
 | 
			
		||||
The Upgrade Orchestration Process
 | 
			
		||||
---------------------------------
 | 
			
		||||
 | 
			
		||||
Upgrade orchestration can be initiated after the initial controller host has
 | 
			
		||||
been manual upgraded and returned to a stability state. Upgrade orchestration
 | 
			
		||||
automatically iterates through the remaining hosts, installing the new software
 | 
			
		||||
load on each one: first the other controller host, then the storage hosts, and
 | 
			
		||||
finally the worker hosts. During worker host upgrades, pods are automatically
 | 
			
		||||
moved to alternate worker hosts.
 | 
			
		||||
 | 
			
		||||
You first create an upgrade orchestration strategy, or plan, for the automated
 | 
			
		||||
upgrade procedure. This customizes the upgrade orchestration, using parameters
 | 
			
		||||
to specify:
 | 
			
		||||
 | 
			
		||||
.. _orchestration-upgrade-overview-ul-eyw-fyr-31b:
 | 
			
		||||
 | 
			
		||||
-   the host types to be upgraded
 | 
			
		||||
 | 
			
		||||
-   whether to upgrade hosts serially or in parallel
 | 
			
		||||
 | 
			
		||||
Based on these parameters, and the state of the hosts, upgrade orchestration
 | 
			
		||||
creates a number of stages for the overall upgrade strategy. Each stage
 | 
			
		||||
generally consists of moving pods, locking hosts, installing upgrades, and
 | 
			
		||||
unlocking hosts for a subset of the hosts on the system.
 | 
			
		||||
 | 
			
		||||
After creating the upgrade orchestration strategy, the you can either apply the
 | 
			
		||||
entire strategy automatically, or apply individual stages to control and monitor
 | 
			
		||||
their progress manually.
 | 
			
		||||
 | 
			
		||||
Update and upgrade orchestration are mutually exclusive; they perform
 | 
			
		||||
conflicting operations. Only a single strategy (sw-patch or sw-upgrade) is
 | 
			
		||||
allowed to exist at a time. If you need to update during an upgrade, you can
 | 
			
		||||
abort/delete the sw-upgrade strategy, and then create and apply a sw-patch
 | 
			
		||||
strategy before going back to the upgrade.
 | 
			
		||||
 | 
			
		||||
Some stages of the upgrade could take a significant amount of time (hours).
 | 
			
		||||
For example, after upgrading a storage host, re-syncing the OSD data could take
 | 
			
		||||
30 minutes per TB (assuming 500MB/s sync rate, which is about half of a 10G
 | 
			
		||||
infrastructure link).
 | 
			
		||||
 | 
			
		||||
.. _orchestration-upgrade-overview-section-N10101-N10026-N10001:
 | 
			
		||||
 | 
			
		||||
------------------------------
 | 
			
		||||
Upgrade Orchestration Workflow
 | 
			
		||||
------------------------------
 | 
			
		||||
 | 
			
		||||
The Upgrade Orchestration procedure has several major parts:
 | 
			
		||||
 | 
			
		||||
.. _orchestration-upgrade-overview-ul-r1k-wzj-wy:
 | 
			
		||||
 | 
			
		||||
-   Manually upgrade controller-1.
 | 
			
		||||
 | 
			
		||||
-   Orchestrate the automatic upgrade of the remaining controller, all the
 | 
			
		||||
    storage nodes, and all the worker nodes.
 | 
			
		||||
 | 
			
		||||
-   Manually complete the upgrade.
 | 
			
		||||
@@ -1,29 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. yim1593277634652
 | 
			
		||||
.. _overview-of-upgrade-abort-procedure:
 | 
			
		||||
 | 
			
		||||
===================================
 | 
			
		||||
Overview of Upgrade Abort Procedure
 | 
			
		||||
===================================
 | 
			
		||||
 | 
			
		||||
You can abort an upgrade procedure if necessary.
 | 
			
		||||
 | 
			
		||||
There are two cases for aborting an upgrade:
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
.. _overview-of-upgrade-abort-procedure-ul-q5f-vmz-bx:
 | 
			
		||||
 | 
			
		||||
-   Before controller-0 has been upgraded (that is, only controller-1 has been
 | 
			
		||||
    upgraded): In this case the upgrade can be aborted and the system will
 | 
			
		||||
    remain in service during the abort.
 | 
			
		||||
 | 
			
		||||
-   After controller-0 has been upgraded (that is, both controllers have been
 | 
			
		||||
    upgraded): In this case the upgrade can only be aborted with a complete
 | 
			
		||||
    outage and a re-install of all hosts. This would only be done as a last
 | 
			
		||||
    resort, if there was absolutely no other way to recover the system.
 | 
			
		||||
 | 
			
		||||
-   :ref:`Rolling Back a Software Upgrade Before the Second Controller Upgrade
 | 
			
		||||
    <rolling-back-a-software-upgrade-before-the-second-controller-upgrade>`  
 | 
			
		||||
 | 
			
		||||
-   :ref:`Rolling Back a Software Upgrade After the Second Controller Upgrade
 | 
			
		||||
    <rolling-back-a-software-upgrade-after-the-second-controller-upgrade>`  
 | 
			
		||||
@@ -1,340 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. kad1593196868935
 | 
			
		||||
.. _performing-an-orchestrated-upgrade-using-the-cli:
 | 
			
		||||
 | 
			
		||||
=============================================
 | 
			
		||||
Perform an Orchestrated Upgrade Using the CLI
 | 
			
		||||
=============================================
 | 
			
		||||
 | 
			
		||||
The upgrade orchestration CLI is :command:`sw-manager`.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |context|
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
   To use upgrade orchestration commands, you need administrator privileges.
 | 
			
		||||
   You must log in to the active controller as user **sysadmin** and source the
 | 
			
		||||
   ``/etc/platform/openrc`` script to obtain administrator privileges. Do not use
 | 
			
		||||
   :command:`sudo`.
 | 
			
		||||
 | 
			
		||||
The upgrade strategy options are shown in the following output:
 | 
			
		||||
 | 
			
		||||
.. code-block:: none
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ sw-manager upgrade-strategy --help
 | 
			
		||||
    usage: sw-manager upgrade-strategy [-h]  ...
 | 
			
		||||
 | 
			
		||||
    optional arguments:
 | 
			
		||||
      -h, --help  show this help message and exit
 | 
			
		||||
 | 
			
		||||
    Software Upgrade Commands:
 | 
			
		||||
 | 
			
		||||
        create    Create a strategy
 | 
			
		||||
        delete    Delete a strategy
 | 
			
		||||
        apply     Apply a strategy
 | 
			
		||||
        abort     Abort a strategy
 | 
			
		||||
        show      Show a strategy
 | 
			
		||||
 | 
			
		||||
You can perform a partially orchestrated upgrade using the |CLI|. Upgrade
 | 
			
		||||
orchestration of other |prod| nodes can be initiated after the initial
 | 
			
		||||
controller host has been manually upgraded and returned to a stability state.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
    Management-affecting alarms cannot be ignored at the indicated severity
 | 
			
		||||
    level or higher by using relaxed alarm rules during an orchestrated upgrade
 | 
			
		||||
    operation. For a list of management-affecting alarms, see |fault-doc|:
 | 
			
		||||
    :ref:`alarm-messages-overview-19c242d3d151`. To display
 | 
			
		||||
    management-affecting active alarms, use the following command:
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ fm alarm-list --mgmt_affecting
 | 
			
		||||
 | 
			
		||||
    During an orchestrated upgrade, the following alarms are ignored even when
 | 
			
		||||
    strict restrictions are selected:
 | 
			
		||||
 | 
			
		||||
    -   900.005, Upgrade in progress
 | 
			
		||||
 | 
			
		||||
    -   900.201, Software upgrade auto apply in progress
 | 
			
		||||
 | 
			
		||||
.. _performing-an-orchestrated-upgrade-using-the-cli-ul-qhy-q1p-v1b:
 | 
			
		||||
 | 
			
		||||
.. rubric:: |prereq|
 | 
			
		||||
 | 
			
		||||
See :ref:`Upgrading All-in-One Duplex / Standard
 | 
			
		||||
<upgrading-all-in-one-duplex-or-standard>`, and perform Steps 1-8, to manually
 | 
			
		||||
upgrade the initial controller node before doing the upgrade orchestration
 | 
			
		||||
described below to upgrade the remaining nodes of the |prod|.
 | 
			
		||||
 | 
			
		||||
- The subclouds must use the Redfish platform management service if it is an
 | 
			
		||||
  All-in-one Simplex subcloud.
 | 
			
		||||
 | 
			
		||||
- Duplex (AIODX/Standard) upgrades are supported, and they do not require
 | 
			
		||||
  remote install via Redfish.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
.. _performing-an-orchestrated-upgrade-using-the-cli-steps-e45-kh5-sy:
 | 
			
		||||
 | 
			
		||||
#.  Create a update strategy using the :command:`sw-manager upgrade-strategy create`
 | 
			
		||||
    command.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sw-manager upgrade-strategy create
 | 
			
		||||
 | 
			
		||||
        strategy-uuid:                          5435e049-7002-4403-acfb-7886f6da14af
 | 
			
		||||
        controller-apply-type:                  serial
 | 
			
		||||
        storage-apply-type:                     serial
 | 
			
		||||
        worker-apply-type:                      serial
 | 
			
		||||
        default-instance-action:                migrate
 | 
			
		||||
        alarm-restrictions:                     strict
 | 
			
		||||
        current-phase:                          build
 | 
			
		||||
        current-phase-completion:               0%
 | 
			
		||||
        state:                                  building
 | 
			
		||||
        inprogress:                             true
 | 
			
		||||
 | 
			
		||||
    Create an upgrade strategy, specifying the following parameters:
 | 
			
		||||
 | 
			
		||||
    -   storage-apply-type:
 | 
			
		||||
 | 
			
		||||
        -   ``serial`` (default): storage hosts will be upgraded one at a time
 | 
			
		||||
 | 
			
		||||
        -   ``parallel``: storage hosts will be upgraded in parallel, ensuring that
 | 
			
		||||
            only one storage node in each replication group is patched at a
 | 
			
		||||
            time.
 | 
			
		||||
 | 
			
		||||
        -   ``ignore``: storage hosts will not be upgraded
 | 
			
		||||
 | 
			
		||||
    -   worker-apply-type:
 | 
			
		||||
 | 
			
		||||
        ``serial`` (default)
 | 
			
		||||
           Worker hosts will be upgraded one at a time.
 | 
			
		||||
 | 
			
		||||
        ``ignore``
 | 
			
		||||
           Worker hosts will not be upgraded.
 | 
			
		||||
 | 
			
		||||
    -   Alarm Restrictions
 | 
			
		||||
 | 
			
		||||
        This option lets you determine how to handle alarm restrictions based
 | 
			
		||||
        on the management affecting statuses of any existing alarms, which
 | 
			
		||||
        takes into account the alarm type as well as the alarm's current
 | 
			
		||||
        severity. If set to relaxed, orchestration will be allowed to proceed
 | 
			
		||||
        if there are no management affecting alarms present.
 | 
			
		||||
 | 
			
		||||
        Performing management actions without specifically relaxing the alarm
 | 
			
		||||
        checks will still fail if there are any alarms present in the system
 | 
			
		||||
        (except for a small list of basic alarms for the orchestration actions
 | 
			
		||||
        such as an upgrade operation in progress alarm not impeding upgrade
 | 
			
		||||
        orchestration).
 | 
			
		||||
 | 
			
		||||
        You can use the CLI command :command:`fm alarm-list --mgmt_affecting`
 | 
			
		||||
        to view the alarms that are management affecting.
 | 
			
		||||
 | 
			
		||||
        **Strict**
 | 
			
		||||
           Maintains alarm restrictions.
 | 
			
		||||
 | 
			
		||||
        **Relaxed**
 | 
			
		||||
           Relaxes the usual alarm restrictions and allows the action to
 | 
			
		||||
           proceed if there are no alarms present in the system with a severity
 | 
			
		||||
           equal to or greater than its management affecting severity.
 | 
			
		||||
 | 
			
		||||
    The upgrade strategy consists of one or more stages, which consist of one
 | 
			
		||||
    or more hosts to be upgraded at the same time. Each stage will be split
 | 
			
		||||
    into steps (for example, query-alarms, lock-hosts, upgrade-hosts).
 | 
			
		||||
    Following are some notes about stages:
 | 
			
		||||
 | 
			
		||||
    -   Controller-0 is upgraded first, followed by storage hosts and then
 | 
			
		||||
        worker hosts.
 | 
			
		||||
 | 
			
		||||
    -   Worker hosts with no instances are upgraded before worker hosts with
 | 
			
		||||
        application pods.
 | 
			
		||||
 | 
			
		||||
    -   Pods will be relocated off each worker host before it is upgraded.
 | 
			
		||||
 | 
			
		||||
    -   The final step in each stage is one of:
 | 
			
		||||
 | 
			
		||||
        **system-stabilize**
 | 
			
		||||
            This waits for a period of time (up to several minutes) and
 | 
			
		||||
            ensures that the system is free of alarms. This ensures that we do
 | 
			
		||||
            not continue to upgrade more hosts if the upgrade has caused an
 | 
			
		||||
            issue resulting in an alarm.
 | 
			
		||||
 | 
			
		||||
        **wait-data-sync**
 | 
			
		||||
           This waits for a period of time (up to many hours) and ensures
 | 
			
		||||
           that data synchronization has completed after the upgrade of a
 | 
			
		||||
           controller or storage node.
 | 
			
		||||
 | 
			
		||||
    Examine the upgrade strategy. Pay careful attention to:
 | 
			
		||||
 | 
			
		||||
    -   The sets of hosts that will be upgraded together in each stage.
 | 
			
		||||
 | 
			
		||||
    -   The sets of pods that will be impacted in each stage.
 | 
			
		||||
 | 
			
		||||
        .. note::
 | 
			
		||||
            It is likely that as each stage is applied, pods will be relocated
 | 
			
		||||
            to worker hosts that have not yet been upgraded. That means that
 | 
			
		||||
            later stages will be relocating more pods than those originally
 | 
			
		||||
            listed in the upgrade strategy. The upgrade strategy is NOT
 | 
			
		||||
            updated, but any additional pods on each worker host will be
 | 
			
		||||
            relocated before it is upgraded.
 | 
			
		||||
 | 
			
		||||
#.  Run :command:`sw-manager upgrade-strategy show` command, to display the
 | 
			
		||||
    current-phase-completion percentage progress indicator in various
 | 
			
		||||
    increments. Once at 100%, it returns:
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sw-manager upgrade-strategy show
 | 
			
		||||
 | 
			
		||||
        strategy-uuid:                          5435e049-7002-4403-acfb-7886f6da14af
 | 
			
		||||
        controller-apply-type:                  serial
 | 
			
		||||
        storage-apply-type:                     serial
 | 
			
		||||
        worker-apply-type:                      serial
 | 
			
		||||
        default-instance-action:                migrate
 | 
			
		||||
        alarm-restrictions:                     strict
 | 
			
		||||
        current-phase:                          build
 | 
			
		||||
        current-phase-completion:               100%
 | 
			
		||||
        state:                                  ready-to-apply
 | 
			
		||||
        build-result:                           success
 | 
			
		||||
        build-reason:
 | 
			
		||||
 | 
			
		||||
#.  Apply the upgrade strategy. You can optionally apply a single stage at a
 | 
			
		||||
    time.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sw-manager upgrade-strategy apply
 | 
			
		||||
 | 
			
		||||
        strategy-uuid:                          5435e049-7002-4403-acfb-7886f6da14af
 | 
			
		||||
        controller-apply-type:                  serial
 | 
			
		||||
        storage-apply-type:                     serial
 | 
			
		||||
        worker-apply-type:                      serial
 | 
			
		||||
        default-instance-action:                migrate
 | 
			
		||||
        alarm-restrictions:                     strict
 | 
			
		||||
        current-phase:                          apply
 | 
			
		||||
        current-phase-completion:               0%
 | 
			
		||||
        state:                                  applying
 | 
			
		||||
        inprogress:                             true
 | 
			
		||||
 | 
			
		||||
    While an upgrade strategy is being applied, it can be aborted. This results
 | 
			
		||||
    in:
 | 
			
		||||
 | 
			
		||||
    -   The current step will be allowed to complete.
 | 
			
		||||
 | 
			
		||||
    -   If necessary an abort phase will be created and applied, which will
 | 
			
		||||
        attempt to unlock any hosts that were locked.
 | 
			
		||||
 | 
			
		||||
    After an upgrade strategy has been applied (or aborted) it must be
 | 
			
		||||
    deleted before another upgrade strategy can be created. If an
 | 
			
		||||
    upgrade strategy application fails, you must address the issue that caused
 | 
			
		||||
    the failure, then delete/re-create the strategy before attempting to apply
 | 
			
		||||
    it again.
 | 
			
		||||
 | 
			
		||||
#.  Run :command:`sw-manager upgrade-strategy show` command, to display the
 | 
			
		||||
    current-phase-completion displaying the field goes from 0% to 100% in
 | 
			
		||||
    various increments. Once at 100%, it returns:
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sw-manager upgrade-strategy show
 | 
			
		||||
 | 
			
		||||
        strategy-uuid:                          b91d8332-9ece-4578-b4dd-e9cf87b73f18
 | 
			
		||||
        controller-apply-type:                  serial
 | 
			
		||||
        storage-apply-type:                     serial
 | 
			
		||||
        worker-apply-type:                      serial
 | 
			
		||||
        default-instance-action:                migrate
 | 
			
		||||
        alarm-restrictions:                     strict
 | 
			
		||||
        current-phase:                          apply
 | 
			
		||||
        current-phase-completion:               100%
 | 
			
		||||
        state:                                  applied
 | 
			
		||||
        apply-result:                           success
 | 
			
		||||
        apply-reason:
 | 
			
		||||
 | 
			
		||||
#.  Activate the upgrade.
 | 
			
		||||
 | 
			
		||||
    During the running of the :command:`upgrade-activate` command, new
 | 
			
		||||
    configurations are applied to the controller. 250.001 (**hostname
 | 
			
		||||
    Configuration is out-of-date**) alarms are raised and are cleared as the
 | 
			
		||||
    configuration is applied. The upgrade state goes from **activating** to
 | 
			
		||||
    **activation-complete** once this is done.
 | 
			
		||||
 | 
			
		||||
    .. only:: partner
 | 
			
		||||
 | 
			
		||||
        .. include:: /_includes/performing-an-orchestrated-upgrade-using-the-cli.rest
 | 
			
		||||
           :start-after: deploymentmanager-begin
 | 
			
		||||
           :end-before: deploymentmanager-end
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-activate
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | Property     | Value                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | uuid         | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
 | 
			
		||||
        | state        | activating                           |
 | 
			
		||||
        | from_release | nn.nn                                |
 | 
			
		||||
        | to_release   | nn.nn                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
    The following states apply when this command is executed.
 | 
			
		||||
 | 
			
		||||
    **activation-requested**
 | 
			
		||||
        State entered when :command:`system upgrade-activate` is executed.
 | 
			
		||||
 | 
			
		||||
    **activating**
 | 
			
		||||
        State entered when we have started activating the upgrade by applying
 | 
			
		||||
        new configurations to the controller and compute hosts.
 | 
			
		||||
 | 
			
		||||
    **activation-complete**
 | 
			
		||||
        State entered when new configurations have been applied to all
 | 
			
		||||
        controller and compute hosts.
 | 
			
		||||
 | 
			
		||||
#.  Check the status of the upgrade again to see it has reached
 | 
			
		||||
    **activation-complete**
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-show
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | Property     | Value                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | uuid         | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
 | 
			
		||||
        | state        | activation-complete                  |
 | 
			
		||||
        | from_release | nn.nn                                |
 | 
			
		||||
        | to_release   | nn.nn                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
#.  Complete the upgrade.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-complete
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | Property     | Value                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | uuid         | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
 | 
			
		||||
        | state        | completing                           |
 | 
			
		||||
        | from_release | nn.nn                                |
 | 
			
		||||
        | to_release   | nn.nn                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
#.  Delete the imported load.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system load-list
 | 
			
		||||
        +----+----------+------------------+
 | 
			
		||||
        | id | state    | software_version |
 | 
			
		||||
        +----+----------+------------------+
 | 
			
		||||
        | 1  | imported | nn.nn            |
 | 
			
		||||
        | 2  | active   | nn.nn            |
 | 
			
		||||
        +----+----------+------------------+
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system load-delete 1
 | 
			
		||||
        Deleted load: load 1
 | 
			
		||||
 | 
			
		||||
.. only:: partner
 | 
			
		||||
 | 
			
		||||
    .. include:: /_includes/performing-an-orchestrated-upgrade-using-the-cli.rest
 | 
			
		||||
        :start-after: Orchupgradecli-begin
 | 
			
		||||
        :end-before: Orchupgradecli-end
 | 
			
		||||
@@ -1,184 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. sab1593196680415
 | 
			
		||||
.. _performing-an-orchestrated-upgrade:
 | 
			
		||||
 | 
			
		||||
===============================
 | 
			
		||||
Perform an Orchestrated Upgrade
 | 
			
		||||
===============================
 | 
			
		||||
 | 
			
		||||
You can perform a partially orchestrated Upgrade of a |prod| system using the
 | 
			
		||||
CLI and Horizon Web interface. Upgrade and stability of the initial controller
 | 
			
		||||
node must be done manually before using upgrade orchestration to orchestrate the
 | 
			
		||||
remaining nodes of the |prod|.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |context|
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
    Management-affecting alarms cannot be ignored at the indicated severity
 | 
			
		||||
    level or higher by using relaxed alarm rules during an orchestrated upgrade
 | 
			
		||||
    operation. For a list of management-affecting alarms, see |fault-doc|:
 | 
			
		||||
    :ref:`alarm-messages-overview-19c242d3d151`. To display
 | 
			
		||||
    management-affecting active alarms, use the following command:
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ fm alarm-list --mgmt_affecting
 | 
			
		||||
 | 
			
		||||
    During an orchestrated upgrade, the following alarms are ignored even when
 | 
			
		||||
    strict restrictions are selected:
 | 
			
		||||
 | 
			
		||||
    -   750.006, Generic alarm for any platform-managed applications as they are auto-applied
 | 
			
		||||
 | 
			
		||||
    -   900.005, Upgrade in progress
 | 
			
		||||
 | 
			
		||||
    -   900.201, Software upgrade auto apply in progress
 | 
			
		||||
 | 
			
		||||
.. _performing-an-orchestrated-upgrade-ul-qhy-q1p-v1b:
 | 
			
		||||
 | 
			
		||||
.. rubric:: |prereq|
 | 
			
		||||
 | 
			
		||||
See :ref:`Upgrading All-in-One Duplex / Standard
 | 
			
		||||
<upgrading-all-in-one-duplex-or-standard>`, and perform Steps 1-8, to manually
 | 
			
		||||
upgrade the initial controller node before doing the upgrade orchestration
 | 
			
		||||
described below to upgrade the remaining nodes of the |prod| system.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
.. _performing-an-orchestrated-upgrade-steps-e45-kh5-sy:
 | 
			
		||||
 | 
			
		||||
#.  Select **Platform** \> **Software Management**, then select the **Upgrade
 | 
			
		||||
    Orchestration** tab.
 | 
			
		||||
 | 
			
		||||
#.  Click the **Create Strategy** button.
 | 
			
		||||
 | 
			
		||||
    The **Create Strategy** dialog appears.
 | 
			
		||||
 | 
			
		||||
#.  Create an upgrade strategy by specifying settings for the parameters in the
 | 
			
		||||
    **Create Strategy** dialog box.
 | 
			
		||||
 | 
			
		||||
    Create an upgrade strategy, specifying the following parameters:
 | 
			
		||||
 | 
			
		||||
    -   storage-apply-type:
 | 
			
		||||
 | 
			
		||||
        ``serial`` (default)
 | 
			
		||||
           Storage hosts will be upgraded one at a time.
 | 
			
		||||
 | 
			
		||||
        ``parallel``
 | 
			
		||||
           Storage hosts will be upgraded in parallel, ensuring that only one
 | 
			
		||||
           storage node in each replication group is upgraded at a time.
 | 
			
		||||
 | 
			
		||||
        ``ignore``
 | 
			
		||||
           Storage hosts will not be upgraded.
 | 
			
		||||
 | 
			
		||||
    -   worker-apply-type:
 | 
			
		||||
 | 
			
		||||
        ``serial`` (default):
 | 
			
		||||
           Worker hosts will be upgraded one at a time.
 | 
			
		||||
 | 
			
		||||
        ``parallel``
 | 
			
		||||
           Worker hosts will be upgraded in parallel, ensuring that:
 | 
			
		||||
 | 
			
		||||
           -   At most max-parallel-worker-hosts (see below) worker hosts
 | 
			
		||||
               will be upgraded at the same time.
 | 
			
		||||
 | 
			
		||||
           -   At most half of the hosts in a host aggregate will be upgraded
 | 
			
		||||
               at the same time.
 | 
			
		||||
 | 
			
		||||
           -   Worker hosts with no application pods are upgraded before
 | 
			
		||||
               worker hosts with application pods.
 | 
			
		||||
 | 
			
		||||
        ``ignore``
 | 
			
		||||
           Worker hosts will not be upgraded.
 | 
			
		||||
 | 
			
		||||
        ``max-parallel-worker-hosts``
 | 
			
		||||
           Specify the maximum worker hosts to upgrade in parallel (minimum:
 | 
			
		||||
           2, maximum: 10).
 | 
			
		||||
 | 
			
		||||
           .. note::
 | 
			
		||||
               For a maximum worker hosts condition in a Standard configuration
 | 
			
		||||
               (50), the value shall be at the maximum 2, which represents the
 | 
			
		||||
               minimum value.
 | 
			
		||||
 | 
			
		||||
        ``alarm-restrictions``
 | 
			
		||||
            This option lets you specify how upgrade orchestration behaves when
 | 
			
		||||
            alarms are present.
 | 
			
		||||
 | 
			
		||||
            You can use the CLI command :command:`fm alarm-list
 | 
			
		||||
            --mgmt_affecting` to view the alarms that are management affecting.
 | 
			
		||||
 | 
			
		||||
            ``Strict``
 | 
			
		||||
               The default strict option will result in upgrade orchestration
 | 
			
		||||
               failing if there are any alarms present in the system (except
 | 
			
		||||
               for a small list of alarms).
 | 
			
		||||
 | 
			
		||||
            ``Relaxed``
 | 
			
		||||
               This option allows orchestration to proceed if alarms are
 | 
			
		||||
               present, as long as none of these alarms are management
 | 
			
		||||
               affecting.
 | 
			
		||||
 | 
			
		||||
#.  Click **Create Strategy** to save the upgrade orchestration strategy.
 | 
			
		||||
 | 
			
		||||
    The upgrade strategy consists of one or more stages, which consist of one
 | 
			
		||||
    or more hosts to be upgraded at the same time. Each stage will be split
 | 
			
		||||
    into steps (for example, query-alarms, lock-hosts, upgrade-hosts).
 | 
			
		||||
    Following are some notes about stages:
 | 
			
		||||
 | 
			
		||||
    -   Controller-0 is upgraded first, followed by storage hosts and then
 | 
			
		||||
        worker hosts.
 | 
			
		||||
 | 
			
		||||
    -   Worker hosts with no application pods are upgraded before worker hosts
 | 
			
		||||
        with application pods.
 | 
			
		||||
 | 
			
		||||
    -   Pods will be moved off each worker host before it is upgraded.
 | 
			
		||||
 | 
			
		||||
    -   The final step in each stage is one of:
 | 
			
		||||
 | 
			
		||||
        **system-stabilize**
 | 
			
		||||
           This waits for a period of time (up to several minutes) and
 | 
			
		||||
           ensures that the system is free of alarms. This ensures that we do
 | 
			
		||||
           not continue to upgrade more hosts if the upgrade has caused an
 | 
			
		||||
           issue resulting in an alarm.
 | 
			
		||||
 | 
			
		||||
        **wait-data-sync**
 | 
			
		||||
           This waits for a period of time (up to many hours) and ensures
 | 
			
		||||
           that data synchronization has completed after the upgrade of a
 | 
			
		||||
           controller or storage node.
 | 
			
		||||
 | 
			
		||||
    Examine the upgrade strategy. Pay careful attention to:
 | 
			
		||||
 | 
			
		||||
    -   The sets of hosts that will be upgraded together in each stage.
 | 
			
		||||
 | 
			
		||||
    -   The sets of pods that will be impacted in each stage.
 | 
			
		||||
 | 
			
		||||
        .. note::
 | 
			
		||||
            It is likely that as each stage is applied, application pods will
 | 
			
		||||
            be relocated to worker hosts that have not yet been upgraded. That
 | 
			
		||||
            means that later stages will be migrating more pods than those
 | 
			
		||||
            originally listed in the upgrade strategy. The upgrade strategy is
 | 
			
		||||
            NOT updated, but any additional pods on each worker host will be
 | 
			
		||||
            relocated before it is upgraded.
 | 
			
		||||
 | 
			
		||||
#.  Apply the upgrade strategy. You can optionally apply a single stage at a
 | 
			
		||||
    time.
 | 
			
		||||
 | 
			
		||||
    While an upgrade strategy is being applied, it can be aborted. This results
 | 
			
		||||
    in:
 | 
			
		||||
 | 
			
		||||
    -   The current step will be allowed to complete.
 | 
			
		||||
 | 
			
		||||
    -   If necessary an abort phase will be created and applied, which will
 | 
			
		||||
        attempt to unlock any hosts that were locked.
 | 
			
		||||
 | 
			
		||||
    After an upgrade strategy has been applied (or aborted) it must be
 | 
			
		||||
    deleted before another upgrade strategy can be created. If an
 | 
			
		||||
    upgrade strategy application fails, you must address the issue that caused
 | 
			
		||||
    the failure, then delete/re-create the strategy before attempting to apply
 | 
			
		||||
    it again.
 | 
			
		||||
 | 
			
		||||
For more information, see: :ref:`Perform an Orchestrated Upgrade Using the CLI <performing-an-orchestrated-upgrade-using-the-cli>`
 | 
			
		||||
 | 
			
		||||
.. only:: partner
 | 
			
		||||
 | 
			
		||||
    .. include:: /_includes/performing-an-orchestrated-upgrade.rest
 | 
			
		||||
       :start-after: Orchupgrade-begin
 | 
			
		||||
       :end-before: Orchupgrade-end
 | 
			
		||||
@@ -1,82 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. fek1552920702618
 | 
			
		||||
.. _populating-the-storage-area:
 | 
			
		||||
 | 
			
		||||
=========================
 | 
			
		||||
Populate the Storage Area
 | 
			
		||||
=========================
 | 
			
		||||
 | 
			
		||||
Software updates (patches) have to be uploaded to the |prod| storage area
 | 
			
		||||
before they can be applied.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#.  Log in as **sysadmin** to the active controller.
 | 
			
		||||
 | 
			
		||||
#.  Upload the update file to the storage area.
 | 
			
		||||
 | 
			
		||||
    .. parsed-literal::
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch upload /home/sysadmin/patches/|pn|-CONTROLLER_<nn.nn>_PATCH_0001.patch
 | 
			
		||||
        Cloud_Platform__CONTROLLER_<nn.nn>_PATCH_0001 is now available
 | 
			
		||||
 | 
			
		||||
    where <nn.nn> in the update file name is the |prod| release number.
 | 
			
		||||
 | 
			
		||||
    This example uploads a single update to the storage area. You can specify
 | 
			
		||||
    multiple update files on the same command separating their names with
 | 
			
		||||
    spaces.
 | 
			
		||||
 | 
			
		||||
    Alternatively, you can upload all update files stored in a directory using
 | 
			
		||||
    a single command, as illustrated in the following example:
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch upload-dir /home/sysadmin/patches
 | 
			
		||||
 | 
			
		||||
    The update is now available in the storage area, but has not been applied
 | 
			
		||||
    to the update repository or installed to the nodes in the cluster.
 | 
			
		||||
 | 
			
		||||
#.  Verify the status of the update.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ sudo sw-patch query
 | 
			
		||||
 | 
			
		||||
    The update state displays *Available*, indicating that it is included in the
 | 
			
		||||
    storage area. Further details about the updates can be retrieved as
 | 
			
		||||
    follows:
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
       $ sudo sw-patch show <patch_id>
 | 
			
		||||
 
 | 
			
		||||
    The :command:`sudo sw-patch query` command returns a list of patch IDs.
 | 
			
		||||
    The :command:`sudo sw-patch show` command provides further detail about
 | 
			
		||||
    the specified <patch_id>.
 | 
			
		||||
 | 
			
		||||
#.  Delete the update files from the root drive.
 | 
			
		||||
 | 
			
		||||
    After the updates are uploaded to the storage area, the original files are
 | 
			
		||||
    no longer required. You must delete them to ensure there is enough disk
 | 
			
		||||
    space to complete the installation.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ rm /home/sysadmin/patches/*
 | 
			
		||||
 | 
			
		||||
    .. caution::
 | 
			
		||||
        If the original files are not deleted before the updates are applied,
 | 
			
		||||
        the installation may fail due to a full disk.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |postreq|
 | 
			
		||||
 | 
			
		||||
When an update in the *Available* state is no longer required, you can delete
 | 
			
		||||
it using the following command:
 | 
			
		||||
 | 
			
		||||
.. parsed-literal::
 | 
			
		||||
 | 
			
		||||
    $ sudo sw-patch delete |pn|-|pvr|-PATCH_0001
 | 
			
		||||
 | 
			
		||||
The update to delete from the storage area is identified by the update
 | 
			
		||||
\(patch) ID reported by the :command:`sw-patch query` command. You can provide
 | 
			
		||||
multiple patch IDs to the delete command, separating their names by spaces.
 | 
			
		||||
@@ -1,95 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. ngk1552920570137
 | 
			
		||||
.. _reclaiming-disk-space:
 | 
			
		||||
 | 
			
		||||
==================
 | 
			
		||||
Reclaim Disk Space
 | 
			
		||||
==================
 | 
			
		||||
 | 
			
		||||
You can free up and reclaim disk space taken by previous updates once a newer
 | 
			
		||||
version of an update has been committed to the system.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#.  Run the :command:`query-dependencies` command to show a list of updates
 | 
			
		||||
    that are required by the specified update (patch), including itself.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        sw-patch query-dependences [ --recursive ] <patch-id>
 | 
			
		||||
 | 
			
		||||
    The :command:`query-dependencies` command will show a list of updates that
 | 
			
		||||
    are required by the specified update (including itself). The
 | 
			
		||||
    ``--recursive`` option will crawl through those dependencies to return a
 | 
			
		||||
    list of all the updates in the specified update's dependency tree. This
 | 
			
		||||
    query is used by the :command:`commit` command in calculating the set of
 | 
			
		||||
    updates to be committed. For example,
 | 
			
		||||
 | 
			
		||||
    .. parsed-literal::
 | 
			
		||||
 | 
			
		||||
        controller-0:/home/sysadmin# sw-patch query-dependencies |pn|-|pvr|-PATCH_0004
 | 
			
		||||
        |pn|-|pvr|-PATCH_0002
 | 
			
		||||
        |pn|-|pvr|-PATCH_0003
 | 
			
		||||
        |pn|-|pvr|-PATCH_0004
 | 
			
		||||
 | 
			
		||||
        controller-0:/home/sysadmin# sw-patch query-dependencies |pn|-|pvr|-PATCH_0004 --recursive
 | 
			
		||||
        |pn|-|pvr|-PATCH_0001
 | 
			
		||||
        |pn|-|pvr|-PATCH_0002
 | 
			
		||||
        |pn|-|pvr|-PATCH_0003
 | 
			
		||||
        |pn|-|pvr|-PATCH_0004
 | 
			
		||||
 | 
			
		||||
#.  Run the :command:`sw-patch commit` command.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        sw-patch commit [ --dry-run ] [ --all ] [ --release ] [ <patch-id> … ]
 | 
			
		||||
 | 
			
		||||
    The :command:`sw-patch commit` command allows you to specify a set of
 | 
			
		||||
    updates to be committed. The commit set is calculated by querying the
 | 
			
		||||
    dependencies of each specified update.
 | 
			
		||||
 | 
			
		||||
    The ``--all`` option, without the ``--release`` option, commits all updates
 | 
			
		||||
    of the currently running release. When two releases are on the system use
 | 
			
		||||
    the ``--release`` option to specify a particular release's updates if
 | 
			
		||||
    committing all updates for the non-running release. The ``--dry-run``
 | 
			
		||||
    option shows the list of updates to be committed and how much disk space
 | 
			
		||||
    will be freed up. This information is also shown without the ``--dry-run``
 | 
			
		||||
    option, before prompting to continue with the operation. An update can only
 | 
			
		||||
    be committed once it has been fully applied to the system, and cannot be
 | 
			
		||||
    removed after.
 | 
			
		||||
 | 
			
		||||
    Following are examples that show the command usage.
 | 
			
		||||
 | 
			
		||||
    The following command lists the status of all updates that are in an
 | 
			
		||||
    *Applied* state.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        controller-0:/home/sysadmin# sw-patch query
 | 
			
		||||
 | 
			
		||||
    The following command commits the updates.
 | 
			
		||||
 | 
			
		||||
    .. parsed-literal::
 | 
			
		||||
 | 
			
		||||
        controller-0:/home/sysadmin# sw-patch commit |pvr|-PATCH_0001 |pvr|-PATCH_0002
 | 
			
		||||
        The following patches will be committed:
 | 
			
		||||
            |pvr|-PATCH_0001
 | 
			
		||||
            |pvr|-PATCH_0002
 | 
			
		||||
 | 
			
		||||
        This commit operation would free 2186.31 MiB
 | 
			
		||||
 | 
			
		||||
        WARNING: Committing a patch is an irreversible operation. Committed patches
 | 
			
		||||
                 cannot be removed.
 | 
			
		||||
 | 
			
		||||
        Would you like to continue? [y/N]: y
 | 
			
		||||
        The patches have been committed.
 | 
			
		||||
 | 
			
		||||
    The following command shows the updates now in the *Committed* state.
 | 
			
		||||
 | 
			
		||||
    .. parsed-literal::
 | 
			
		||||
 | 
			
		||||
        controller-0:/home/sysadmin# sw-patch query
 | 
			
		||||
        Patch ID             RR  Release   Patch State
 | 
			
		||||
        ================   ===== ========  =========
 | 
			
		||||
        |pvr|-PATCH_0001     N    |pvr|    Committed
 | 
			
		||||
        |pvr|-PATCH_0002     Y    |pvr|    Committed
 | 
			
		||||
@@ -1,117 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. scm1552920603294
 | 
			
		||||
.. _removing-reboot-required-software-updates:
 | 
			
		||||
 | 
			
		||||
=======================================
 | 
			
		||||
Remove Reboot-Required Software Updates
 | 
			
		||||
=======================================
 | 
			
		||||
 | 
			
		||||
Updates in the *Applied* or *Partial-Apply* states can be removed if necessary,
 | 
			
		||||
for example, when they trigger undesired or unplanned effects on the cluster.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |context|
 | 
			
		||||
 | 
			
		||||
Rolling back updates is conceptually identical to installing updates. A
 | 
			
		||||
roll-back operation can be commanded for an update in either the *Applied* or
 | 
			
		||||
the *Partial-Apply* states. As the update is removed, it goes through the
 | 
			
		||||
following state transitions:
 | 
			
		||||
 | 
			
		||||
**Applied or Partial-Apply to Partial-Remove**
 | 
			
		||||
    An update in the *Partial-Remove* state indicates that it has been removed
 | 
			
		||||
    from zero or more, but not from all, the applicable hosts.
 | 
			
		||||
 | 
			
		||||
    Use the command :command:`sw-patch remove` to trigger this transition.
 | 
			
		||||
 | 
			
		||||
**Partial-Remove to Available**
 | 
			
		||||
    Use the command :command:`sudo sw-patch host-install-async <hostname>`
 | 
			
		||||
    repeatedly targeting each one of the applicable hosts in the cluster. The
 | 
			
		||||
    transition to the *Available* state is complete when the update is removed
 | 
			
		||||
    from all target hosts. The update remains in the update storage area as if
 | 
			
		||||
    it had just been uploaded.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        The command :command:`sudo sw-patch host-install-async <hostname>` both
 | 
			
		||||
        installs and removes updates as necessary.
 | 
			
		||||
 | 
			
		||||
The following example describes removing an update that applies only to the
 | 
			
		||||
controllers. Update removal can be done using the Horizon Web interface as
 | 
			
		||||
discussed in :ref:`Install Reboot-Required Software Updates Using Horizon
 | 
			
		||||
<installing-reboot-required-software-updates-using-horizon>`.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#.  Log in as Keystone user **admin** to the active controller.
 | 
			
		||||
 | 
			
		||||
#.  Verify the state of the update.
 | 
			
		||||
 | 
			
		||||
    .. parsed-literal::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sudo sw-patch query
 | 
			
		||||
        Patch ID                         Patch State
 | 
			
		||||
        =========================        ===========
 | 
			
		||||
        |pn|-|pvr|-PATCH_0001         Applied
 | 
			
		||||
 | 
			
		||||
    In this example the update is listed in the *Applied* state, but it could
 | 
			
		||||
    also be in the *Partial-Apply* state.
 | 
			
		||||
 | 
			
		||||
#.  Remove the update.
 | 
			
		||||
 | 
			
		||||
    .. parsed-literal::
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sudo sw-patch remove |pn|-|pvr|-PATCH_0001
 | 
			
		||||
        |pn|-|pvr|-PATCH_0001 has been removed from the repo
 | 
			
		||||
 | 
			
		||||
    The update is now in the *Partial-Remove* state, ready to be removed from
 | 
			
		||||
    the impacted hosts where it was currently installed.
 | 
			
		||||
 | 
			
		||||
#.  Query the updating status of all hosts in the cluster.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ sudo sw-patch query-hosts
 | 
			
		||||
 | 
			
		||||
          Hostname      IP Address     Patch Current  Reboot Required  Release  State
 | 
			
		||||
        ============  ===============  =============  ===============  =======  =====
 | 
			
		||||
        worker-0      192.168.204.179       Yes             No          nn.nn   idle
 | 
			
		||||
        worker-1      192.168.204.173       Yes             No          nn.nn   idle
 | 
			
		||||
        controller-0  192.168.204.3         No              No          nn.nn   idle
 | 
			
		||||
        controller-1  192.168.204.4         No              No          nn.nn   idle
 | 
			
		||||
        storage-0     192.168.204.213       Yes             No          nn.nn   idle
 | 
			
		||||
        storage-1     192.168.204.181       Yes             No          nn.nn   idle
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
    In this example, the controllers have updates ready to be removed, and
 | 
			
		||||
    therefore must be rebooted.
 | 
			
		||||
 | 
			
		||||
#.  Remove all pending-for-removal updates from controller-0.
 | 
			
		||||
 | 
			
		||||
    #.  Swact controller services away from controller-0.
 | 
			
		||||
 | 
			
		||||
    #.  Lock controller-0.
 | 
			
		||||
 | 
			
		||||
    #.  Run the updating (patching) sequence.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ sudo sw-patch host-install-async controller-0
 | 
			
		||||
 | 
			
		||||
    #.  Unlock controller-0.
 | 
			
		||||
 | 
			
		||||
#.  Remove all pending-for-removal updates from controller-1.
 | 
			
		||||
 | 
			
		||||
    #.  Swact controller services away from controller-1.
 | 
			
		||||
 | 
			
		||||
    #.  Lock controller-1.
 | 
			
		||||
 | 
			
		||||
    #.  Run the updating sequence.
 | 
			
		||||
 | 
			
		||||
    #.  Unlock controller-1.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ sudo sw-patch host-install-async controller-1
 | 
			
		||||
 | 
			
		||||
.. rubric:: |result|
 | 
			
		||||
 | 
			
		||||
The cluster is up to date now. All updates have been removed, and the update
 | 
			
		||||
|pn|-|pvr|-PATCH_0001 can be deleted from the storage area if necessary.
 | 
			
		||||
@@ -1,160 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. eiu1593277809293
 | 
			
		||||
.. _rolling-back-a-software-upgrade-after-the-second-controller-upgrade:
 | 
			
		||||
 | 
			
		||||
================================================================
 | 
			
		||||
Roll Back a Software Upgrade After the Second Controller Upgrade
 | 
			
		||||
================================================================
 | 
			
		||||
 | 
			
		||||
After the second controller is upgraded, you can still roll back a software
 | 
			
		||||
upgrade, however, the rollback will impact the hosting of applications.
 | 
			
		||||
 | 
			
		||||
The upgrade abort procedure can only be applied before the
 | 
			
		||||
:command:`upgrade-complete` command is issued. Once this command is issued
 | 
			
		||||
the upgrade cannot be aborted. If you must revert to the previous release,
 | 
			
		||||
then restore the system using the backup data taken prior to the upgrade.
 | 
			
		||||
 | 
			
		||||
In some scenarios additional actions will be required to complete the upgrade
 | 
			
		||||
abort. It may be necessary to restore the system from a backup.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#.  Run the :command:`upgrade-abort` command to abort the upgrade (running from
 | 
			
		||||
    controller-1).
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-abort
 | 
			
		||||
 | 
			
		||||
    Once this is done there is no going back; the upgrade must be completely
 | 
			
		||||
    aborted.
 | 
			
		||||
 | 
			
		||||
    The following state applies when you run this command.
 | 
			
		||||
 | 
			
		||||
    -   aborting-reinstall:
 | 
			
		||||
 | 
			
		||||
        -   State entered when :command:`system upgrade-abort` is executed
 | 
			
		||||
            after upgrading controller-0.
 | 
			
		||||
 | 
			
		||||
        -   Remain in this state until the abort is completed.
 | 
			
		||||
 | 
			
		||||
#.  Lock controller-0.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-lock controller-0
 | 
			
		||||
 | 
			
		||||
#.  Lock all storage and worker nodes that don't have ceph-mon configured
 | 
			
		||||
    (ceph-mon usually on worker-0 or storage-0). Execute the
 | 
			
		||||
    :command:`system ceph-mon-list` command to determine which hosts are running
 | 
			
		||||
    ceph-mon.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system ceph-mon-list
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
 | 
			
		||||
        Skip this step if doing this procedure on a |prod| Duplex
 | 
			
		||||
        system.
 | 
			
		||||
 | 
			
		||||
#.  Use wipedisk on all worker and storage nodes, except on storage-0
 | 
			
		||||
    or on the worker node that has ceph-mon configured (worker-0 usually).
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        Skip this step if doing this procedure on a |prod| Duplex system.
 | 
			
		||||
 | 
			
		||||
    #.  Execute :command:`wipedisk` from the shell on each storage or worker
 | 
			
		||||
        host.
 | 
			
		||||
 | 
			
		||||
    #.  Power down each host.
 | 
			
		||||
 | 
			
		||||
#.  Power off all storage and worker nodes except the node with ceph-mon.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        Skip this step if doing this procedure on a |prod| Duplex system.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-lock <hostID>
 | 
			
		||||
 | 
			
		||||
#.  Downgrade controller-0.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-downgrade controller-0
 | 
			
		||||
 | 
			
		||||
    The host is re-installed with the previous release load.
 | 
			
		||||
 | 
			
		||||
#.  Unlock controller-0.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-unlock controller-0
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        Wait for controller-0 to become unlocked-enabled. Wait for the
 | 
			
		||||
        |DRBD| sync 400.001 Services-related alarm to be raised and then cleared.
 | 
			
		||||
 | 
			
		||||
#.  Swact to controller-0.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-swact controller-1
 | 
			
		||||
 | 
			
		||||
    Swacting back to controller-0 will switch back to using the previous
 | 
			
		||||
    release databases, which were frozen at the time of the swact to
 | 
			
		||||
    controller-1. This is essentially the same result as a system restore.
 | 
			
		||||
 | 
			
		||||
#.  Lock controller-1.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-lock controller-1
 | 
			
		||||
 | 
			
		||||
    The host is re-installed with the previous release load.
 | 
			
		||||
 | 
			
		||||
#.  Downgrade controller-1.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-downgrade controller-1
 | 
			
		||||
 | 
			
		||||
#.  Unlock controller-1.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-unlock controller-1
 | 
			
		||||
 | 
			
		||||
#.  Run wipedisk on the worker node that was online (or the storage-0 node) and
 | 
			
		||||
    power off the host.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        Skip this step if doing this procedure on a |prod| Duplex system.
 | 
			
		||||
 | 
			
		||||
#.  Power up and unlock storage, then worker hosts one at a time.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        Skip this step if doing this procedure on a |prod| Duplex system.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-unlock <hostID>
 | 
			
		||||
 | 
			
		||||
    The hosts are re-installed with the previous release load. As each worker
 | 
			
		||||
    host goes online, application pods will be automatically recovered by the
 | 
			
		||||
    system.
 | 
			
		||||
 | 
			
		||||
#.  Complete the upgrade.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-abort-complete
 | 
			
		||||
 | 
			
		||||
    This cleans up the upgrade release, configuration, databases, and so forth.
 | 
			
		||||
 | 
			
		||||
#.  Delete the upgrade release load.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system load-delete
 | 
			
		||||
@@ -1,78 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. wyr1593277734184
 | 
			
		||||
.. _rolling-back-a-software-upgrade-before-the-second-controller-upgrade:
 | 
			
		||||
 | 
			
		||||
=================================================================
 | 
			
		||||
Roll Back a Software Upgrade Before the Second Controller Upgrade
 | 
			
		||||
=================================================================
 | 
			
		||||
 | 
			
		||||
After the first controller is upgraded, you can still perform an in-service
 | 
			
		||||
abort of an upgrade before the second Controller (controller-0 in the examples
 | 
			
		||||
of this procedure) has been upgraded. The :command:`system upgrade-abort`
 | 
			
		||||
command can be run from the node that is updated with the latest release and
 | 
			
		||||
has upgraded successfully.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#.  Abort the upgrade with the :command:`upgrade-abort` command.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-abort
 | 
			
		||||
 | 
			
		||||
    The upgrade state is set to aborting. Once this is executed, there is no
 | 
			
		||||
    canceling; the upgrade must be completely aborted.
 | 
			
		||||
 | 
			
		||||
    The following states apply when you execute this command.
 | 
			
		||||
 | 
			
		||||
    -   aborting:
 | 
			
		||||
 | 
			
		||||
        -   State entered when :command:`system upgrade-abort` is executed
 | 
			
		||||
            before upgrading controller-0.
 | 
			
		||||
 | 
			
		||||
        -   Remain in this state until the abort is completed.
 | 
			
		||||
 | 
			
		||||
#.  Make controller-0 active.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-swact controller-1
 | 
			
		||||
 | 
			
		||||
    If controller-1 was active with the new upgrade release, swacting back to
 | 
			
		||||
    controller-0 will switch back to using the previous release databases,
 | 
			
		||||
    which were frozen at the time of the swact to controller-1. Any changes to
 | 
			
		||||
    the system that were made while controller-1 was active will be lost.
 | 
			
		||||
 | 
			
		||||
#.  Lock and downgrade controller-1.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-lock controller-1
 | 
			
		||||
        ~(keystone_admin)]$ system host-downgrade controller-1
 | 
			
		||||
 | 
			
		||||
    The host is re-installed with the previous release load.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        The downgrade process will take a minimum of 20 to 30 minutes to
 | 
			
		||||
        complete.
 | 
			
		||||
 | 
			
		||||
        You can view the downgrade progress on controller-1 using the
 | 
			
		||||
        serial console.
 | 
			
		||||
 | 
			
		||||
#.  Unlock controller-1.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-unlock controller-1
 | 
			
		||||
 | 
			
		||||
#.  Complete the upgrade.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-complete
 | 
			
		||||
 | 
			
		||||
#.  Delete the newer upgrade release that has been aborted.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system load-delete <loadID>
 | 
			
		||||
@@ -1,18 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. qbz1552920585263
 | 
			
		||||
.. _software-update-space-reclamation:
 | 
			
		||||
 | 
			
		||||
=================================
 | 
			
		||||
Software Update Space Reclamation
 | 
			
		||||
=================================
 | 
			
		||||
 | 
			
		||||
|prod-long| provides functionality for reclaiming disk space used by older
 | 
			
		||||
versions of software updates once newer versions have been committed.
 | 
			
		||||
 | 
			
		||||
The :command:`sw-patch commit` command allows you to “commit” a set of software
 | 
			
		||||
updates, which effectively locks down those updates and makes them unremovable.
 | 
			
		||||
In doing so, |prod-long| is able to free up the disk space in patch storage and
 | 
			
		||||
the software repo.
 | 
			
		||||
 | 
			
		||||
.. caution::
 | 
			
		||||
    This action is irreversible.
 | 
			
		||||
@@ -27,9 +27,6 @@ following items:
 | 
			
		||||
 | 
			
		||||
Software updates can be installed manually or by the Update Orchestrator, which
 | 
			
		||||
automates a rolling install of an update across all of the |prod-long| hosts.
 | 
			
		||||
For more information on manual updates, see :ref:`Manage Software Updates
 | 
			
		||||
<managing-software-updates>`. For more information on upgrade orchestration,
 | 
			
		||||
see :ref:`Orchestrated Software Update <update-orchestration-overview>`.
 | 
			
		||||
 | 
			
		||||
.. warning::
 | 
			
		||||
    Do NOT use the |updates-doc| guide for |prod-dc| orchestrated
 | 
			
		||||
@@ -42,8 +39,10 @@ see :ref:`Orchestrated Software Update <update-orchestration-overview>`.
 | 
			
		||||
 | 
			
		||||
|prod| handles multiple updates being applied and removed at once. Software
 | 
			
		||||
updates can modify and update any area of |prod| software, including the kernel
 | 
			
		||||
itself. For information on populating, installing and removing software
 | 
			
		||||
updates, see :ref:`Manage Software Updates <managing-software-updates>`.
 | 
			
		||||
itself.
 | 
			
		||||
 | 
			
		||||
.. For information on populating, installing and removing software
 | 
			
		||||
.. updates, see :ref:`Manage Software Updates <managing-software-updates>`.
 | 
			
		||||
 | 
			
		||||
There are two different kinds of Software updates that you can use to update
 | 
			
		||||
the |prod| software:
 | 
			
		||||
@@ -59,8 +58,7 @@ the |prod| software:
 | 
			
		||||
    which automates a rolling install of an update across all of the
 | 
			
		||||
    |prod-long| hosts.
 | 
			
		||||
 | 
			
		||||
    For information on populating, installing and removing software updates,
 | 
			
		||||
    see :ref:`Manage Software Updates <managing-software-updates>`.
 | 
			
		||||
    .. For information on populating, installing and removing software updates, see :ref:`Manage Software Updates <managing-software-updates>`.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        A 10 GB internal management network is required for reboot-required
 | 
			
		||||
 
 | 
			
		||||
@@ -17,11 +17,11 @@ Software Upgrades
 | 
			
		||||
hosts are upgraded one at time while continuing to provide its hosting services
 | 
			
		||||
to its hosted applications. An upgrade can be performed manually or using
 | 
			
		||||
Upgrade Orchestration, which automates much of the upgrade procedure, leaving a
 | 
			
		||||
few manual steps to prevent operator oversight. For more information on manual
 | 
			
		||||
upgrades, see :ref:`Manual Platform Components Upgrade
 | 
			
		||||
<manual-upgrade-overview>`. For more information on upgrade orchestration, see
 | 
			
		||||
:ref:`Orchestrated Platform Component Upgrade
 | 
			
		||||
<orchestration-upgrade-overview>`.
 | 
			
		||||
few manual steps to prevent operator oversight.
 | 
			
		||||
 | 
			
		||||
.. For more information on manual upgrades, see :ref:`Manual Platform Components Upgrade <manual-upgrade-overview>`.
 | 
			
		||||
 | 
			
		||||
.. For more information on upgrade orchestration, see :ref:`Orchestrated Platform Component Upgrade <orchestration-upgrade-overview>`.
 | 
			
		||||
 | 
			
		||||
.. warning::
 | 
			
		||||
    Do NOT use information in the |updates-doc| guide for |prod-dc|
 | 
			
		||||
@@ -59,9 +59,9 @@ running in a 'compatibility' mode where all inter-node messages are using
 | 
			
		||||
message formats from the old release of software. Prior to upgrading the second
 | 
			
		||||
controller, you reach a "point-of-no-return for an in-service abort" of the
 | 
			
		||||
upgrades process. The second controller is loaded with the new release of
 | 
			
		||||
software and becomes the new Standby controller. For more information on manual
 | 
			
		||||
upgrades, see :ref:`Manual Platform Components Upgrade
 | 
			
		||||
<manual-upgrade-overview>` .
 | 
			
		||||
software and becomes the new Standby controller.
 | 
			
		||||
 | 
			
		||||
.. For more information on manual upgrades, see :ref:`Manual Platform Components Upgrade <manual-upgrade-overview>` .
 | 
			
		||||
 | 
			
		||||
If present, storage nodes are locked, upgraded and unlocked one at a time in
 | 
			
		||||
order to respect the redundancy model of |prod| storage nodes. Storage nodes
 | 
			
		||||
@@ -107,13 +107,13 @@ abort:
 | 
			
		||||
 | 
			
		||||
-   Before controller-0 has been upgraded (that is, only controller-1 has been
 | 
			
		||||
    upgraded): In this case the upgrade can be aborted and the system will
 | 
			
		||||
    remain in service during the abort, see, :ref:`Rolling Back a Software
 | 
			
		||||
    Upgrade Before the Second Controller Upgrade
 | 
			
		||||
    <rolling-back-a-software-upgrade-before-the-second-controller-upgrade>`.
 | 
			
		||||
    remain in service during the abort.
 | 
			
		||||
 | 
			
		||||
    .. See, :ref:`Rolling Back a Software Upgrade Before the Second Controller Upgrade <rolling-back-a-software-upgrade-before-the-second-controller-upgrade>`.
 | 
			
		||||
 | 
			
		||||
-   After controller-0 has been upgraded (that is, both controllers have been
 | 
			
		||||
    upgraded): In this case the upgrade can only be aborted with a complete
 | 
			
		||||
    outage and a reinstall of all hosts. This would only be done as a last
 | 
			
		||||
    resort, if there was absolutely no other way to recover the system, see,
 | 
			
		||||
    :ref:`Rolling Back a Software Upgrade After the Second Controller Upgrade
 | 
			
		||||
    <rolling-back-a-software-upgrade-after-the-second-controller-upgrade>`.
 | 
			
		||||
    resort, if there was absolutely no other way to recover the system.
 | 
			
		||||
 | 
			
		||||
    .. See, :ref:`Rolling Back a Software Upgrade After the Second Controller Upgrade <rolling-back-a-software-upgrade-after-the-second-controller-upgrade>`.
 | 
			
		||||
 
 | 
			
		||||
@@ -1,69 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. agv1552920520258
 | 
			
		||||
.. _update-orchestration-cli:
 | 
			
		||||
 | 
			
		||||
========================
 | 
			
		||||
Update Orchestration CLI
 | 
			
		||||
========================
 | 
			
		||||
 | 
			
		||||
The update orchestration CLI is :command:`sw-manager`. Use this to create your
 | 
			
		||||
update strategy.
 | 
			
		||||
 | 
			
		||||
The commands and options map directly to the parameter descriptions in the web
 | 
			
		||||
interface dialog, described in :ref:`Configuring Update Orchestration
 | 
			
		||||
<configuring-update-orchestration>`.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
    To use update orchestration commands, you need administrator privileges.
 | 
			
		||||
    You must log in to the active controller as user **sysadmin** and source
 | 
			
		||||
    the ``/etc/platform/openrc`` script to obtain administrator privileges. Do not
 | 
			
		||||
    use :command:`sudo`.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
    Management-affecting alarms cannot be ignored at the indicated severity
 | 
			
		||||
    level or higher by using relaxed alarm rules during an orchestrated update
 | 
			
		||||
    operation. For a list of management-affecting alarms, see |fault-doc|:
 | 
			
		||||
    :ref:`Alarm Messages <100-series-alarm-messages-starlingx>`. To display
 | 
			
		||||
    management-affecting active alarms, use the following command:
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)$ fm alarm-list --mgmt_affecting
 | 
			
		||||
 | 
			
		||||
    During an orchestrated update operation, the following alarms are ignored
 | 
			
		||||
    even when strict restrictions are selected:
 | 
			
		||||
 | 
			
		||||
    -   200.001, Maintenance host lock alarm
 | 
			
		||||
 | 
			
		||||
    -   900.001, Patch in progress
 | 
			
		||||
 | 
			
		||||
    -   900.005, Upgrade in progress
 | 
			
		||||
 | 
			
		||||
    -   900.101, Software patch auto apply in progress
 | 
			
		||||
 | 
			
		||||
.. _update-orchestration-cli-ul-qhy-q1p-v1b:
 | 
			
		||||
 | 
			
		||||
Help is available for the overall command and also for each sub-command. For
 | 
			
		||||
example:
 | 
			
		||||
 | 
			
		||||
.. code-block:: none
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$  sw-manager patch-strategy --help
 | 
			
		||||
    usage: sw-manager patch-strategy [-h]  ...
 | 
			
		||||
    
 | 
			
		||||
    optional arguments:
 | 
			
		||||
      -h, --help  show this help message and exit
 | 
			
		||||
 | 
			
		||||
Update orchestration commands include:
 | 
			
		||||
 | 
			
		||||
.. _update-orchestration-cli-ul-cvv-gdd-nx:
 | 
			
		||||
 | 
			
		||||
-   :command:`create` - Create a strategy
 | 
			
		||||
 | 
			
		||||
-   :command:`delete` - Delete a strategy
 | 
			
		||||
 | 
			
		||||
-   :command:`apply` - Apply a strategy
 | 
			
		||||
 | 
			
		||||
-   :command:`abort` - Abort a strategy
 | 
			
		||||
 | 
			
		||||
-   :command:`show` - Show a strategy
 | 
			
		||||
@@ -1,95 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. kzb1552920557323
 | 
			
		||||
.. _update-orchestration-overview:
 | 
			
		||||
 | 
			
		||||
=============================
 | 
			
		||||
Update Orchestration Overview
 | 
			
		||||
=============================
 | 
			
		||||
 | 
			
		||||
Update orchestration allows an entire |prod| system to be updated with a single
 | 
			
		||||
operation.
 | 
			
		||||
 | 
			
		||||
.. contents:: |minitoc|
 | 
			
		||||
   :local:
 | 
			
		||||
   :depth: 1
 | 
			
		||||
 | 
			
		||||
You can configure and run update orchestration using the CLI, the Horizon Web
 | 
			
		||||
interface, or the ``stx-nfv`` REST API.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
    Updating of |prod-dc| is distinct from updating of other |prod|
 | 
			
		||||
    configurations. 
 | 
			
		||||
    
 | 
			
		||||
.. xbooklink    For information on updating |prod-dc|, see |distcloud-doc|:
 | 
			
		||||
    :ref:`Update Management for Distributed Cloud
 | 
			
		||||
    <update-management-for-distributed-cloud>`.
 | 
			
		||||
 | 
			
		||||
.. _update-orchestration-overview-section-N10031-N10023-N10001:
 | 
			
		||||
 | 
			
		||||
---------------------------------
 | 
			
		||||
Update Orchestration Requirements
 | 
			
		||||
---------------------------------
 | 
			
		||||
 | 
			
		||||
Update orchestration can only be done on a system that meets the following
 | 
			
		||||
conditions:
 | 
			
		||||
 | 
			
		||||
.. _update-orchestration-overview-ul-e1y-t4c-nx:
 | 
			
		||||
 | 
			
		||||
-   The system is clear of alarms (with the exception of alarms for locked
 | 
			
		||||
    hosts, and update applications in progress).
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        When configuring update orchestration, you have the option to ignore
 | 
			
		||||
        alarms with a severity less than management-affecting severity. For
 | 
			
		||||
        more information, see :ref:`Configuring Update Orchestration
 | 
			
		||||
        <configuring-update-orchestration>`.
 | 
			
		||||
 | 
			
		||||
-   All hosts must be unlocked-enabled-available.
 | 
			
		||||
 | 
			
		||||
-   Two controller hosts must be available.
 | 
			
		||||
 | 
			
		||||
-   All storage hosts must be available.
 | 
			
		||||
 | 
			
		||||
-   When installing reboot required updates, there must be spare worker
 | 
			
		||||
    capacity to move hosted application pods off the worker host\(s) being
 | 
			
		||||
    updated such that hosted application services are not impacted.
 | 
			
		||||
 | 
			
		||||
.. _update-orchestration-overview-section-N1009D-N10023-N10001:
 | 
			
		||||
 | 
			
		||||
--------------------------------
 | 
			
		||||
The Update Orchestration Process
 | 
			
		||||
--------------------------------
 | 
			
		||||
 | 
			
		||||
Update orchestration automatically iterates through all hosts on the system and
 | 
			
		||||
installs the applied updates to each host: first the controller hosts, then the
 | 
			
		||||
storage hosts, and finally the worker hosts. During the worker host updating,
 | 
			
		||||
hosted application pod re-locations are managed automatically. The controller
 | 
			
		||||
hosts are always updated serially. The storage hosts and worker hosts can be
 | 
			
		||||
configured to be updated in parallel in order to reduce the overall update
 | 
			
		||||
installation time.
 | 
			
		||||
 | 
			
		||||
Update orchestration can install one or more applied updates at the same time.
 | 
			
		||||
It can also install reboot-required updates or in-service updates or both at
 | 
			
		||||
the same time. Update orchestration only locks and unlocks (that is, reboots)
 | 
			
		||||
a host to install an update if at least one reboot-required update has been
 | 
			
		||||
applied.
 | 
			
		||||
 | 
			
		||||
You first create an update orchestration strategy, or plan, for the automated
 | 
			
		||||
updating procedure. This customizes the update orchestration, using parameters
 | 
			
		||||
to specify:
 | 
			
		||||
 | 
			
		||||
.. _update-orchestration-overview-ul-eyw-fyr-31b:
 | 
			
		||||
 | 
			
		||||
-   the host types to be updated
 | 
			
		||||
 | 
			
		||||
-   whether to update hosts serially or in parallel
 | 
			
		||||
 | 
			
		||||
Based on these parameters, and the state of the hosts, update orchestration
 | 
			
		||||
creates a number of stages for the overall update strategy. Each stage
 | 
			
		||||
generally consists of re-locating hosted application pods, locking hosts,
 | 
			
		||||
installing updates, and unlocking hosts for a subset of the hosts on the
 | 
			
		||||
system.
 | 
			
		||||
 | 
			
		||||
After creating the update orchestration strategy, the user can either apply the
 | 
			
		||||
entire strategy automatically, or manually apply individual stages to control
 | 
			
		||||
and monitor the update progress.
 | 
			
		||||
@@ -1,76 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. utq1552920689344
 | 
			
		||||
.. _update-status-and-lifecycle:
 | 
			
		||||
 | 
			
		||||
===========================
 | 
			
		||||
Update Status and Lifecycle
 | 
			
		||||
===========================
 | 
			
		||||
 | 
			
		||||
|prod| software updates move through different status levels as the updates are
 | 
			
		||||
being applied.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |context|
 | 
			
		||||
 | 
			
		||||
After adding an update (patch) to the storage area you must move it to the
 | 
			
		||||
repository, which manages distribution for the cluster. From there, you can
 | 
			
		||||
install the updates to the hosts that require them.
 | 
			
		||||
 | 
			
		||||
Some of the available updates may be required on controller hosts only, while
 | 
			
		||||
others may be required on worker or storage hosts. Use :command:`sw-patch
 | 
			
		||||
query-hosts` to see which hosts are impacted by the newly applied (or
 | 
			
		||||
removed) updates. You can then use :command:`sw-patch host-install` to update
 | 
			
		||||
the software on individual hosts.
 | 
			
		||||
 | 
			
		||||
To keep track of software update installation, you can use the
 | 
			
		||||
:command:`sw-patch query` command.
 | 
			
		||||
 | 
			
		||||
.. parsed-literal::
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ sudo sw-patch query
 | 
			
		||||
    Patch ID	                Patch State
 | 
			
		||||
    ===========                 ============
 | 
			
		||||
    |pvr|-<nn>.<nn>_PATCH_0001  Applied
 | 
			
		||||
 | 
			
		||||
where <nn>.<nn> in the update filename is the |prod| release number.
 | 
			
		||||
 | 
			
		||||
This shows the 'Patch State' for each of the updates in the storage area:
 | 
			
		||||
 | 
			
		||||
``Available``
 | 
			
		||||
    An update in the *Available* state has been added to the storage area, but
 | 
			
		||||
    is not currently in the repository or installed on the hosts.
 | 
			
		||||
 | 
			
		||||
``Partial-Apply``
 | 
			
		||||
    An update in the *Partial-Apply* state has been added to the software
 | 
			
		||||
    updates repository using the :command:`sw-patch apply` command, but has not
 | 
			
		||||
    been installed on all hosts that require it. It may have been installed on
 | 
			
		||||
    some but not others, or it may not have been installed on any hosts. If any
 | 
			
		||||
    reboot-required update is in a partial state (Partial-Apply or
 | 
			
		||||
    Partial-Remove), you cannot update the software on any given host without
 | 
			
		||||
    first locking it. If, for example, you had one reboot-required update and
 | 
			
		||||
    one in-service update, both in a Partial-Apply state and both applicable to
 | 
			
		||||
    node X, you cannot just install the non-reboot-required update to the
 | 
			
		||||
    unlocked node X.
 | 
			
		||||
 | 
			
		||||
``Applied``
 | 
			
		||||
    An update in the *Applied* state has been installed on all hosts that
 | 
			
		||||
    require it.
 | 
			
		||||
 | 
			
		||||
You can use the :command:`sw-patch query-hosts` command to see which hosts are
 | 
			
		||||
fully updated (Patch Current). This also shows which hosts require
 | 
			
		||||
reboot, either because they are not fully updated, or because they are fully
 | 
			
		||||
updated but not yet rebooted.
 | 
			
		||||
 | 
			
		||||
.. code-block:: none
 | 
			
		||||
 | 
			
		||||
    ~(keystone_admin)]$ sudo sw-patch query-hosts
 | 
			
		||||
 | 
			
		||||
     Hostname      IP Address    Patch Current  Reboot Required  Release  State
 | 
			
		||||
    ============  ==============  =============  ===============  =======  =====
 | 
			
		||||
    worker-0      192.168.204.95       Yes             No          nn.nn   idle
 | 
			
		||||
    worker-1      192.168.204.63       Yes             No          nn.nn   idle
 | 
			
		||||
    worker-2      192.168.204.99       Yes             No          nn.nn   idle
 | 
			
		||||
    worker-3      192.168.204.49       Yes             No          nn.nn   idle
 | 
			
		||||
    controller-0  192.168.204.3        Yes             No          nn.nn   idle
 | 
			
		||||
    controller-1  192.168.204.4        Yes             No          nn.nn   idle
 | 
			
		||||
    storage-0     192.168.204.37       Yes             No          nn.nn   idle
 | 
			
		||||
    storage-1     192.168.204.90       Yes             No          nn.nn   idle
 | 
			
		||||
@@ -1,566 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. btn1592861794542
 | 
			
		||||
.. _upgrading-all-in-one-duplex-or-standard:
 | 
			
		||||
 | 
			
		||||
====================================
 | 
			
		||||
Upgrade All-in-One Duplex / Standard
 | 
			
		||||
====================================
 | 
			
		||||
 | 
			
		||||
You can upgrade the |prod| Duplex or Standard configurations with a new release
 | 
			
		||||
of |prod| software.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |prereq|
 | 
			
		||||
 | 
			
		||||
.. _upgrading-all-in-one-duplex-or-standard-ul-ezb-b11-cx:
 | 
			
		||||
 | 
			
		||||
-   Validate the list of new images with the target release. If you are using a
 | 
			
		||||
    private registry for installs/upgrades, you must populate your private
 | 
			
		||||
    registry with the new images prior to bootstrap and/or patch application.
 | 
			
		||||
 | 
			
		||||
-   Perform a full backup to allow recovery.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
       Back up files in the ``/home/sysadmin`` and ``/root`` directories prior
 | 
			
		||||
       to doing an upgrade. Home directories are not preserved during backup or
 | 
			
		||||
       restore operations, blade replacement, or upgrades.
 | 
			
		||||
 | 
			
		||||
-   The system must be 'patch current'. All updates available for the current
 | 
			
		||||
    release running on the system must be applied, and all patches must be
 | 
			
		||||
    committed. To find and download applicable updates, visit the |dnload-loc|.
 | 
			
		||||
 | 
			
		||||
-   Transfer the new release software load to controller-0 (or onto a USB
 | 
			
		||||
    stick); controller-0 must be active.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        Make sure that the filesystem containing the ``/home/sysadmin``
 | 
			
		||||
        directory has enough space (at least 2GB of free space),
 | 
			
		||||
        otherwise the upgrade may fail. If more space is needed, it is
 | 
			
		||||
        recommended to delete the ``.iso bootimage`` recently imported after
 | 
			
		||||
        running the :command:`load-import` command.
 | 
			
		||||
 | 
			
		||||
-   Transfer the new release software license file to controller-0, (or onto a
 | 
			
		||||
    USB stick).
 | 
			
		||||
 | 
			
		||||
-   Transfer the new release software signature to controller-0 (or onto a USB
 | 
			
		||||
    stick).
 | 
			
		||||
 | 
			
		||||
-   Unlock all hosts.
 | 
			
		||||
 | 
			
		||||
    -   All nodes must be unlocked as the health check prevents the upgrade
 | 
			
		||||
        cannot if there are locked nodes.
 | 
			
		||||
 | 
			
		||||
.. include:: /_includes/manual-image-cleanup-note-b43d78f2ba4a.rest
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    The upgrade procedure includes steps to resolve system health issues.
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
 | 
			
		||||
    Upgrading hosts should be completed within 24 hours to avoid a kubeadm token
 | 
			
		||||
    timeout.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#.  Ensure that controller-0 is the active controller.
 | 
			
		||||
 | 
			
		||||
#.  Install the license file for the release you are upgrading.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system license-install <license_file>
 | 
			
		||||
 | 
			
		||||
    For example,
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system license-install license.lic
 | 
			
		||||
 | 
			
		||||
#.  Import the new release.
 | 
			
		||||
 | 
			
		||||
    #.  Run the :command:`load-import` command on controller-0 to import
 | 
			
		||||
        the new release.
 | 
			
		||||
 | 
			
		||||
        Source ``/etc/platform/openrc``. Also, you can specify either the full
 | 
			
		||||
        file path or relative paths to the ``*.iso`` bootimage file and to the
 | 
			
		||||
        ``*.sig`` bootimage signature file.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            $ source /etc/platform/openrc
 | 
			
		||||
            ~(keystone_admin)]$ system load-import [--local] /home/sysadmin/<bootimage>.iso <bootimage>.sig
 | 
			
		||||
 | 
			
		||||
            +--------------------+-----------+
 | 
			
		||||
            | Property           | Value     |
 | 
			
		||||
            +--------------------+-----------+
 | 
			
		||||
            | id                 | 2         |
 | 
			
		||||
            | state              | importing |
 | 
			
		||||
            | software_version   | nn.nn     |
 | 
			
		||||
            | compatible_version | nn.nn     |
 | 
			
		||||
            | required_patches   |           |
 | 
			
		||||
            +--------------------+-----------+
 | 
			
		||||
 | 
			
		||||
        The :command:`load-import` must be done on controller-0.
 | 
			
		||||
 | 
			
		||||
        (Optional) If ``--local`` is specified, the ISO and sig files are
 | 
			
		||||
        transferred directly from the active controller filesystem to the
 | 
			
		||||
        load directory, otherwise, they are transferred via the API.
 | 
			
		||||
 | 
			
		||||
        .. note::
 | 
			
		||||
 | 
			
		||||
            If ``--local`` is specified, the ISO and sig files are transferred
 | 
			
		||||
            directly from the active controller filesystem to the load directory,
 | 
			
		||||
            if it is not specified, the files are transferred via the API.
 | 
			
		||||
 | 
			
		||||
        .. note::
 | 
			
		||||
            This will take a few minutes to complete.
 | 
			
		||||
 | 
			
		||||
    #.  Check to ensure the load was successfully imported.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system load-list
 | 
			
		||||
            +----+----------+------------------+
 | 
			
		||||
            | id | state    | software_version |
 | 
			
		||||
            +----+----------+------------------+
 | 
			
		||||
            | 1  | active   | nn.nn            |
 | 
			
		||||
            | 2  | imported | nn.nn            |
 | 
			
		||||
            +----+----------+------------------+
 | 
			
		||||
 | 
			
		||||
#.  Apply any required software updates.
 | 
			
		||||
 | 
			
		||||
    The system must be 'patch current'. All software updates related to your
 | 
			
		||||
    current |prod| software release must be uploaded, applied, and installed.
 | 
			
		||||
 | 
			
		||||
    All software updates to the new |prod| release only need to be uploaded
 | 
			
		||||
    and applied. The install of these software updates will occur automatically
 | 
			
		||||
    during the software upgrade procedure as the hosts are reset to load the
 | 
			
		||||
    new release of software.
 | 
			
		||||
 | 
			
		||||
    To find and download applicable updates, visit the |dnload-loc|.
 | 
			
		||||
 | 
			
		||||
    For more information, see :ref:`Manage Software Updates
 | 
			
		||||
    <managing-software-updates>`.
 | 
			
		||||
 | 
			
		||||
#.  Confirm that the system is healthy.
 | 
			
		||||
 | 
			
		||||
    Check the current system health status, resolve any alarms and other issues
 | 
			
		||||
    reported by the :command:`system health-query-upgrade` command, then
 | 
			
		||||
    recheck the system health status to confirm that all **System Health**
 | 
			
		||||
    fields are set to *OK*. For example:
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system health-query-upgrade
 | 
			
		||||
 | 
			
		||||
        System Health:
 | 
			
		||||
        All hosts are provisioned: [OK]
 | 
			
		||||
        All hosts are unlocked/enabled: [OK]
 | 
			
		||||
        All hosts have current configurations: [OK]
 | 
			
		||||
        All hosts are patch current: [OK]
 | 
			
		||||
        Ceph Storage Healthy: [OK]
 | 
			
		||||
        No alarms: [OK]
 | 
			
		||||
        All kubernetes nodes are ready: [OK]
 | 
			
		||||
        All kubernetes control plane pods are ready: [OK]
 | 
			
		||||
        All PodSecurityPolicies are removed: [OK]
 | 
			
		||||
        Required patches are applied: [OK]
 | 
			
		||||
        License valid for upgrade: [OK]
 | 
			
		||||
        No instances running on controller-1: [OK]
 | 
			
		||||
        All kubernetes applications are in a valid state: [OK]
 | 
			
		||||
        Active controller is controller-0: [OK]
 | 
			
		||||
        Disk space requirement: [OK]
 | 
			
		||||
        Boot Device and Root file system Device: [OK]
 | 
			
		||||
 | 
			
		||||
    By default, the upgrade process cannot be run with active alarms present.
 | 
			
		||||
    Use the command :command:`system upgrade-start --force` to force the upgrade
 | 
			
		||||
    process to start and ignore non-management-affecting alarms.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        It is strongly recommended that you clear your system of any and all
 | 
			
		||||
        alarms before doing an upgrade. While the :command:`--force` option is
 | 
			
		||||
        available to run the upgrade, it is a best practice to clear any
 | 
			
		||||
        alarms.
 | 
			
		||||
 | 
			
		||||
#.  Start the upgrade from controller-0.
 | 
			
		||||
 | 
			
		||||
    Make sure that controller-0 is the active controller, and you are logged
 | 
			
		||||
    into controller-0 as **sysadmin** and your present working directory is
 | 
			
		||||
    your home directory.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-start
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | Property     | Value                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | uuid         | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
 | 
			
		||||
        | state        | starting                             |
 | 
			
		||||
        | from_release | nn.nn                                |
 | 
			
		||||
        | to_release   | nn.nn                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
    This will make a copy of the upgrade data onto a |DRBD| file system to be
 | 
			
		||||
    used in the upgrade. Configuration changes are not allowed after this point
 | 
			
		||||
    until the swact to controller-1 is completed.
 | 
			
		||||
 | 
			
		||||
    The following upgrade state applies once this command is executed:
 | 
			
		||||
 | 
			
		||||
    -   ``started``:
 | 
			
		||||
 | 
			
		||||
        -   State entered after :command:`system upgrade-start` completes.
 | 
			
		||||
 | 
			
		||||
        -   Release <nn>.<nn> system data (for example, postgres databases) has
 | 
			
		||||
            been exported to be used in the upgrade.
 | 
			
		||||
 | 
			
		||||
        -   Configuration changes must not be made after this point, until the
 | 
			
		||||
            upgrade is completed.
 | 
			
		||||
 | 
			
		||||
    As part of the upgrade, the upgrade process checks the health of the system
 | 
			
		||||
    and validates that the system is ready for an upgrade.
 | 
			
		||||
 | 
			
		||||
    The upgrade process checks that no alarms are active before starting an
 | 
			
		||||
    upgrade.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
 | 
			
		||||
        Use the command :command:`system upgrade-start --force` to force the
 | 
			
		||||
        upgrade process to start and ignore non-management-affecting alarms.
 | 
			
		||||
        This should **ONLY** be done if you ascertain that these alarms will
 | 
			
		||||
        interfere with the upgrades process.
 | 
			
		||||
 | 
			
		||||
    On systems with Ceph storage, the process also checks that the Ceph cluster
 | 
			
		||||
    is healthy.
 | 
			
		||||
 | 
			
		||||
#.  Upgrade controller-1.
 | 
			
		||||
 | 
			
		||||
    #.  Lock controller-1.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-lock controller-1
 | 
			
		||||
 | 
			
		||||
    #.  Upgrade controller-1.
 | 
			
		||||
 | 
			
		||||
        Controller-1 installs the update and reboots, then performs data
 | 
			
		||||
        migration.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-upgrade controller-1
 | 
			
		||||
 | 
			
		||||
        Wait for controller-1 to reinstall with the load N+1 and becomes
 | 
			
		||||
        **locked-disabled-online** state.
 | 
			
		||||
 | 
			
		||||
        The following data migration states apply when this command is
 | 
			
		||||
        executed:
 | 
			
		||||
 | 
			
		||||
        -   ``data-migration``:
 | 
			
		||||
 | 
			
		||||
            -   State entered when :command:`system host-upgrade controller-1`
 | 
			
		||||
                is executed.
 | 
			
		||||
 | 
			
		||||
            -   System data is being migrated from release N to release N+1.
 | 
			
		||||
 | 
			
		||||
            .. note::
 | 
			
		||||
                The upgrade process will take a minimum of 20 to 30 minutes to
 | 
			
		||||
                complete.
 | 
			
		||||
 | 
			
		||||
                You can view the upgrade progress on controller-1 using the
 | 
			
		||||
                serial console.
 | 
			
		||||
 | 
			
		||||
        -   ``data-migration-complete or upgrading-controllers``:
 | 
			
		||||
 | 
			
		||||
            -   State entered when controller-1 upgrade is complete.
 | 
			
		||||
 | 
			
		||||
            -   System data has been successfully migrated from release <nn>.<nn>
 | 
			
		||||
                to the newer Version.
 | 
			
		||||
 | 
			
		||||
        -   ``data-migration-failed``:
 | 
			
		||||
 | 
			
		||||
            -   State entered if data migration on controller-1 fails.
 | 
			
		||||
 | 
			
		||||
            -   Upgrade must be aborted.
 | 
			
		||||
 | 
			
		||||
            .. note::
 | 
			
		||||
                Review the ``/var/log/sysinv.log`` on the active controller for
 | 
			
		||||
                more details on data migration failure.
 | 
			
		||||
 | 
			
		||||
    #.  Check the upgrade state.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system upgrade-show
 | 
			
		||||
            +--------------+--------------------------------------+
 | 
			
		||||
            | Property     | Value                                |
 | 
			
		||||
            +--------------+--------------------------------------+
 | 
			
		||||
            | uuid         | e7c8f6bc-518c-46d4-ab81-7a59f8f8e64b |
 | 
			
		||||
            | state        | data-migration-complete              |
 | 
			
		||||
            | from_release | nn.nn                                |
 | 
			
		||||
            | to_release   | nn.nn                                |
 | 
			
		||||
            +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
        If the :command:`upgrade-show` status indicates
 | 
			
		||||
        *data-migration-failed*, then there is an issue with the data
 | 
			
		||||
        migration. Check the issue before proceeding to the next step.
 | 
			
		||||
 | 
			
		||||
    #.  Unlock controller-1.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-unlock controller-1
 | 
			
		||||
 | 
			
		||||
        Wait for controller-1 to enter the state *unlocked-enabled*. Wait for
 | 
			
		||||
        the |DRBD| sync **400.001** Services-related alarm to be raised and then
 | 
			
		||||
        cleared.
 | 
			
		||||
 | 
			
		||||
        The **upgrading-controllers** state applies when this command is executed.
 | 
			
		||||
        This state is entered after controller-1 has been upgraded to release nn.nn
 | 
			
		||||
        and data migration is successfully completed.
 | 
			
		||||
 | 
			
		||||
        If the controller transitions to **unlocked-disabled-failed**, check the
 | 
			
		||||
        issue before proceeding to the next step. The alarms may indicate a
 | 
			
		||||
        configuration error. Check the result of the configuration logs on
 | 
			
		||||
        controller-1, (for example, Error logs in
 | 
			
		||||
        controller1:``/var/log/puppet``).
 | 
			
		||||
 | 
			
		||||
#.  Set controller-1 as the active controller. Swact to controller-1.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-swact controller-0
 | 
			
		||||
 | 
			
		||||
    Wait until services have become active on the new active controller-1 before
 | 
			
		||||
    proceeding to the next step. The swact is complete when all services on
 | 
			
		||||
    controller-1 are in the state ``enabled-active``. Use the command ``system
 | 
			
		||||
    servicegroup-list`` to monitor progress.
 | 
			
		||||
 | 
			
		||||
#.  Upgrade controller-0.
 | 
			
		||||
 | 
			
		||||
    #.  Lock controller-0.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-lock controller-0
 | 
			
		||||
 | 
			
		||||
    #.  Upgrade controller-0.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-upgrade controller-0
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
    #.  Unlock controller-0.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-unlock controller-0
 | 
			
		||||
 | 
			
		||||
        Wait until the |DRBD| sync **400.001** Services-related alarm is raised
 | 
			
		||||
        and then cleared before proceeding to the next step.
 | 
			
		||||
 | 
			
		||||
        -   upgrading-hosts:
 | 
			
		||||
 | 
			
		||||
            -   State entered when both controllers are running release nn.nn
 | 
			
		||||
                software.
 | 
			
		||||
 | 
			
		||||
        .. note::
 | 
			
		||||
            |AIO-DX| or Controllers of Standard configurations can be
 | 
			
		||||
            upgraded, using steps 1-9 above.
 | 
			
		||||
 | 
			
		||||
#.  Check the system health to ensure that there are no unexpected alarms.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ fm alarm-list
 | 
			
		||||
 | 
			
		||||
    Clear all alarms unrelated to the upgrade process.
 | 
			
		||||
 | 
			
		||||
#.  If using Ceph a storage backend, upgrade the storage nodes one at a time.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        Proceed to step 13 if no storage/worker node is present.
 | 
			
		||||
 | 
			
		||||
    The storage node must be locked and all OSDs must be down in order to do
 | 
			
		||||
    the upgrade.
 | 
			
		||||
 | 
			
		||||
    #.  Lock storage-0.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-lock storage-0
 | 
			
		||||
 | 
			
		||||
    #.  Verify that the |OSDs| are down after the storage node is locked.
 | 
			
		||||
 | 
			
		||||
        In the Horizon interface, navigate to **Admin** \> **Platform** \>
 | 
			
		||||
        **Storage Overview** to view the status of the |OSDs|.
 | 
			
		||||
 | 
			
		||||
    #.  Upgrade storage-0.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-upgrade storage-0
 | 
			
		||||
 | 
			
		||||
        The upgrade is complete when the node comes online. At that point
 | 
			
		||||
        you can safely unlock the node.
 | 
			
		||||
 | 
			
		||||
        After upgrading a storage node, but before unlocking, there are Ceph
 | 
			
		||||
        synchronization alarms (that appear to be making progress in
 | 
			
		||||
        synching), and there are infrastructure network interface alarms
 | 
			
		||||
        (since the infrastructure network interface configuration has not been
 | 
			
		||||
        applied to the storage node yet, as it has not been unlocked).
 | 
			
		||||
 | 
			
		||||
        Unlock the node as soon as the upgraded storage node comes online.
 | 
			
		||||
 | 
			
		||||
    #.  Unlock storage-0.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-unlock storage-0
 | 
			
		||||
 | 
			
		||||
        Wait for all alarms to clear after the unlock before proceeding to
 | 
			
		||||
        upgrade the next storage host.
 | 
			
		||||
 | 
			
		||||
    #.  Repeat the above steps for each storage host.
 | 
			
		||||
 | 
			
		||||
        .. note::
 | 
			
		||||
            After upgrading the first storage node you can expect alarm
 | 
			
		||||
            **800.003**. The alarm is cleared after all storage nodes are
 | 
			
		||||
            upgraded.
 | 
			
		||||
 | 
			
		||||
#.  Upgrade worker hosts, if any, one at a time.
 | 
			
		||||
 | 
			
		||||
    #.  Lock worker-0.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-lock worker-0
 | 
			
		||||
 | 
			
		||||
    #.  Upgrade worker-0.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-upgrade worker-0
 | 
			
		||||
 | 
			
		||||
        Wait for the host to run the installer, reboot, and go online before
 | 
			
		||||
        unlocking it in the next step.
 | 
			
		||||
 | 
			
		||||
    #.  Unlock worker-0.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system host-unlock worker-0
 | 
			
		||||
 | 
			
		||||
        After the unlock wait for all alarms to clear before proceeding to the
 | 
			
		||||
        next worker host.
 | 
			
		||||
 | 
			
		||||
    #.  Repeat the above steps for each worker host.
 | 
			
		||||
 | 
			
		||||
#.  Set controller-0 as the active controller. Swact to controller-0.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-swact controller-1
 | 
			
		||||
 | 
			
		||||
    Wait until services have become available on the active controller-0 before
 | 
			
		||||
    proceeding to the next step. When all services on controller-0 are in the
 | 
			
		||||
    ``enabled-active`` state, the swact is complete.
 | 
			
		||||
 | 
			
		||||
#.  Activate the upgrade.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-activate
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | Property     | Value                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | uuid         | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
 | 
			
		||||
        | state        | activating                           |
 | 
			
		||||
        | from_release | nn.nn                                |
 | 
			
		||||
        | to_release   | nn.nn                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
    When running the :command:`upgrade-activate` command, new
 | 
			
		||||
    configurations are applied to the controller. 250.001 (**hostname
 | 
			
		||||
    Configuration is out-of-date**) alarms are raised and are cleared as the
 | 
			
		||||
    configuration is applied. The upgrade state goes from ``activating`` to
 | 
			
		||||
    ``activation-complete`` once this is done.
 | 
			
		||||
 | 
			
		||||
    .. only:: partner
 | 
			
		||||
 | 
			
		||||
        .. include:: /_includes/upgrading-all-in-one-duplex-or-standard.rest
 | 
			
		||||
           :start-after: deploymentmanager-begin
 | 
			
		||||
           :end-before: deploymentmanager-end
 | 
			
		||||
 | 
			
		||||
    The following states apply when this command is executed.
 | 
			
		||||
 | 
			
		||||
    ``activation-requested``
 | 
			
		||||
        State entered when :command:`system upgrade-activate` is executed.
 | 
			
		||||
 | 
			
		||||
    ``activating``
 | 
			
		||||
        State entered when the system has started activating the upgrade by applying
 | 
			
		||||
        new configurations to the controller and compute hosts.
 | 
			
		||||
 | 
			
		||||
    ``activating-hosts``
 | 
			
		||||
        State entered when applying host-specific configurations. This state is
 | 
			
		||||
        entered only if needed.
 | 
			
		||||
 | 
			
		||||
    ``activation-complete``
 | 
			
		||||
        State entered when new configurations have been applied to all
 | 
			
		||||
        controller and compute hosts.
 | 
			
		||||
 | 
			
		||||
    #.  Check the status of the upgrade again to see it has reached
 | 
			
		||||
        ``activation-complete``.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system upgrade-show
 | 
			
		||||
            +--------------+--------------------------------------+
 | 
			
		||||
            | Property     | Value                                |
 | 
			
		||||
            +--------------+--------------------------------------+
 | 
			
		||||
            | uuid         | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
 | 
			
		||||
            | state        | activation-complete                  |
 | 
			
		||||
            | from_release | nn.nn                                |
 | 
			
		||||
            | to_release   | nn.nn                                |
 | 
			
		||||
            +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        This can take more than half an hour to complete.
 | 
			
		||||
 | 
			
		||||
    **activation-failed**
 | 
			
		||||
        Check ``/var/log/sysinv.log`` for further information.
 | 
			
		||||
 | 
			
		||||
#.  Complete the upgrade.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-complete
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | Property     | Value                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | uuid         | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
 | 
			
		||||
        | state        | completing                           |
 | 
			
		||||
        | from_release | nn.nn                                |
 | 
			
		||||
        | to_release   | nn.nn                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
#.  Delete the imported load.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system load-list
 | 
			
		||||
        +----+----------+------------------+
 | 
			
		||||
        | id | state    | software_version |
 | 
			
		||||
        +----+----------+------------------+
 | 
			
		||||
        | 1  | imported | nn.nn            |
 | 
			
		||||
        | 2  | active   | nn.nn            |
 | 
			
		||||
        +----+----------+------------------+
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system load-delete 1
 | 
			
		||||
        Deleted load: load 1
 | 
			
		||||
 | 
			
		||||
.. only:: partner
 | 
			
		||||
 | 
			
		||||
    .. include:: /_includes/upgrading-all-in-one-duplex-or-standard.rest
 | 
			
		||||
        :start-after: upgradeDX-begin
 | 
			
		||||
        :end-before: upgradeDX-end
 | 
			
		||||
@@ -1,483 +0,0 @@
 | 
			
		||||
 | 
			
		||||
.. nfq1592854955302
 | 
			
		||||
.. _upgrading-all-in-one-simplex:
 | 
			
		||||
 | 
			
		||||
==========================
 | 
			
		||||
Upgrade All-in-One Simplex
 | 
			
		||||
==========================
 | 
			
		||||
 | 
			
		||||
You can upgrade a |prod| Simplex configuration with a new release of |prod|
 | 
			
		||||
software.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |prereq|
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
.. _upgrading-all-in-one-simplex-ul-ezb-b11-cx:
 | 
			
		||||
 | 
			
		||||
-   Validate the list of new images with the target release. If you are using a
 | 
			
		||||
    private registry for installs/upgrades, you must populate your private
 | 
			
		||||
    registry with the new images prior to bootstrap and/or patch application.
 | 
			
		||||
 | 
			
		||||
-   Perform a full backup to allow recovery.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
 | 
			
		||||
       Back up files in the ``/root`` directory prior to doing an upgrade, the
 | 
			
		||||
       ``/home`` size limit is 2000 MB. Although container image sizes are
 | 
			
		||||
       preserved, ``/root`` directory is not preserved during backup or restore
 | 
			
		||||
       operations, server replacement, or upgrades.
 | 
			
		||||
 | 
			
		||||
       For more details on backup and what is included see :ref:`Back Up System
 | 
			
		||||
       Data <backing-up-starlingx-system-data>`.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
 | 
			
		||||
       The backup and restore function of an upgrade is specific to an |AIO-SX|
 | 
			
		||||
       deployment only.
 | 
			
		||||
 | 
			
		||||
-   Ensure that the following conditions are met:
 | 
			
		||||
 | 
			
		||||
    -   The system is patch current.
 | 
			
		||||
 | 
			
		||||
    -   There should be sufficient free space in ``/opt/platform-backup.``.
 | 
			
		||||
        Remove any unused files if necessary.
 | 
			
		||||
 | 
			
		||||
    -   The new software load has been imported.
 | 
			
		||||
 | 
			
		||||
    -   A valid license file has been installed.
 | 
			
		||||
 | 
			
		||||
-   Transfer the new release software load to controller-0 (or onto a USB
 | 
			
		||||
    stick); controller-0 must be active.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
 | 
			
		||||
        Make sure that the ``/home/sysadmin`` directory has enough space (at
 | 
			
		||||
        least 2GB of free space), otherwise the upgrade may fail once it starts.
 | 
			
		||||
        If more space is needed, it is recommended to delete the ``.iso``
 | 
			
		||||
        bootimage previously imported after the :command:`load-import`
 | 
			
		||||
        command.
 | 
			
		||||
 | 
			
		||||
-   Transfer the new release software license file to controller-0 (or onto a
 | 
			
		||||
    USB stick).
 | 
			
		||||
 | 
			
		||||
-   Transfer the new release software signature to controller-0 (or onto a USB
 | 
			
		||||
    stick).
 | 
			
		||||
 | 
			
		||||
.. include:: /_includes/manual-image-cleanup-note-b43d78f2ba4a.rest
 | 
			
		||||
 | 
			
		||||
.. note::
 | 
			
		||||
    The upgrade procedure includes steps to resolve system health issues.
 | 
			
		||||
 | 
			
		||||
End user container images in ``registry.local`` will be backed up during the
 | 
			
		||||
upgrade process. This only includes images other than |prod| system and
 | 
			
		||||
application images. These images are limited to 5 GB in total size. If the
 | 
			
		||||
system contains more than 5 GB of these images, the upgrade start will fail.
 | 
			
		||||
For more details, see :ref:`Contents of System Backup
 | 
			
		||||
<backing-up-starlingx-system-data-ul-s3t-bz4-kjb>`.
 | 
			
		||||
 | 
			
		||||
.. rubric:: |proc|
 | 
			
		||||
 | 
			
		||||
#.  Source the platform environment.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        $ source /etc/platform/openrc
 | 
			
		||||
        ~(keystone_admin)]$
 | 
			
		||||
 | 
			
		||||
#.  Install the license file for the release you are upgrading to.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system license-install <license_file>
 | 
			
		||||
 | 
			
		||||
    For example,
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system license-install license.lic
 | 
			
		||||
 | 
			
		||||
#.  Import the new release.
 | 
			
		||||
 | 
			
		||||
    #.  Run the :command:`load-import` command on controller-0 to import
 | 
			
		||||
        the new release.
 | 
			
		||||
 | 
			
		||||
        Source ``/etc/platform/openrc``. Also, you can specify either the
 | 
			
		||||
        full file path or relative paths to the ``*.iso`` bootimage file and to
 | 
			
		||||
        the ``*.sig`` bootimage signature file.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            $ source /etc/platform/openrc
 | 
			
		||||
            ~(keystone_admin)]$ system load-import [--local] /home/sysadmin/<bootimage>.iso <bootimage>.sig
 | 
			
		||||
 | 
			
		||||
            +--------------------+-----------+
 | 
			
		||||
            | Property           | Value     |
 | 
			
		||||
            +--------------------+-----------+
 | 
			
		||||
            | id                 | 2         |
 | 
			
		||||
            | state              | importing |
 | 
			
		||||
            | software_version   | nn.nn     |
 | 
			
		||||
            | compatible_version | nn.nn     |
 | 
			
		||||
            | required_patches   |           |
 | 
			
		||||
            +--------------------+-----------+
 | 
			
		||||
 | 
			
		||||
        The :command:`load-import` must be done on controller-0.
 | 
			
		||||
 | 
			
		||||
        (Optional) If ``--local`` is specified, the ISO and sig files are
 | 
			
		||||
        uploaded directly from the active controller, where `<local_iso_file_path>`
 | 
			
		||||
        and `<local_sig_file_path>` are paths on the active controller to load
 | 
			
		||||
        ISO files and sig files respectively.
 | 
			
		||||
 | 
			
		||||
        .. note::
 | 
			
		||||
 | 
			
		||||
            If ``--local`` is specified, the ISO and sig files are transferred
 | 
			
		||||
            directly from the active controller filesystem to the load directory,
 | 
			
		||||
            if it is not specified, the files are transferred via the API.
 | 
			
		||||
 | 
			
		||||
        .. note::
 | 
			
		||||
            This will take a few minutes to complete.
 | 
			
		||||
 | 
			
		||||
    #.  Check to ensure the load was successfully imported.
 | 
			
		||||
 | 
			
		||||
        .. code-block:: none
 | 
			
		||||
 | 
			
		||||
            ~(keystone_admin)]$ system load-list
 | 
			
		||||
            +----+----------+------------------+
 | 
			
		||||
            | id | state    | software_version |
 | 
			
		||||
            +----+----------+------------------+
 | 
			
		||||
            | 1  | active   | nn.nn            |
 | 
			
		||||
            | 2  | imported | nn.nn            |
 | 
			
		||||
            +----+----------+------------------+
 | 
			
		||||
 | 
			
		||||
#.  Apply any required software updates.
 | 
			
		||||
 | 
			
		||||
    The system must be 'patch current'. All software updates related to your
 | 
			
		||||
    current |prod| software release must be uploaded, applied, and installed.
 | 
			
		||||
 | 
			
		||||
    All software updates to the new |prod| release only need to be uploaded
 | 
			
		||||
    and applied. The install of these software updates will occur automatically
 | 
			
		||||
    during the software upgrade procedure as the hosts are reset to load the
 | 
			
		||||
    new release of software.
 | 
			
		||||
 | 
			
		||||
    To find and download applicable updates, visit the |dnload-loc|.
 | 
			
		||||
 | 
			
		||||
    For more information, see :ref:`Manage Software Updates
 | 
			
		||||
    <managing-software-updates>`.
 | 
			
		||||
 | 
			
		||||
#.  Confirm that the system is healthy.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        Do not modify protected filesystem directories before backup.
 | 
			
		||||
 | 
			
		||||
    Check the current system health status, resolve any alarms and other issues
 | 
			
		||||
    reported by the :command:`system health-query-upgrade` command, then
 | 
			
		||||
    recheck the system health status to confirm that all **System Health**
 | 
			
		||||
    fields are set to *OK*.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system health-query-upgrade
 | 
			
		||||
        System Health:
 | 
			
		||||
        All hosts are provisioned: [OK]
 | 
			
		||||
        All hosts are unlocked/enabled: [OK]
 | 
			
		||||
        All hosts have current configurations: [OK]
 | 
			
		||||
        All hosts are patch current: [OK]
 | 
			
		||||
        Ceph Storage Healthy: [OK]
 | 
			
		||||
        No alarms: [OK]
 | 
			
		||||
        All kubernetes nodes are ready: [OK]
 | 
			
		||||
        All kubernetes control plane pods are ready: [OK]
 | 
			
		||||
        All PodSecurityPolicies are removed: [OK]
 | 
			
		||||
        Required patches are applied: [OK]
 | 
			
		||||
        License valid for upgrade: [OK]
 | 
			
		||||
        No instances running on controller-1: [OK]
 | 
			
		||||
        All kubernetes applications are in a valid state: [OK]
 | 
			
		||||
        Active controller is controller-0: [OK]
 | 
			
		||||
        Disk space requirement: [OK]
 | 
			
		||||
        Boot Device and Root file system Device: [OK]
 | 
			
		||||
 | 
			
		||||
    By default, the upgrade process cannot be run with Active Alarms present.
 | 
			
		||||
    However, management affecting alarms can be ignored with the
 | 
			
		||||
    :command:`--force` option with the :command:`system upgrade-start` command
 | 
			
		||||
    to force the upgrade process to start.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        It is strongly recommended that you clear your system of all
 | 
			
		||||
        alarms before doing an upgrade. While the :command:`--force` option is
 | 
			
		||||
        available to run the upgrade, it is a best practice to clear any
 | 
			
		||||
        alarms.
 | 
			
		||||
 | 
			
		||||
#.  Start the upgrade.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-start
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | Property     | Value                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | uuid         | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
 | 
			
		||||
        | state        | starting                             |
 | 
			
		||||
        | from_release | nn.nn                                |
 | 
			
		||||
        | to_release   | nn.nn                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
    This will back up the system data and images to ``/opt/platform-backup.``.
 | 
			
		||||
    ``/opt/platform-backup.`` is preserved when the host is reinstalled. With the
 | 
			
		||||
    platform backup, the size of ``/home/sysadmin`` must be less than 2GB.
 | 
			
		||||
 | 
			
		||||
    This process may take several minutes.
 | 
			
		||||
 | 
			
		||||
    When the upgrade state is upgraded to *started* the process is complete.
 | 
			
		||||
 | 
			
		||||
    Any changes made to the system after this point will be lost when the data
 | 
			
		||||
    is restored.
 | 
			
		||||
 | 
			
		||||
    The following upgrade state applies once this command is executed:
 | 
			
		||||
 | 
			
		||||
    -   ``started``:
 | 
			
		||||
 | 
			
		||||
        -   State entered after :command:`system upgrade-start` completes.
 | 
			
		||||
 | 
			
		||||
        -   Release <nn>.<nn> system data (for example, postgres databases) has
 | 
			
		||||
            been exported to be used in the upgrade.
 | 
			
		||||
 | 
			
		||||
        -   Configuration changes must not be made after this point, until the
 | 
			
		||||
            upgrade is completed.
 | 
			
		||||
 | 
			
		||||
    The upgrade process checks the health of the system and validates that the
 | 
			
		||||
    system is ready for an upgrade.
 | 
			
		||||
 | 
			
		||||
    The upgrade process checks that no alarms are active before starting an
 | 
			
		||||
    upgrade.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
 | 
			
		||||
        Use the command :command:`system upgrade-start --force` to force the
 | 
			
		||||
        upgrades process to start and to ignore management affecting alarms.
 | 
			
		||||
        This should **ONLY** be done if you have ascertained that these alarms
 | 
			
		||||
        will not interfere with the upgrades process.
 | 
			
		||||
 | 
			
		||||
#.  Check the upgrade state.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-show
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | Property     | Value                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | uuid         | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
 | 
			
		||||
        | state        | started                              |
 | 
			
		||||
        | from_release | nn.nn                                |
 | 
			
		||||
        | to_release   | nn.nn                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
    Ensure the upgrade state is *started*. It will take several minutes to
 | 
			
		||||
    transition to the *started* state.
 | 
			
		||||
 | 
			
		||||
#.  (Optional) Copy the upgrade data from the system to an alternate safe
 | 
			
		||||
    location (such as a USB drive or remote server).
 | 
			
		||||
 | 
			
		||||
    The upgrade data is located under ``/opt/platform-backup``. Example file names
 | 
			
		||||
    are:
 | 
			
		||||
 | 
			
		||||
    **lost+found upgrade_data_2020-06-23T033950\_61e5fcd7-a38d-40b0-ab83-8be55b87fee2.tgz**
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ ls /opt/platform-backup/
 | 
			
		||||
 | 
			
		||||
#.  Lock controller-0.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-lock controller-0
 | 
			
		||||
 | 
			
		||||
#.  Upgrade controller-0.
 | 
			
		||||
 | 
			
		||||
    This is the point of no return. All data except ``/opt/platform-backup/``
 | 
			
		||||
    will be erased from the system. This will wipe the ``rootfs`` and reboot the
 | 
			
		||||
    host. The new release must then be manually installed (via network or
 | 
			
		||||
    USB).
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-upgrade controller-0
 | 
			
		||||
        WARNING: THIS OPERATION WILL COMPLETELY ERASE ALL DATA FROM THE SYSTEM.
 | 
			
		||||
        Only proceed once the system data has been copied to another system.
 | 
			
		||||
        Are you absolutely sure you want to continue?  [yes/N]: yes
 | 
			
		||||
 | 
			
		||||
#.  Install the new release of |prod-long| Simplex software via network or USB.
 | 
			
		||||
 | 
			
		||||
#.  Verify and configure IP connectivity. External connectivity is required to
 | 
			
		||||
    run the Ansible upgrade playbook. The |prod-long| boot image will |DHCP| out
 | 
			
		||||
    all interfaces so the server may have obtained an IP address and have
 | 
			
		||||
    external IP connectivity if a |DHCP| server is present in your environment.
 | 
			
		||||
    Verify this using the :command:`ip addr` command. Otherwise, manually
 | 
			
		||||
    configure an IP address and default IP route.
 | 
			
		||||
 | 
			
		||||
#.  Restore the upgrade data.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ ansible-playbook /usr/share/ansible/stx-ansible/playbooks/upgrade_platform.yml
 | 
			
		||||
 | 
			
		||||
    .. only:: starlingx
 | 
			
		||||
 | 
			
		||||
        .. important::
 | 
			
		||||
 | 
			
		||||
            If you are upgrading from r7.0 to r8.0 use the command below instead:
 | 
			
		||||
 | 
			
		||||
            .. code-block:: none
 | 
			
		||||
 | 
			
		||||
                ansible-playbook /usr/share/ansible/stx-ansible/playbooks/upgrade_platform.yml -e "upgrade_mode=old"
 | 
			
		||||
 | 
			
		||||
    .. only:: partner
 | 
			
		||||
 | 
			
		||||
        .. include:: /_includes/upgrading-all-in-one-simplex.rest
 | 
			
		||||
           :start-after: note-upgrade-begin
 | 
			
		||||
           :end-before: note-upgrade-end
 | 
			
		||||
 | 
			
		||||
    Once the host has installed the new load, this will restore the upgrade
 | 
			
		||||
    data and migrate it to the new load.
 | 
			
		||||
 | 
			
		||||
    The playbook can be run locally or remotely and must be provided with the
 | 
			
		||||
    following parameter:
 | 
			
		||||
 | 
			
		||||
    ``ansible_become_pass``
 | 
			
		||||
       The ansible playbook will check ``/home/sysadmin/<hostname\>.yml`` for
 | 
			
		||||
       these user configuration override files for hosts. For example, if
 | 
			
		||||
       running ansible locally, ``/home/sysadmin/localhost.yml``.
 | 
			
		||||
 | 
			
		||||
    By default the playbook will search for the upgrade data file under
 | 
			
		||||
    ``/opt/platform-backup``. If required, use the ``upgrade_data_file``
 | 
			
		||||
    parameter to specify the path to the ``upgrade_data``.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        This playbook does not support replay.
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        This can take more than one hour to complete.
 | 
			
		||||
 | 
			
		||||
    Once the data restoration is complete the upgrade state will be set to
 | 
			
		||||
    *upgrading-hosts*.
 | 
			
		||||
 | 
			
		||||
#.  Check the status of the upgrade.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-show
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | Property     | Value                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | uuid         | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
 | 
			
		||||
        | state        | upgrading-hosts                      |
 | 
			
		||||
        | from_release | nn.nn                                |
 | 
			
		||||
        | to_release   | nn.nn                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
#.  Unlock controller-0.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system host-unlock controller-0
 | 
			
		||||
 | 
			
		||||
    This step is required only for Simplex systems that are not a subcloud.
 | 
			
		||||
 | 
			
		||||
#.  Activate the upgrade.
 | 
			
		||||
 | 
			
		||||
    During the running of the :command:`upgrade-activate` command, new
 | 
			
		||||
    configurations are applied to the controller. 250.001 (**hostname
 | 
			
		||||
    Configuration is out-of-date**) alarms are raised and then cleared as the
 | 
			
		||||
    configuration is applied. The upgrade state goes from *activating* to
 | 
			
		||||
    *activation-complete* once this is done.
 | 
			
		||||
 | 
			
		||||
    .. only:: partner
 | 
			
		||||
 | 
			
		||||
        .. include:: /_includes/upgrading-all-in-one-simplex.rest
 | 
			
		||||
           :start-after: deploymentmanager-begin
 | 
			
		||||
           :end-before: deploymentmanager-end
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-activate
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | Property     | Value                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | uuid         | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
 | 
			
		||||
        | state        | activating                           |
 | 
			
		||||
        | from_release | nn.nn                                |
 | 
			
		||||
        | to_release   | nn.nn                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
    The following states apply when this command is executed.
 | 
			
		||||
 | 
			
		||||
    ``activation-requested``
 | 
			
		||||
        State entered when :command:`system upgrade-activate` is executed.
 | 
			
		||||
 | 
			
		||||
    ``activating``
 | 
			
		||||
        State entered when we have started activating the upgrade by applying
 | 
			
		||||
        new configurations to the controller and compute hosts.
 | 
			
		||||
 | 
			
		||||
    ``activating-hosts``
 | 
			
		||||
        State entered when applying host-specific configurations. This state is
 | 
			
		||||
        entered only if needed.
 | 
			
		||||
 | 
			
		||||
    ``activation-complete``
 | 
			
		||||
        State entered when new configurations have been applied to all
 | 
			
		||||
        controller and compute hosts.
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
    #.  Check the status of the upgrade again to see it has reached
 | 
			
		||||
        ``activation-complete``.
 | 
			
		||||
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-show
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | Property     | Value                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | uuid         | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
 | 
			
		||||
        | state        | activation-complete                  |
 | 
			
		||||
        | from_release | nn.nn                                |
 | 
			
		||||
        | to_release   | nn.nn                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
    .. note::
 | 
			
		||||
        This can take more than half an hour to complete.
 | 
			
		||||
 | 
			
		||||
    **activation-failed**
 | 
			
		||||
        Check ``/var/log/sysinv.log`` for further information.
 | 
			
		||||
 | 
			
		||||
#.  Complete the upgrade.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system upgrade-complete
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | Property     | Value                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
        | uuid         | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
 | 
			
		||||
        | state        | completing                           |
 | 
			
		||||
        | from_release | nn.nn                                |
 | 
			
		||||
        | to_release   | nn.nn                                |
 | 
			
		||||
        +--------------+--------------------------------------+
 | 
			
		||||
 | 
			
		||||
#.  Delete the imported load.
 | 
			
		||||
 | 
			
		||||
    .. code-block:: none
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system load-list
 | 
			
		||||
        +----+----------+------------------+
 | 
			
		||||
        | id | state    | software_version |
 | 
			
		||||
        +----+----------+------------------+
 | 
			
		||||
        | 1  | imported | nn.nn            |
 | 
			
		||||
        | 2  | active   | nn.nn            |
 | 
			
		||||
        +----+----------+------------------+
 | 
			
		||||
 | 
			
		||||
        ~(keystone_admin)]$ system load-delete 1
 | 
			
		||||
        Deleted load: load 1
 | 
			
		||||
 | 
			
		||||
.. only:: partner
 | 
			
		||||
 | 
			
		||||
   .. include:: /_includes/upgrading-all-in-one-simplex.rest
 | 
			
		||||
       :start-after: upgradeAIO-begin
 | 
			
		||||
       :end-before: upgradeAIO-end
 | 
			
		||||
		Reference in New Issue
	