OpenStack-Ansible Bug Triage
What is a bug triage
"Bug triage is a process where tracker issues are screened and prioritised. Triage should help ensure we appropriately manage all reported issues - bugs as well as improvements and feature requests." (Source: Moodle bug triage)
Reported bugs need confirmation, prioritization, and ensure they do not go stale. If you care about OpenStack stability but are not wanting to actively develop the roles and playbooks used within the OpenStack-Ansible project, consider contributing in the area of bug triage.
The bug triage practices in OpenStack-Ansible are based on the OpenStack Bug Triage Documentation and on the Nova Bug triage page.
Bug classification
The Status of a bug is one of the following:
- New - The bug was just created.
- Incomplete - The bug is waiting on input from the reporter.
- Confirmed - The bug was reproduced or confirmed as a genuine bug.
- Triaged - The bug comments contain a full analysis on how to properly fix the issue.
- In Progress - Work on the fix is in progress and the bug has an assignee.
- Fix Committed - The branch containing the fix was merged into the master branch.
- Fix Released - The fix is included in the proposed branch, a past milestone or a past release.
- Invalid - This is not a bug.
- Opinion - This is a valid issue, but it is an opinion of the reporter.
- Won't Fix - This is a valid issue, but we do not intend to fix that.
The Importance of a bug is one of the following:
- Critical - The bug can take down infrastructures, or gates are blocked. Handle as soon as possible.
- High - Schedule to be fixed soon.
- Medium - Fix when convenient, or schedule to fix later.
- Low - Fix when convenient.
- Wishlist - Not a bug. It is an enhancement or a new feature.
- Undecided - Not decided yet. It might need more discussion.
Bug triage meeting duties
If the bug description is incomplete, or the report is lacking the information necessary to reproduce the issue, ask the reporter to provide missing information, and set the bug status to Incomplete
If the bug report contains enough information and you can reproduce it (or it looks valid), then you should set its status to Confirmed.
If the bug has security implications, set the security flag (under "This report is public" on the top right)
If the bug affects a specific area covered by an official tag, you should set the tag. For example, if the bug is likely to be quite easy to solve, add the low-hanging-fruit tag.
The bug triage meeting is probably a good time for people with bug supervisors rights to also prioritize bugs per importance (on top of classifying them on status).
Bug skimming duty
To help triaging bugs, one person of the bug team can be on "bug skimming duty".
- Q
-
What is the goal of the bug skimming duty?
- A
-
Bug skimming duty reduces the amount of work other developers have to spend to do a proper root cause analysis (and later fix) of bug reports. For this, close the obviously invalid bug reports, confirm the obviously valid bug reports, ask questions if things are unclear.
- Q
-
Do I need to prove that a bug report is valid/invalid before I can set it to Confirmed/Invalid ?
- A
-
No. Sometimes it is not even possible because you do not have the resources. Looking at the code and tests often enables you to make an educated guess. Citing your sources in a comment helps the discussion.
- Q
-
What is the best status to close a bug report if its issue cannot be reproduced?
- A
-
Definitively Invalid. The status Incomplete is an open state and means that more information is necessary.
- Q
-
How do I handle open bug reports which are Incomplete for too long?
- A
-
If it is in this state for more than 30 days and no answers to the open questions are given, close it with Won't Fix.
- Q
-
How do I handle dependencies to other bugs or TBD features in other projects? For example, I can fix a bug in OpenStack-Ansible but I need that a feature in Compute (nova) gets implemented before.
- A
-
Leave a comment in the OpenStack-Ansible bug report which explains this dependency and leave a link to the blueprint or bug report of the other project you depend on.
- Q
-
Do I have to double-check bug reports which are New and have an assignee?
- A
-
Usually not. This bug report has an inconsistent state though. If a bug report has an assignee, it should be In Progress and have an importance set.
Bug skimming duty weekly checklist
Prioritize or reprioritize OpenStack-Ansible confirmed bugs.
Move year old wishlist bugs to Opinion/Wishlist to remove clutter. You can use the following message:
This wishlist bug has been open a year without any activity. I am moving this to "Opinion / Wishlist". This is an easily-obtainable queue of older requests. This bug can be reopened (set back to "New") if someone decides to work on this.
Move bugs that can not be reproduced to an invalid state if they are unmodified for more than a month.
Send an email to the openstack-dev list with the list of bugs to triage during the week. A new bug marked as Critical or High must be treated in priority.