.. bla1593031188931
 | 
						|
.. _orchestration-upgrade-overview:
 | 
						|
 | 
						|
==============================
 | 
						|
Upgrade Orchestration Overview
 | 
						|
==============================
 | 
						|
 | 
						|
Upgrade Orchestration automates much of the upgrade procedure, leaving a few
 | 
						|
manual steps for operator oversight.
 | 
						|
 | 
						|
.. contents:: |minitoc|
 | 
						|
   :local:
 | 
						|
   :depth: 1
 | 
						|
 | 
						|
.. note::
 | 
						|
    Upgrading of |prod-dc| is distinct from upgrading other |prod|
 | 
						|
    configurations.
 | 
						|
    
 | 
						|
.. xbooklink    For information on updating |prod-dc|, see |distcloud-doc|:
 | 
						|
    :ref:`Upgrade Management <upgrade-management-overview>`.
 | 
						|
 | 
						|
.. note::
 | 
						|
 | 
						|
    The upgrade orchestration commands are prefixed with :command:`sw-manager`.
 | 
						|
    To use upgrade orchestration commands, you need administrator privileges.
 | 
						|
    You must log in to the active controller as user **sysadmin** and source the
 | 
						|
    ``/etc/platform/openrc`` script to obtain administrator privileges. Do not use
 | 
						|
    :command:`sudo`.
 | 
						|
 | 
						|
.. code-block:: none
 | 
						|
 | 
						|
    ~(keystone_admin)]$ sw-manager upgrade-strategy --help
 | 
						|
    usage: sw-manager upgrade-strategy [-h]  ...
 | 
						|
    
 | 
						|
    optional arguments:
 | 
						|
      -h, --help  show this help message and exit
 | 
						|
    
 | 
						|
    Software Upgrade Commands:
 | 
						|
      
 | 
						|
        create    Create a strategy
 | 
						|
        delete    Delete a strategy
 | 
						|
        apply     Apply a strategy
 | 
						|
        abort     Abort a strategy
 | 
						|
        show      Show a strategy
 | 
						|
 | 
						|
.. _orchestration-upgrade-overview-section-N10029-N10026-N10001:
 | 
						|
 | 
						|
----------------------------------
 | 
						|
Upgrade Orchestration Requirements
 | 
						|
----------------------------------
 | 
						|
 | 
						|
Upgrade orchestration can only be done on a system that meets the following
 | 
						|
conditions:
 | 
						|
 | 
						|
.. _orchestration-upgrade-overview-ul-blp-gcx-ry:
 | 
						|
 | 
						|
-   The system is clear of alarms (with the exception of the alarm upgrade in
 | 
						|
    progress).
 | 
						|
 | 
						|
-   All hosts must be unlocked, enabled, and available.
 | 
						|
 | 
						|
-   The system is fully redundant (two controller nodes available, at least
 | 
						|
    one complete storage replication group available for systems with Ceph
 | 
						|
    backend).
 | 
						|
 | 
						|
-   An upgrade has been started, and controller-1 has been upgraded and is
 | 
						|
    active.
 | 
						|
 | 
						|
-   No orchestration strategy exists. Patch, upgrade, firmware, kubernetes,
 | 
						|
    and kube rootca are all types of orchestration. An upgrade cannot be
 | 
						|
    orchestrated while another orchestration is in progress.
 | 
						|
 | 
						|
-   Sufficient free capacity or unused worker resources must be available
 | 
						|
    across the cluster. A rough calculation is: 
 | 
						|
    
 | 
						|
    ``Required spare capacity ( %) = (<Number-of-hosts-to-upgrade-in-parallel> / <total-number-of-hosts>) * 100``
 | 
						|
 | 
						|
.. _orchestration-upgrade-overview-section-N10081-N10026-N10001:
 | 
						|
 | 
						|
---------------------------------
 | 
						|
The Upgrade Orchestration Process
 | 
						|
---------------------------------
 | 
						|
 | 
						|
Upgrade orchestration can be initiated after the initial controller host has
 | 
						|
been manual upgraded and returned to a stability state. Upgrade orchestration
 | 
						|
automatically iterates through the remaining hosts, installing the new software
 | 
						|
load on each one: first the other controller host, then the storage hosts, and
 | 
						|
finally the worker hosts. During worker host upgrades, pods are automatically
 | 
						|
moved to alternate worker hosts.
 | 
						|
 | 
						|
You first create an upgrade orchestration strategy, or plan, for the automated
 | 
						|
upgrade procedure. This customizes the upgrade orchestration, using parameters
 | 
						|
to specify:
 | 
						|
 | 
						|
.. _orchestration-upgrade-overview-ul-eyw-fyr-31b:
 | 
						|
 | 
						|
-   the host types to be upgraded
 | 
						|
 | 
						|
-   whether to upgrade hosts serially or in parallel
 | 
						|
 | 
						|
Based on these parameters, and the state of the hosts, upgrade orchestration
 | 
						|
creates a number of stages for the overall upgrade strategy. Each stage
 | 
						|
generally consists of moving pods, locking hosts, installing upgrades, and
 | 
						|
unlocking hosts for a subset of the hosts on the system.
 | 
						|
 | 
						|
After creating the upgrade orchestration strategy, the you can either apply the
 | 
						|
entire strategy automatically, or apply individual stages to control and monitor
 | 
						|
their progress manually.
 | 
						|
 | 
						|
Update and upgrade orchestration are mutually exclusive; they perform
 | 
						|
conflicting operations. Only a single strategy (sw-patch or sw-upgrade) is
 | 
						|
allowed to exist at a time. If you need to update during an upgrade, you can
 | 
						|
abort/delete the sw-upgrade strategy, and then create and apply a sw-patch
 | 
						|
strategy before going back to the upgrade.
 | 
						|
 | 
						|
Some stages of the upgrade could take a significant amount of time (hours).
 | 
						|
For example, after upgrading a storage host, re-syncing the OSD data could take
 | 
						|
30 minutes per TB (assuming 500MB/s sync rate, which is about half of a 10G
 | 
						|
infrastructure link).
 | 
						|
 | 
						|
.. _orchestration-upgrade-overview-section-N10101-N10026-N10001:
 | 
						|
 | 
						|
------------------------------
 | 
						|
Upgrade Orchestration Workflow
 | 
						|
------------------------------
 | 
						|
 | 
						|
The Upgrade Orchestration procedure has several major parts:
 | 
						|
 | 
						|
.. _orchestration-upgrade-overview-ul-r1k-wzj-wy:
 | 
						|
 | 
						|
-   Manually upgrade controller-1.
 | 
						|
 | 
						|
-   Orchestrate the automatic upgrade of the remaining controller, all the
 | 
						|
    storage nodes, and all the worker nodes.
 | 
						|
 | 
						|