Test Plan for NSXv plugin v2.0.0
|
|
================================
|
|
|
|
************
|
|
Introduction
|
|
************
|
|
|
|
Purpose
|
|
=======
|
|
|
|
Main purpose of this document is intended to describe Quality Assurance
|
|
activities, required to insure that Fuel plugin for VMware NSXv driver is
|
|
ready for production. The project will be able to offer VMware NSXv
|
|
integration functionality with MOS. The scope of this plan defines the
|
|
following objectives:
|
|
|
|
* Identify testing activities;
|
|
* Outline testing approach, test types, test cycle that will be used;
|
|
* List of metrics and deliverable elements;
|
|
* List of items for testing and out of testing scope;
|
|
* Detect exit criteria in testing purposes;
|
|
* Describe test environment.
|
|
|
|
Scope
|
|
=====
|
|
|
|
Fuel NSXv plugin includes NSX plugin for Neutron which is developed by
|
|
third party. This test plan covers a full functionality of Fuel NSXv plugin,
|
|
include basic scenarios related with NSXv Neutron plugin.
|
|
|
|
Following test types should be provided:
|
|
|
|
* Smoke/BVT tests
|
|
* Integration tests
|
|
* System tests
|
|
* Destructive tests
|
|
* GUI tests
|
|
|
|
Performance testing will be executed on the scale lab and a custom set of
|
|
rally scenarios must be run with NSXv environment. Configuration, environment
|
|
and scenarios for performance/scale testing should be determine separately.
|
|
|
|
Intended Audience
|
|
=================
|
|
|
|
This document is intended for project team staff (QA and Dev engineers and
|
|
managers) and all other persons who are interested in testing results.
|
|
|
|
Limitation
|
|
==========
|
|
|
|
Plugin (or its components) has the following limitations:
|
|
|
|
* VMware NSXv plugin can be enabled only with Neutron tunnel segmentation.
|
|
* Environment with enabled VMware NSXv plugin can't contains compute nodes.
|
|
* Only VMware NSX Manager Virtual Appliance 6.1.4 or later is supported.
|
|
|
|
Product compatibility matrix
|
|
============================
|
|
|
|
.. list-table:: product compatibility matrix
|
|
:widths: 15 10 30
|
|
:header-rows: 1
|
|
|
|
* - Requirement
|
|
- Version
|
|
- Comment
|
|
* - MOS
|
|
- 8.0
|
|
-
|
|
* - OpenStack release
|
|
- Liberty with Ubuntu 14.04
|
|
-
|
|
* - vSphere
|
|
- 5.5 and 6.0
|
|
-
|
|
* - NSXv
|
|
- 6.2.0 and 6.1.4 (not tested)
|
|
-
|
|
|
|
**************************************
|
|
Evaluation Mission and Test Motivation
|
|
**************************************
|
|
|
|
Project main goal is to build a MOS plugin that integrates a Neutron VMware
|
|
NSX plugin. This will allow to use Neutron for networking in vmware-related
|
|
environments. The plugin must be compatible with the version 8.0 of Mirantis
|
|
OpenStack and should be tested with software/hardware described in
|
|
`product compatibility matrix`_.
|
|
|
|
See the VMware NSX Plugin specification for more details.
|
|
|
|
Evaluation mission
|
|
==================
|
|
|
|
* Find important problems with integration of Neutron VMware NSX plugin.
|
|
* Verify a specification.
|
|
* Provide tests for maintenance update.
|
|
* Lab environment deployment.
|
|
* Deploy MOS with developed plugin installed.
|
|
* Create and run specific tests for plugin/deployment.
|
|
* Documentation.
|
|
|
|
*****************
|
|
Target Test Items
|
|
*****************
|
|
|
|
* Install/uninstall Fuel NSXv plugin
|
|
* Deploy Cluster with Fuel NSXv plugin by Fuel
|
|
* Roles of nodes
|
|
* controller
|
|
* mongo
|
|
* compute-vmware
|
|
* cinder-vmware
|
|
* Hypervisors:
|
|
* Qemu+Vcenter
|
|
* Storage:
|
|
* Ceph
|
|
* Cinder
|
|
* VMWare vCenter/ESXi datastore for images
|
|
* Network
|
|
* Neutron with tunnel segmentation
|
|
* HA + Neutron
|
|
* Additional components
|
|
* Ceilometer
|
|
* Health Check
|
|
* Upgrade master node
|
|
* MOS and VMware-NSX plugin
|
|
* Computes(Nova)
|
|
* Launch and manage instances
|
|
* Launch instances in batch
|
|
* Networks (Neutron)
|
|
* Create and manage public and private networks.
|
|
* Create and manage routers.
|
|
* Port binding / disabling
|
|
* Security groups
|
|
* Assign vNIC to a VM
|
|
* Connection between instances
|
|
* Horizon
|
|
* Create and manage projects
|
|
* Glance
|
|
* Create and manage images
|
|
* GUI
|
|
* Fuel UI
|
|
* CLI
|
|
* Fuel CLI
|
|
|
|
*************
|
|
Test approach
|
|
*************
|
|
|
|
The project test approach consists of Smoke, Integration, System, Regression
|
|
Failover and Acceptance test levels.
|
|
|
|
**Smoke testing**
|
|
|
|
The goal of smoke testing is to ensure that the most critical features of Fuel
|
|
VMware NSXv plugin work after new build delivery. Smoke tests will be used by
|
|
QA to accept software builds from Development team.
|
|
|
|
**Integration and System testing**
|
|
|
|
The goal of integration and system testing is to ensure that new or modified
|
|
components of Fuel and MOS work effectively with Fuel VMware NSXv plugin
|
|
without gaps in data flow.
|
|
|
|
**Regression testing**
|
|
|
|
The goal of regression testing is to verify that key features of Fuel VMware
|
|
NSXv plugin are not affected by any changes performed during preparation to
|
|
release (includes defects fixing, new features introduction and possible
|
|
updates).
|
|
|
|
**Failover testing**
|
|
|
|
Failover and recovery testing ensures that the target-of-test can successfully
|
|
failover and recover from a variety of hardware, software, or network
|
|
malfunctions with undue loss of data or data integrity.
|
|
|
|
**Acceptance testing**
|
|
|
|
The goal of acceptance testing is to ensure that Fuel VMware NSXv plugin has
|
|
reached a level of stability that meets requirements and acceptance criteria.
|
|
|
|
|
|
***********************
|
|
Entry and exit criteria
|
|
***********************
|
|
|
|
Criteria for test process starting
|
|
==================================
|
|
|
|
Before test process can be started it is needed to make some preparation
|
|
actions - to execute important preconditions. The following steps must be
|
|
executed successfully for starting test phase:
|
|
|
|
* all project requirements are reviewed and confirmed;
|
|
* implementation of testing features has finished (a new build is ready for testing);
|
|
* implementation code is stored in GIT;
|
|
* test environment is prepared with correct configuration, installed all needed software, hardware;
|
|
* test environment contains the last delivered build for testing;
|
|
* test plan is ready and confirmed internally;
|
|
* implementation of manual tests and autotests (if any) has finished.
|
|
|
|
Feature exit criteria
|
|
=====================
|
|
|
|
Testing of a feature can be finished when:
|
|
|
|
* All planned tests (prepared before) for the feature are executed; no defects are found during this run;
|
|
* All planned tests for the feature are executed; defects found during this run are verified or confirmed to be acceptable (known issues);
|
|
* The time for testing of that feature according to the project plan has run out and Project Manager confirms that no changes to the schedule are possible.
|
|
|
|
Suspension and resumption criteria
|
|
==================================
|
|
|
|
Testing of a particular feature is suspended if there is a blocking issue
|
|
which prevents tests execution. Blocking issue can be one of the following:
|
|
|
|
* Testing environment for the feature is not ready
|
|
* Testing environment is unavailable due to failure
|
|
* Feature has a blocking defect, which prevents further usage of this feature and there is no workaround available
|
|
* CI tests fail
|
|
|
|
************
|
|
Deliverables
|
|
************
|
|
|
|
List of deliverables
|
|
====================
|
|
|
|
Project testing activities are to be resulted in the following reporting documents:
|
|
|
|
* Test plan
|
|
* Test report
|
|
* Automated test cases
|
|
|
|
Acceptance criteria
|
|
===================
|
|
|
|
* All acceptance criteria for user stories are met.
|
|
* All test cases are executed. BVT tests are passed
|
|
* Critical and high issues are fixed
|
|
* All required documents are delivered
|
|
* Release notes including a report on the known errors of that release
|