Cycle Highligts original deadline was the same as Feature Freeze date. This caused extra burden to PTLs as while they were reviewing the last patches at FF, they also needed to write the highligts at the same time. This patch postpones one week the Cycle Highlights task so that the deadline indicates more that is needed AFTER the projects feature freeze, but still gives the time to Marketing team to process the cycle highligts. Note that the best is to collect the Cycle Highlights in advance as much and as soon as possible, because for Marketing team perspective having an incomplete list of highlights is better than waiting until a complete list can be constructed. Change-Id: Ibe8f0faebcce480bac79a789fb689112038b48c8
6.1 KiB
2023.1 Antelope Release Schedule
Note
Deadlines are generally the Thursday of the week on which they are noted below. Exceptions to this policy will be explicitly mentioned in the event description.
05 October 2022 - 22 March 2023 (24 weeks)
Cross-project events
2023.1 Antelope Project Team Gathering (PTG)
A Virtual PTG will be held during this week (October 17-21, 2022). The Project Teams Gathering provides an opportunity for teams to collaborate and plan, and discuss requirements for future releases.
Antelope-1 milestone
16 November, 2022 is the Antelope-1 milestone. See project-specific notes for relevant deadlines.
Zed Cycle-Trailing Release Deadline
All projects following the cycle-trailing release model must release their Zed deliverables by 14 December, 2022.
Antelope-2 milestone
04 January, 2023 is the Antelope-2 milestone. See project-specific notes for relevant deadlines.
Membership Freeze
Projects must participate in at least two milestones in order to be considered part of the release. Projects made official after the second milestone, or which fail to produce milestone releases for at least one of the first and second milestones as well as the third milestone, are therefore not considered part of the release for the cycle. This does not apply to cycle-trailing packaging / lifecycle management projects.
Extra-ATC freeze
All contributions to OpenStack are valuable, but some are not expressed as Gerrit code changes. That allow teams to list active contributors to their projects and who do not have a code contribution this cycle, and therefore won't automatically be considered an Active Technical Contributor and allowed to vote. This is done by adding extra-atcs to https://opendev.org/openstack/governance/src/branch/master/reference/projects.yaml before the Extra-ATC freeze on 01 February, 2023.
Final release for non-client libraries
Libraries that are not client libraries (Oslo and others) should issue their final release during this week. That allows to give time for last-minute changes before feature freeze.
Antelope-3 milestone
15 February, 2023 is the Antelope-3 milestone. See project-specific notes for relevant deadlines.
Feature freeze
The Antelope-3 milestone marks feature freeze for projects following the release:cycle-with-rc model. No featureful patch should be landed after this point. Exceptions may be granted by the project PTL.
Final release for client libraries
Client libraries should issue their final release during this week, to match feature freeze.
Soft StringFreeze
You are no longer allowed to accept proposed changes containing modifications in user-facing strings. Such changes should be rejected by the review team and postponed until the next series development opens (which should happen when RC1 is published).
Requirements freeze
After the Antelope-3 milestone, only critical requirements and constraints changes will be allowed. Freezing our requirements list gives packagers downstream an opportunity to catch up and prepare packages for everything necessary for distributions of the upcoming release. The requirements remain frozen until the stable branches are created, with the release candidates.
RC1 target week
The week of 27 February, 2023 is the target date for projects following the release:cycle-with-rc model to issue their first release candidate.
Hard StringFreeze
This happens when the RC1 for the project is tagged. At this point, ideally no strings are changed (or added, or removed), to give translators time to finish up their efforts.
Final RCs and intermediary releases
The week of 13th - 17th March, 2023 is the last week to issue release candidates or intermediary releases before release week. During release week, only final-release-critical releases will be accepted (at the discretion of the release team).
Antelope release
The Antelope coordinated release will happen on Wednesday, 22 March, 2023.
Cycle Highlights
Cycle highlights need to be added to the release deliverables after the feature freeze to be included in any marketing release messaging. Highlights may be added after this point, but they will likely only be useful for historical purposes.
See the Project Team Guide for more details and instructions on adding these highlights.